DocketNumber: No. CV 94 56130 S
Citation Numbers: 1996 Conn. Super. Ct. 4082-V, 16 Conn. L. Rptr. 571
Judges: RITTENBAND, J.
Filed Date: 5/14/1996
Status: Non-Precedential
Modified Date: 4/18/2021
FACTS/PROCEDURAL HISTORY
On March 23, 1987, the then property owners, Stephen J. Dellaquila Della Construction Co., Inc. applied (application #249) to the Commission for a sixty-two lot subdivision of property at Florida and Stebbons Road in the Town of Somers, Connecticut. (Return of Record [ROR], Item 6). On July 23, 1987, the Commission approved that application for division of the property into fifty-nine lots. (ROR, Item 6). The Commission entitled said property as "The Homes At Heron Pond, Property of Stephen J. Dellaquila Della Construction Co. Inc., Stebbins Florida Roads. Somers, Conn., dated July 15, 1987." (Defendant's Exhibit, P Z 1).
On September 24, 1987, Rene Veilleux of Veilleux Enterprises, Inc. requested the Commission to allow Veilleux to construct the subdivision in two phases.1 (ROR, Item 6). On October 8, 1987, the Commission approved Veilleux's request on behalf of Ken Rutledge, the new owner of the former Della Subdivision.2 (ROR, Item 6). These two phases were subsequently completed.
On April 14, 1994, the Commission approved the construction of CT Page 4082-W Phase III of the Heron Pond Subdivision subject to the posting of a bond.3 (ROR, Item 3-I). As of this date, Maple Leaf was the record owner of Phase III. (Plaintiff's Exhibit A).
On May 16, 1994, Mr. Veilleux, president of Maple Leaf Construction, formally requested an extension of the original subdivision approval "to allow for the time needed to proceed and complete the site improvements on this final phase of Heron Pond."4 (ROR, Item I-F). On June 30, 1994, the Commission held a public hearing to determine whether to grant Maple Leaf an extension. (ROR, Item 3-B). The Commission subsequently denied Maple Leaf's request for an extension for the Heron Pond Subdivision for the following reasons:
(1) since the approval of the subdivision, new data is now available concerning watercourses which may or may not have an impact on the subdivision;
(2) with new data available to staff and consultants, certain lots within the subdivision (phase III) may not be suitable for building;
(3) if the developer completes the roadway and particular lots become nonconforming to current regulations, the town would become liable for the maintenance of the roadways;
(4) the drainage pipe which currently appears to be blocked, may or may not have an impact on the water within the area if it were to be cleared. The cleaning of that particular area may or may not also have an impact on the existing homes; and
(5) the current subdivision approval will expire on July 23, 1994 (ROR, Item 3-C).
The Commission published legal notice of its decision in the Journal Inquirer on July 13, 1994. (ROR, Item 2-A). On July 27, 1994, the plaintiff filed an appeal with the clerk of the superior court, judicial district of Tolland at Rockville. The plaintiff asserts that the Commission acted illegally, arbitrarily and in abuse of its discretion by: (1) ignoring the spirit and legislative intent of General Statutes §
The defendant filed a return of record on October 5, 1994, and an answer on January 25, 1995. On January 10, 1996, the parties appeared before the court and argued the merits of the appeal.
JURISDICTION
In order to take advantage of a statutory right of appeal from a decision of an administrative agency, there must be strict compliance with the statutory provisions which create that right.Simko v. Board of Appeals,
A. Aggrievement
Aggrievement is a jurisdictional matter and a prerequisite for maintaining an appeal. Winchester Woods Associates v. Planning Zoning Commission,
The plaintiff alleges that it is the owner of the property which is the subject of this appeal. (ROR, Item 3B). The plaintiff further alleges that the defendant has deprived the plaintiff of the right to use its property as it intended and as permitted by law. At oral argument, the parties stipulated that Maple Leaf owned the Phase III lots in question when the Commission denied Maple Leaf's request for an extension. The court finds from the CT Page 4082-Y record that the denial of the plaintiff's request for an extension specifically and injuriously affected its property, which is the subject of this appeal. Accordingly, the court finds that the plaintiff is aggrieved.
B. Timeliness
General Statutes §
STANDARD OF REVIEW
A trial court may grant relief in an appeal from a decision of an administrative authority only where the authority has acted unreasonably, illegally, arbitrarily or has abused its discretion.Smith v. Zoning Board of Appeals,
"The burden of proof is on the plaintiff to demonstrate that the board acted improperly." Spero v. Zoning Board of Appeals,
DECISION CT Page 4082-Z
This appeal appears to be a case of first impression regarding Connecticut General Statutes §
The plaintiff contends that §
Connecticut General Statutes §
The Supreme Court has held that the word "may" is discretionary and not mandatory. Seals v. Hickey,
Although a court need not reference a statute's legislative history when the language of a statute is clear and unambiguous,American Universal Ins. Co. v. DelGrecco,
The court concludes, therefore, by a plain reading of General Statutes §
Although the court finds that the Commission has discretion to grant or deny subdivision extensions, the Commission can not be unreasonable in its decision. In the present action, the court must consider whether the Commission had a reasonable basis to deny Maple Leaf's extension request.
The court concludes that the Commission reasonably denied Maple Leaf's request for an extension for the reasons as set forth below.
First, Maple Leaf sought an extension at a point when their Inland Wetlands approval had expired. The record reflects that the Inland Wetlands approval expired in 1992. Maple Leaf argues that the subdivision problems were on the agenda of the Inland Wetlands Commission and that the Commission should have given Maple Leaf the extension to go before the Inland Wetlands Commission. The court, however, finds that the Commission did not have to grant Maple Leaf an extension to give it time to go before the Inland Wetlands Commission when the approval had since expired in 1992.
Second, Maple Leaf did not meet its burden of establishing why the Commission should have granted it an extension. The Town of Somers Subdivision Regulations § 8.01.01 provides that: "[t]he Commission will consider an application for extension of time to complete improvements and the term of the performance bond when good cause for the extension is shown." (Emphasis added.)
In its initial letter formally requesting an extension, Maple Leaf requested the extension "to allow for the time needed to proceed and complete the site improvements on the final phase of Heron Pond." (ROR, Item 1-F). Moreover, the transcript of the June 30, 1994 Commission meeting demonstrates that Maple Leaf failed to provide specific reasons or show good cause as to why they required an extension beyond the fact that it needed an extension to continue the third phase. (ROR, Item 3-B). The Commission could not have acted illegally, arbitrarily or in abuse of its discretion by denying Maple Leaf's extension when Maple Leaf failed to meet its burden of showing good cause for the extension.
Third, the court finds that the discretionary power provided CT Page 4082-BB to the Commission pursuant to General Statutes §
The legislature, by enacting
The court is well aware that General Statutes §
It is, however, a rudimentary rule of statutory construction that the legislature is presumed to be aware of all existing statutes, and, therefore, clearly knew of the maximum mandatory approval when it passed
Moreover, the Commission denied the extension for the following reasons:
CT Page 4082-CC(1) since the approval of the subdivision, new data is now available concerning watercourses which may or may not have an impact on the subdivision;
(2) with new data available to staff and consultants, certain lots within the subdivision (phase III) may not be suitable for building;
(3) if the developer completes the roadway and particular lots become nonconforming to current regulations, the town would become liable for the maintenance of the roadways;
(4) the drainage pipe which currently appears to be blocked, may or may not have an impact on the water within the area if it were to be cleared. The cleaning of that particular area may or may not also have an impact on the existing homes; and
(5) the current subdivision approval will expire on July 23, 1994. (ROR, Item 3-C).
The first reason was probably the basis for the Commission being concerned that the original Inland Wetlands permit had expired in 1992, and that Maple Leaf had yet to go before the Inland Wetlands Commission to obtain a new permit. This was a valid reason.
The court also finds that reasons two, three and four as well as the first reason as indicated above were proper and fulfilled the purpose of
The court further finds that the record supports the above reasons, and even if only one is valid, the Commission's decision must stand.8
Finally, the court finds by a preponderance of the evidence that the Commission accomplished the requirement of recording and filing notice of the expiration of the approval of the subdivision plan, pursuant to General Statutes §
For all of the above reasons, the court finds that the Commission did not act illegally, arbitrarily, unreasonably or in abuse of its discretion in denying Maple Leaf's application to extend. Accordingly, the plaintiff's appeal is dismissed.