DocketNumber: No. CV-033578S
Citation Numbers: 1993 Conn. Super. Ct. 9495
Judges: AURIGEMMA, J.
Filed Date: 11/3/1993
Status: Non-Precedential
Modified Date: 4/17/2021
B S filed the mechanic's lien on the property of Quadrangle after it performed certain excavation work and erected a retaining wall on Quadrangle's property in June and July of 1986. On July 22, 1986 several large blocks of the wall shifted, causing the wall CT Page 9496 to "fail." After the failure of the wall Quadrangle had the back fill behind the wall removed and some of the wall itself dismantled to determine who was at fault for the wall failure.
Although B S instituted this action in 1987, its path to trial was impeded by a convoluted thicket of counterclaims and third-party actions brought by Quadrangle in which Quadrangle claimed that B S, Atlantic Pipe Corporation, another mechanic's lienor on the property, and Dr. Clarence Welti, a soils expert, were responsible for the failure of the wall and were liable in damages to Quadrangle.
B S is seeking to recover the amount of $278,293, statutory interest and attorney's fees. Quadrangle denies that any amount is due to B S because of a lien waiver provision in an unexecuted contract between Schnip Building Company ("Schnip"), Quadrangle's general contractor, and B S.
The court finds that on May 21, 1986 B S submitted a proposed contract to perform site excavation work and construct a "Doublewall" retaining wall on Quadrangle's property for a total price of $326,568. The proposal was orally accepted by Schnip several days after it was submitted. Under the proposal the amount B S charged to construct the retaining wall was $33,000.
The negligence of B S in constructing the wall was alleged by Quadrangle in its counterclaim. Quadrangle never alleged that B S improperly or negligently performed the vast majority of the work it did, yet Quadrangle has failed to pay B S for that work.
The court finds that B S performed the following work pursuant to an oral agreement with Schnip: moving approximately 30,000 cubic yards of soil and other on site material; excavation for a building; placement of five inch concrete pad; filling and compacting ten feet of bank run gravel under slab; placement of fifteen inches of bank run gravel under paving; construction of "Doublewall" retaining wall. B S performed the aforementioned services in a accordance with good construction practices and the "failure" of the retaining wall was not due to any negligence of B S. The reasonable value of the services is $278,293.
The issue of whether a lienor has waived his rights to file a mechanic's lien is ordinarily a question of fact for the trier. Pomarico v. Gary Construction, Inc.,
Quadrangle relies on waiver language contained in the small print of a preprinted contract which was sent by Schnip to B S on July 22, 1986, the day the retaining wall failed. As of that date B S had already completed the work for which it seeks payment. B S never signed that contract and never agreed to, or even discussed, the mechanic's lien waiver provision thereof. None of the witnesses called by Quadrangle testified to any discussions with B S about the lien waiver provision of the unsigned contract. Therefore, Quadrangle relies solely on an erroneous response to a production request in urging the court to find that B S waived its mechanic's lien rights.
On March 15, 1990, an attorney for B S responded to the following request for production:
4. Identify all documents which you claim constitute the contract and/or agreements between Schnip Construction, Inc. and Bourgeois Shaw for the construction on the job which is the subject of the above-captioned action.
Answer: See contract dated May 28, 1986 including Rider A and Rider B attached thereto.
A party's answers to interrogatories or production requests are not judicial admissions, but rather, non-binding evidentiary admissions. Piantedosi v. Florida,
The court awards B S the amount of $278,293 in damages against Quadrangle as principal on the bond and against Seaboard as surety on that bond.
B S also seeks to recover statutory interest against Quadrangle and Seaboard. Seaboard and Quadrangle contest their liability for statutory interest on the bond for the reason that the bond does not contain any provision for interest. This court is not aware of any case law which addresses the issue of whether mechanic's lienor may recover interest on a bond substituted for a mechanic's lien. Therefore, it is necessary to examine the relevant statutes, case law on surety bonds in general, and the language of the bond itself.
Section
(a) Whenever any mechanic's lien has been placed upon any real estate . . . . the owner of the real estate . . . may make an application to any judge of the superior court that the lien be dissolved upon the substitution of a bond with surety. . . . If the judge is satisfied that the applicant in good faith intends to contest the lien, he shall, if the applicant offers a bond, with sufficient surety, conditioned to pay the lienor, such amount as a court of competent jurisdiction may adjudge to have been secured by the lien, with interest and costs, order the lien to be dissolved and such bond substituted for the lien . . . (emphasis added).
The bond is question is entitled "Release of Mechanic's Lien Bond" and provides that Quadrangle and Seaboard are jointly and severally liable in the sum of $280,000 for all judgements rendered against Quadrangle's property in favor of B S on the mechanic's lien. It recites the date of the mechanic's lien, September 23, 1986, and the volume and page of the land records in which the lien was recorded. It further states:
Whereas, Quadrangle Limited Partnership, seeks to discharge said lien pursuant to Connecticut CT Page 9499 General Statutes Section
49-37 .
The plaintiff argues that the language of section
In Six Carpenters, Inc. v. Beach Carpenters Corporation,
The construction urged by the [lienor] would discourage the substitution of bonds by agreement because of a fear of waiving defenses to the underlying lien. Moreover, it would lead to public mischief by compelling judicial intervention when not needed nor desired.
In this case the construction urged by Seaboard and Quadrangle would discourage lienors from agreeing to substitute bonds for liens because of a fear of waiving rights under the lien. This would also encourage needless resort to the courts and would contravene the legislative intent of section
Reading the interest and cost provisions of section
Based on the foregoing the provisions of section
The determination of whether interest is a proper element of damages is to be made in view of the demands of justice. Scribner Sons v. O'Brien,
After causing B S to suffer protracted delay in the prosecution of it mechanic's lien action, Quadrangle failed to prove that B S was negligent in any way with respect to the retaining wall. The award of interest in a mechanic's lien foreclosure has been upheld even where the defendant's failure to pay was done in good faith. General Electric Supply Co. v. Southern New England Telephone Co.,
B S also seeks to recover attorney's fees from Quadrangle and Seaboard. It cannot recover such fees because the bond does not provide for attorney's fees and there is nothing in section
B S has argued that A. Secondino Sons, Inc. v. LoRicco,
In a mechanic's lien foreclosure action where there is no CT Page 9501 underlying obligation by the landowner to pay attorney's fees, such as this action, then any attorney's fees awarded are, in effect, only recoverable to the extent of the value of the liened property because a mechanic's lien is a claim on the land only. Section
By the Court
Aurigemma, J.
International Harvester Co. v. L. G. DeFelice & Son, Inc. , 151 Conn. 325 ( 1964 )
Scribner v. O'Brien, Inc. , 169 Conn. 389 ( 1975 )
A & B Auto Salvage, Inc. v. Zoning Board of Appeals , 189 Conn. 573 ( 1983 )
Henry F. Raab Connecticut, Inc. v. J. W. Fisher Co. , 183 Conn. 108 ( 1981 )
New Britain Lumber Co. v. American Surety Co. , 113 Conn. 1 ( 1931 )
General Electric Supply Co. v. Southern New England ... , 185 Conn. 583 ( 1981 )