DocketNumber: No. 07 54 03
Citation Numbers: 1995 Conn. Super. Ct. 14177
Judges: STANLEY, J.
Filed Date: 12/18/1995
Status: Non-Precedential
Modified Date: 4/17/2021
On or about May 27, 1992, the principal and the surety executed their labor and material payment bond covering the East Haddam High School project. On or about March 9, 1993, the principal and the plaintiff entered into a written contract for the plaintiff to provide labor and materials for the consideration of $13,700.00. Thereafter, on September 20, 1993 and September 22, 1993, the principal and the plaintiff entered into two written change orders for the additional consideration of $6,500.00 and $25,500.00, respectively. The plaintiff has received payments from the principal in the amount of $30,646.00, leaving a balance due and owing of $15,054.00, which the principal and the surety have refused and neglected to pay.
On August 8, 1995 and August 12, 1995, the surety and principal, respectively, each filed a motion to dismiss the plaintiff's complaint and memorandums of law in support thereof. In response, on August 11, 1995 and August 17, 1995, the plaintiff filed memorandums of law in opposition to the defendants' motions to dismiss. Thereafter, on August 28, 1995, the plaintiff filed a supplemental memorandum of law in opposition to the surety's motion to dismiss and, on September 28, 1995, the principal filed a supplemental memorandum of law in support of its motion to dismiss.
A motion to dismiss is the proper vehicle by which to challenge the court's jurisdiction over the subject matter in a particular case. Practice Book § 142. Subject matter jurisdiction, which cannot be waived or conferred by consent;Serrani v. Board of Ethics,
The defendants argue that the court lacks subject matter jurisdiction over the present matter, because the plaintiff has failed to comply with Practice Book § 185, which requires that the notice mandated under General Statutes §
Practice Book § 185, which applies to payment bonds on public projects; Valley Oil Co. v. Barry,
Whenever in an action of tort or upon a statute the plaintiff is compelled to allege the giving of a notice required by statute, he shall either recite the same in his complaint or annex a copy thereto.
Additionally, General Statutes §
Any person who performed work or supplied materials for which a requisition was submitted to, or for which an estimate was prepared by, the awarding authority and who does not receive full payment for such work or materials within sixty days of the applicable payment date provided for in subsection (a) of section
49-41a , or any person who supplied materials or performed subcontracting work not included on a requisition or estimate who has not received full payment for such materials or work within sixty days after the date such materials were supplied or CT Page 14179 such work was performed, may enforce his right to payment under the bond by serving a notice of claim on the surety that issued the bond and a copy of such notice to the contractor named as principal in the bond within one hundred eighty days of the applicable payment date provided for in subsection (a) of section49-41a , or, in the case of a person supplying materials or performing subcontracting work not included on a requisition or estimate, within one hundred eighty days after the date such materials were supplied or such work was performed.
General Statutes §
Where, as here, "the language of the statute is clear and unambiguous, the courts cannot, by construction, read into statutes provisions which are not clearly stated." (Citations omitted; internal quotation marks omitted.) Farmers MechanicsSavings Bank v. Garofalo,
General Statutes §
The subcontractor's obligation to give notice to the general contractor of its claim on a payment bond, even if the subcontractor and the general contractor have a direct contractual relationship, was added by an amendment to the statute in 1987. Public Acts 1987, No. 87-345, § 2.
Accordingly, the court finds unpersuasive the plaintiff's argument that General Statutes §
Any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing the payment bond shall have a right of action upon the payment bond upon giving written notice of claim as provided in this section.
However, the court agrees with the defendants that this language is meant to include second-tier subcontractors and suppliers, rather than to exclude first-tier subcontractors and suppliers from the statute's notice requirements, because the statute unambiguously provides that:
any person . . . who has not received full payment . . . may enforce his right to payment under the bond by serving a notice of claim on the surety that issued the bond and a copy of such notice to the contractor named as principal in the bond . . . .
Further, while the Okee court held that a subcontractor may sue on a surety bond despite its failure to comply precisely with all of the notice requirements of General Statutes §
In the present case, it is undisputed that the plaintiff neither recited the notice mandated under General Statutes §
Accordingly, the court finds that the defendants' motions to dismiss ought to be, and are, hereby granted.
BY THE COURT:
STANLEY, J.