DocketNumber: No. CV93-0704020S
Citation Numbers: 1996 Conn. Super. Ct. 4213, 17 Conn. L. Rptr. 173
Judges: CORRADINO, J.
Filed Date: 5/8/1996
Status: Non-Precedential
Modified Date: 4/17/2021
On or about September 4, 1990 Stack entered into a contract with the plaintiff, Ten Hoeve Bros., Inc. ("Ten Hoeve") whereby Stack was able to purchase materials from Ten Hoeve on an open account. Among the materials sold to Stack on this open account were materials to be used by Stack at the Project. Stack failed to pay for $24,301.74 worth of materials and equipment it had purchased from Ten Hoeve for use at the Project.
On or about June 29, 1992, Ann Del Mastro, Ten Hoeve's Credit Manager, gave oral and written notice to Raymond Miller of the City's Public Works Department that Stack had failed to pay for $24,301.74 worth of materials and equipment used by Stack at the Project and requested payment from the city.
The City refused to pay Ten Hoeve for the materials used by Stack at the Project, even though purchase order No. 111264 had a $99,547.74 balance when it received Del Mastro's letter on July 1, 1992.
At least $20,000 remained in purchase order No. 111264 until February, 1993. This action was commenced on April 7, 1993. The CT Page 4213-A plaintiff seeks partial summary judgment on the first count of its Amended Complaint (Equitable Lien). The defendant city of Hartford has filed a cross motion for summary judgment as to this count and also as to the seventh and eighth counts of the complaint. The rules regarding motions for summary judgment are well-known. The dispute between the parties is not so much a factual as a legal dispute.
1.
I believe the defendant City should prevail on its motion for summary judgment as to counts seven and count eight.
Count seven of the amended complaint alleges the city breached its statutory duty (§
The eighth count must similarly fail. In that count the plaintiff claims the city was negligent since it failed to ensure that the general contractor secured a payment bond. There can be no cause of action. For negligence without a duty and fault in the performance of that duty. As just indicated no such duty was owed to the plaintiff by the city in the procurement of the payment bond.
2.
The plaintiff has brought an equitable lien action based on and directed to the fact that at the time it notified the city that Stack had not paid the plaintiff, funds existed in a purchase order created by the city so that Stack could complete the project.
Equitable liens are well-known to the courts though their use and thus litigation surrounding them has declined over the years with the creation of statutory liens of various sorts. Such liens are generally discussed in The Law of Restitution. Palmer Vol. I, § 1.5 (1978), Pomeroy's Equity Jurisprudence, Vol. I, § 165 et seq., 51 Am.Jur.2d § 22 et seq., Restatement of Restitution, § 161; an ALR article deals with a topic related to the issue now before the court, "Building and Construction Contracts: Contractor's Equitable Lien Upon Percentage of Funds Withheld by Contractee or Lender", 54 A.L.R. 3d 848 (1973). Connecticut courts have recognized the concept of equitable liens, Witaker v. Williams,
An equitable lien differs from a so-called common law lien because the latter lien involves the right to retain property until a debt or demand due the party retaining the property is satisfied; under an equitable lien possession remains with the debtor or the person against whom the demand is made; Forster v. Thornton,
An equitable lien can be based on an express or implied contract but as one case said: "The trend of modern decisions is to hold that in the absence of an express contract, a lien based upon the fundamental maxims of equity may be implied and declared by a court of equity out of general considerations of right and justice as applied to the relationship of the parties and the circumstances of their dealing", Calaurcio v. Levson, et al.,
As the above referenced ALR article indicates equitable lien doctrine has been applied in litigation by various parties arising out of disputes over various claims for failure to pay under construction contracts. There is authority for allowing an equitable lien to suppliers in factual situations similar to the one now before the court. In the case of Active Fire SprinklersCorp. v. US Postal Service,
In Penninsulcer Supply Co. v. CB Day Realty,
It could be argued that whatever the general law of equitable liens might be an equitable lien should not be permitted here because this plaintiff as a supplier of materials would have been protected in its claim if a bond had been filed pursuant to Section
The plaintiff here does not base its claim on §
All of this is especially so in light of the fact that our payment bond statute relates only to the creation of a remedy for subcontractors as against sureties. Apart from the question of governmental immunity why should anything in the §
Neither can it be said that if an equitable lien, such as the one proposed here, could be placed against property of the state or its subdivision §§
Our payment bond statute is modeled on the Federal Miller Act, 40 U.S.C. § 270a-270f. When the Miller Act was created it was deemed necessary because subcontractors were unable to assert liens against government property due to governmental immunity, U.S. v.Ansonia Brass Copper Co.,
Connecticut's Supreme Court has noted that our payment bond statute was modelled on the Miller Act and at least in interpreting §
As noted in Active Fire Sprinkler Corp. v. U.S. PostalService, supra an equitable lien filed by a supplier against a "Contract Balance" fund was permitted despite the existence of the federal payment bond statute. The Active Fire Sprinkler Corp., is not distinguishable from the case now before the court at least on the basis of a different factual scenario regarding the federal payment bond statute and the situation regarding the failure to procure a payment bond in this case. In fact arguably the ActiveFire Sprinkler case presents a stronger case for denying an CT Page 4213-F equitable lien to a subcontractor than the facts here. In ActiveFire Sprinkler a Miller Act payment bond had been secured for the job but a district court judge had held that the plaintiff subcontractor could not intervene in the bond action since it had failed to sue timely on the bond. The Miller Act requires suit must be brought by suppliers within one year of delivering materials to the job,
But it must be said that the mere fact that certain federal or state cases have permitted an equitable lien to suppliers in certain construction contract cases and that the Federal payment bond statute has been held not to bar such a common law remedy does not mean that our state should recognize this remedy. Nor does it mean that even if it does that the remedy should be applied against an owner that is a government agency the state or its subdivisions. It certainly does not mean that under the facts of this case that this lien action should prevail.
The previously mentioned article on "Liens" in 51 Am.Jur.2d at sections 22 et seq. pp. 160 et seq. makes clear as several of the cases cited by the defendant do also that the various states have very different views about the equitable lien remedy. Some states do not recognize it at all, other states put severe limitations upon it and require there to be an underlying debt between the supplier and the owner or imply that there must be an express or implied contract providing for the placement of such a lien. On the other hand some courts like the Florida courts and federal courts use very broad language to justify the placing of such liens in a situation like the one now before the court. I've cited some of those cases, they use language about unjust enrichment and simple fairness. "Unjust enrichment" is a vague and pliable term, however, and in deciding whether an equitable lien should be allowed the particular facts of a case have to be examined and the effects of a decision allowing such a lien in a particular industry. The court will proceed to do that not only to determine whether the concept of equitable liens should be recognized generally but also in terms of whether such a lien should be permitted here.
The facts and circumstances of this case are not particularly unusual. The owner of a property site has to have construction CT Page 4213-G work of some type performed. The owner hires a general contractor who in turn hires subcontractors and various subcontractors and suppliers and materialmen perform work at the site or deliver suppliers and materials which are used to complete the job. The owner only dealt directly with the general and itself has no contractural relationship with subcontractors or suppliers. The owner makes periodic payments to the general but for some reason falls behind in the se payments or gets into financial difficulty and cannot complete the job. Subcontractors or suppliers can protect themselves by a mechanics lien; when a government job is involved a payment bond can be secured. Absent such statutory remedies the subcontractors or suppliers may have a problem in collecting for their labor or material from the owner. It's said there's no privity of contract — a magic word dictating no recovery should be allowed. In the ordinary case where a stranger puts improvements on land without consent of the owner it is easy to see why such a rule should prevail. The opportunity for an owner to be taken advantage where there is no contractural agreement is obvious. But the equity courts have made exceptions to this general rule where the circumstances of a case would make it unfair to apply such a rule. A claim is allowed against the owner for example when the owner encourages the stranger to proceed with improvements or where one of the parties acts in ignorance of the true facts but the owner remains silent when the owner could have prevented the stranger from operating under the delusion that he or she was going to be compensated. Robinson v. Robinson,
In a construction contract it would be difficult for an owner to say it was not aware subcontractors and suppliers were engaged in activities that would be of benefit to the owner. But the owner relies on the fact it has engaged a general contractor and has made contract payments to it which the owner in the ordinary case has a right to presume the general will use to compensate subcontractors and suppliers. If the general through its own fault or mismanagement fails to do this it is difficult to see how a claim could be allowed against the owner since the owner may then be making double payments, could never estimate costs and construction activity might thus come to a halt.
But as noted mechanics lien and payment bond statutes have been created to protect subcontractors and suppliers despite these general rules.
What if, however, the subcontractor or the supplier did not or CT Page 4213-H could not place a mechanic's lien? What if no payment bond was procured? What if the subcontractor or supplier has no one to blame but itself for failing to perfect or act upon the mechanic's lien or started the job or delivered material knowing there was no payment bond? No one would argue that having failed to utilize these self-protective devices the subcontractor or supplier would be in a better position than they would have been before these statutory devices were enacted — that it is still true that no direct claim would be allowed against the owner.
But the possibility of unfairness to the subcontractor and supplier still remains. In other words these people did work or supplied material, an owner is benefited and the owner knew before the job the benefit would be received. Admittedly for the reasons noted a direct claim cannot be allowed against the owner if he made his contract with the general who in turn hired the subcontractors and suppliers. But these reasons are based on the need to avoid double costs, the need to allow owners and developers to calculate costs accurately and the importance of these considerations if construction activity is going to take place at all.
However, where the particular circumstances of a case are such that these reasons no longer apply then if a court can provide an equitable remedy to subcontractors and suppliers, why shouldn't it do so?
In other words in the peculiar and discrete case where no mechanics lien or payment bond is available, where a benefit was provided to an owner which the owner was well aware of, where an owner has allocated monies already for the general which have been put in a special account, where a portion if not the bulk of these monies were to go to pay subcontractors and suppliers, why shouldn't the courts use an equitable lien to protect unpaid subcontractors and suppliers at least where the project has been completed? There is no question of double payment since the money is already allocated, the allocation represents cost estimates that were already made for the job. The equitable lien would only apply to a specific fund and not generally to the assets of the party against whom the claim is made even if that fund did not satisfy the full claim of the party asserting the lien. Such a view comports with the position courts have taken with regards to equitable liens — they are so-called "floating equities" until the jurisdiction of a court is invoked directed against a specific chattel or fund which in some sense represents partial or complete satisfaction of the claim the party who wishes to impose the lien CT Page 4213-I is advancing, Clement v. Homes,
Thus some of the dire predictions of municipal paralysis made by the defendant city if the court were to entertain the possibility of the imposition of an equitable lien are not realistic at least where the lien is allowed against an identified fund set aside by the city itself and the project is completed.
The circumscribed way in which an equitable lien should be allowed to operate also answers the defendant city's broad claim that governmental immunity should in all cases preclude the imposition of an equitable lien on a contract balance. The defendant correctly notes that a municipality is entitled to governmental immunity in the performance of governmental functions,Ryszkiewicz v. New Britain,
But in a case at least where a contract is completed and a special fund denominated a contract balance exists (as in ActiveFire Sprinkler) the governmental immunity argument doesn't seem to be very convincing. Where is the discretionary activity? The funds have already been purposely put into a special account the only question is whether they should be subject to an equitable lien or whether the government should be allowed to withdraw the funds and use them for other activities having nothing to do with the original purpose for which the fund was created. Also governmental immunity like any other immunity can be waived. Where a city puts funds into what is in effect a contract balance account to pay the general contractor, who the city must be taken to know will use a portion of the funds to pay subcontractors or suppliers, how can it rely on governmental immunity if a court decides it would be inequitable not to impose a lien on the contract a balance fund. A court would not be interfering with ongoing governmental operations but would merely be preventing the municipality from being unjustly enriched by transferring specifically allocated CT Page 4213-J funds back to the general treasury despite receiving the benefit for the payment of which the funds were allocated in the first place. The question still remains as to how this general analysis applies to the facts of this case and this analysis also leads to certain problems with the plaintiff's request for an equitable lien based on those facts.
Here while the project was still going on the plaintiff claims to have given oral and written notice to an official at the city's Public Works Department that the general contractor had failed to pay for certain supplies. Under such circumstances it would be unacceptable and even create some mischief to hold that any equitable lien later fixed on by a court should reflect the amount in a purchase order account created for the general contractor's expenditures at the time notice of non-payment was given by the supplier. At the time the notice was given the owner, or here the city, had no particular obligation to pay the supplier itself, it would be difficult to say there had been unjust enrichment where the job hadn't even been completed, and such a rule might breed chaos. Construction projects would just stop and under the guise of enforcing an equitable principle through creation of a lien the court would end up assigning priorities to the claims of particular suppliers and materialmen. From another perspective there would be also real infringement on the objectives sought to be achieved by the doctrine of governmental immunity if such a result were to be reached at least where the owner is a municipality. The activities of the municipality in disbursing funds upon receipt of the notice from an unpaid supplier during the middle of a job would be directly affected — activities which would be clearly discretionary.
The very nature of an equitable lien is that it is not operative until court action is taken and then it attaches only as to existent chattels or undisbursed funds, see Restatement of the Law: Restitution § 161 comment (e): "An equitable lien can be established and enforced only if there is some property which is subject to the lien", see also § 215(1) of the Restatement.
Neither is this a case like Kennedy Electric Co. v. U.S.Postal Service,
As to the $20000 remaining in the purchase order when it was closed out in February 1993 a different question may be presented. The project still had not been completed and the close out occurred before suit was brought so it could be asked — what is the equitable lien going to attach to? As the Restatement indicates if the fund cannot be traced on what is the equitable lien to attach. If the chattel or fund cannot be traced then there is only a personal claim against the city but no such personal claim is appropriate by the subcontractor.
On the other hand I am not quite clear on how or more exactly for what purposes the purchase order was closed out. If it was closed out with the money just going to the city's general fund, or if the money was used to complete phases of or aspects of the project not contracted for with the general contractor then it might be a logical extension of the equitable principles here discussed to say that the city should not be allowed to do this. If the monies were used merely to complete the project in the manner that the general contractor had agreed to then I do not believe an equitable lien would be appropriate — to what is it to attach and how could it be improper for the city to complete the project. Absent my ability to resolve these just mentioned factual questions I do not believe the plaintiff's motion or the defendant's cross motion for summary judgment should be granted as to the first count of the plaintiff's complaint.
Nelson v. Nelson Neal Lumber Co. , 171 Wash. 55 ( 1932 )
Henningsen v. United States Fidelity & Guaranty Co. of ... , 28 S. Ct. 389 ( 1908 )
Active Fire Sprinkler Corp. v. The United States Postal ... , 811 F.2d 747 ( 1987 )
ARCHITECTONICS, INC. v. Salem-American Ventures , 350 So. 2d 581 ( 1977 )
Employers' Liability Assurance Corp. v. Crandall , 22 Conn. Super. Ct. 404 ( 1961 )
American Masons' Supply Co. v. F. W. Brown Co. , 174 Conn. 219 ( 1978 )
United States v. Ansonia Brass & Copper Co. , 31 S. Ct. 49 ( 1910 )
Edward Meyers Caldwell v. J. Reuel Armstrong, Trustee in ... , 342 F.2d 485 ( 1965 )