DocketNumber: No. CV-97-0569696-S
Citation Numbers: 1997 Conn. Super. Ct. 6346
Judges: LAVINE, JUDGE.
Filed Date: 6/3/1997
Status: Non-Precedential
Modified Date: 4/18/2021
Many of the pertinent facts are set out in plaintiff's May 19, 1997 brief in support of its application. As recited by the plaintiff, in summary, this matter relates to a major construction contract between the Housing Authority of the City of Waterbury (hereinafter "WHA") and Alca Construction Company, Inc. (hereinafter "Alca"). According to plaintiff's recitation, the parties entered into a construction contract which called for the renovation of six buildings in a Waterbury public housing project known as Berkley Heights. The WHA received funding for the project from the Federal Department of Housing and Urban Development ("HUD"), and the WHA agreed to abide by HUD's rules and regulations governing the funding of such projects. Alca submitted a winning bid of $10,477,500 and the parties entered into a contract on April 22, 1993. According to plaintiff, HUD regulations require that local housing authorities receiving HUD funding use certain contract forms contained in its procurement handbook for all construction contracts let pursuant to HUD funding, and specifically provide that such forms may not be modified without written HUD approval.
Plaintiff essentially makes two claims. Plaintiff argues, first, that Article 31 of HUD form 5370, "General Conditions of the Contract for Construction," contains language constituting an agreement between the parties to arbitrate in this case. Noting that arbitration is looked upon favorably as a viable alternative to protracted litigation, plaintiff argues that the contract — in particular Article 31 — must be read to mean the parties have agreed to arbitrate. See pages 4-11 of plaintiff's May 19, 1997, Brief in Support, and cases cited therein. Where there is a question as to whether arbitration has been agreed to, plaintiff argues, see e.g. Board of Education v. Frey,
Plaintiff relies principally on Section (e) of Article 31, "Disputes," in support of its first claim — that the parties agreed to arbitrate. Article 31 reads as follows:
31. Disputes
(a) "Claim," as used in this clause, means a written demand or written assertion by one of the contracting parties seeking, as a matter of right, the payment of money in a sum certain, the adjustment or interpretation of the contract terms, or other relief arising under or relating to the contract. A claim arising under the contract, unlike a claim relating to the contract, is a claim that can be resolved under a contract clause that provides for the relief sought by the claimant. A voucher, invoice, or other routine request for payment that is not in dispute when submitted is not a claim. The submission may be converted to a claim by complying with the requirements of this clause, if it is disputed either as a liability or amount or is not acted upon in a reasonable time.
(b) Except for disputes arising under the clauses entitled Labor Standards and Labor Standards — Nonroutine Maintenance, herein, all disputes arising under or relating to this contract, including any claims for damages for the alleged breach thereof which are not disposed of by agreement, shall be resolved under this
(c) All claims by the contractor shall be made in writing and submitted to the Contracting Officer for a written decision. A claim by the PHA/IHA against the Contractor shall be subject to a written decision by the Contracting Officer.
(d) The Contracting Officer shall, within ___ (60 unless otherwise indicated) days after receipt of the request, CT Page 6349 decide the claim or notify the Contractor of the date by which the decision will be made.
(e) The Contracting Officer's decision shall be final unless the Contractor (1) appeals in writing to a higher level of the PHA/IHA in accordance with the PHA's/IHA's policy and procedures, (2) refers the appeal to an independent mediator or arbitrator, or (3) files suit in a court of competent jurisdiction. Such appeal must be made within (30 unless otherwise indicated) days after receipt of the Contracting Officer's decision.
(f) The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appeal or action arising under or relating to the contract, and comply with any decision of the Contracting Officer.
As defendant correctly observes, a claim for arbitration must be based on an agreement between the parties in writing that states clearly the intention of the parties to settle by arbitration any controversy arising out of a dispute. See
Connecticut General Statute Section
The threshold issue for the court to decide, therefore, is CT Page 6350 whether the plaintiff and defendant entered into an agreement clearly requiring arbitration. The court, in examining the relevant contract language, must determine whether or not the parties clearly intended to agree to arbitration in this case.White v. Kampner,
Having reviewed the documents and exhibits submitted to me, including the HUD general conditions, HUD form 5370, and the supplemental general conditions, and having considered the briefs submitted, and the oral arguments made, I conclude that the contract documents, generally, and Article 31(e) specifically, cannot reasonably be read to mean that the parties entered into an agreement to arbitrate. I agree with the defendant's argument that Article 31 is merely a contract provision setting forth a series of potential or possible procedures which might be used in the resolution of disputes. As defendant notes, Article 31 refers to mediation and refers to arbitration, but it falls short of constituting an agreement to mediate or arbitrate. Defendant notes correctly that this section clearly contemplates the possibility that the parties may, in some other section of their contract, have agreed to resolve their disputes in the courts or that, alternatively, a matter may be referred to an independent mediator or arbitrator. But conspicuously lacking from the agreement is a provision clearly stating that all, or a portion of any, disagreements or disputes arising out of the contract or the breach thereof shall be submitted to arbitration. Such provisions are found in many of the reported decisions relating to this issue. See, e.g., Security Ins. Co. of Hartford v.DeLaurentis,
Moreover, as defendant notes, Article 31 of the Supplemental General Conditions at page 9 provides explicitly that:
The parties agree that any and all claims asserted by or against the PHA arising out of this contract or related thereto shall be heard and determined either in the federal courts of the United States located in Connecticut or in the Connecticut state state's courts located in the county of New Haven, Connecticut.
I agree with defendant that this is a forum provision, and cannot be read in conjunction with all of the contract documents to suggest that the parties have in fact agreed to arbitrate.1
Plaintiff's second argument, in essence, is that the defendant has waived its right to object to arbitration by filing an answer and setoff in this matter, or should be estopped from objecting to arbitration. See plaintiff's Exhibit 11 to its May 19, 1997, Brief in Support of Application to Compel Arbitration and Appoint an Arbitrator. I agree with defendant's argument that the mistaken filing of an answer and setoff, immediately disavowed prior to the institution of arbitration proceedings, cannot be construed to constitute a waiver. As defendant notes, a waiver is an intentional relinquishment of a known right.National Transportation Company v. Toguet,
Among those cases cited by defendant in support of its argument are the following: Azcon Construction Company, Inc. v.Golden Hills Resort, Inc.,
SUMMARY AND CONCLUSION
In conclusion, a review of the relevant documents and provisions persuades me that there was no agreement to arbitrate in this case. Moreover, given the circumstances presented, plaintiff's claim that defendant has surrendered its right to object to arbitration by mistakenly filing an answer and setoff, immediately disavowed prior to the institution of any arbitration proceedings, is rejected. Given the facts and circumstances of this case, granting plaintiff's application would require defendant to engage in an arbitration it has not consented to.
Consequently, plaintiff's application to compel arbitration and appoint an arbitrator is denied.
Douglas S. Lavine Judge Superior Court
Atkinson v. Sinclair Refining Co. , 82 S. Ct. 1318 ( 1962 )
Garrison v. Garrison , 190 Conn. 173 ( 1983 )
W. J. Megin, Inc. v. State , 181 Conn. 47 ( 1980 )
Board of Education v. Frey , 174 Conn. 578 ( 1978 )
National Transportation Co., Inc. v. Toquet , 123 Conn. 468 ( 1937 )
Gary Excavating, Inc. v. Town of North Haven , 164 Conn. 119 ( 1972 )
Conntech Development Company v. University of Connecticut ... , 102 F.3d 677 ( 1996 )
A. Sangivanni & Sons v. F. M. Floryan & Co. , 158 Conn. 467 ( 1969 )
Connecticut Union of Telephone Workers, Inc. v. Southern ... , 148 Conn. 192 ( 1961 )