DocketNumber: No. 33 09 50
Judges: HODGSON, J.
Filed Date: 5/21/1992
Status: Non-Precedential
Modified Date: 4/18/2021
The application of BBED alleges only that "there is not probable cause to sustain the validity of the lien." At the hearing, the owner presented, without objection by the lienor, evidence in support of its invocation of
The Lienor seeks to collect for lumber worth $11,342.19 that it supplied to Frederick Buonfiglio d/b/a Buonfiglio Builders used in the construction of a house for BBED. The construction contract between BBED and Buonfiglio provides that Buonfiglio would build a single family house at Lot #2 Damascus Road for the sum of $81,110. By the terms of the contract, which was executed on July 16, 1991, ten percent of the contract amount was to be paid upon signing, thirty percent after completion of the foundation, shell, roof, and windows, thirty percent upon completion of the rough plumbing, insulation, sheetrock and taping, and the balance upon completion and issuance of a certificate of occupancy.
On July 12, 1991, Buonfiglio had borrowed $20,000.00 from BBED after explaining that he was in the process of building a number of houses and was experiencing cash flow difficulties. Buonfiglio failed to pay the note on its due date of September 15, 1991, and he advised BBED in early October 1991 that he would have to abandon construction of the house at Lot #2, Damascus Road because of his financial situation. On October 3, 1991, BBED paid Buonfiglio $24,000.00, which represented the installment due pursuant to the construction contract upon completion of the foundation, shell, roof and windows. Though the note provided that BBED could offset the $20,000.00 indebtedness from any amounts it owed Buonfiglio, no offset was made for the reason that Buonfiglio urged BBED to wait because he was still having financial problems.
On some date prior to December 1, 1991, but which date was not established by the evidence presented, Buonfiglio filed for bankruptcy. In December 1991, BBED hired him to act as construction supervisor on the house at Lot #2 Damascus Road. Buonfiglio will be compensated by BBED by receipt of a percentage of the profits from the project.
BBED presented evidence to the effect that the cost to complete the house on Damascus Road that Buonfiglio left CT Page 4961 unfinished will bring the total cost to a figure approximately $4,000.00 in excess of the $81,110.00 specified in the contract with Buonfiglio, and BBED thus has established one of the requirements for discharge of a mechanic's lien pursuant to
Pursuant to
The application to discharge the mechanic's lien of National Lumber, Inc. is denied.
BEVERLY J. HODGSON JUDGE OF THE SUPERIOR COURT.