DocketNumber: No. CV 01 0084961S
Citation Numbers: 2001 Conn. Super. Ct. 13468-cr
Judges: DIPENTIMA, JUDGE.
Filed Date: 9/18/2001
Status: Non-Precedential
Modified Date: 4/18/2021
Under General Statutes §
The hearing in probable cause for the issuance of a prejudgment remedy is not contemplated to be a full scale trial on the merits of the plaintiff's claim. The plaintiff does not have to establish that he will prevail, only that there is probable cause to sustain the validity of the claim. . . . The court's role in such a hearing is to determine probable success by weighing probabilities. . . . Moreover, this weighing process applies to both legal and factual issues.
(Internal citations omitted; quotation marks omitted.) Bank of BostonConnecticut v. Schlesinger,
Applying the standard of probable cause to the evidence presented by the plaintiff, the court determines the following. The parties signed the agreement on July 26, 1999, for $424,986.00. The defendant agreed to use pole barn construction. The building permit issued on April 28, 2000, although the town of Derby would not permit building to begin until June 2000.
The plaintiff was responsible for the site work, and completed the staking for each building in August 2000. The staking was required to be completed before the defendant could begin excavation. The excavation began in August and was completed around the beginning of November. The plaintiff was responsible for paving the floor pads after the excavation; six floor pads were poured by the end of November when they had to suspend pouring cement due to concerns of frost and freezing. In November and December 2000 and January 2001, the plaintiff complained to the defendant's representative that the work was not getting done. In December 2000 and January 2001 the plaintiff learned that the subcontractors hired by the defendant had not been paid by the defendant for work completed. In January 2001, the plaintiff requested that at minimum, four of the buildings be completed. On February 12, 2001, the CT Page 13468-ct plaintiff sent a letter to the defendant terminating the contract. At the time of the plaintiff's letter, the plaintiff had paid the defendant a total of $306,594.35. The plaintiff hired another contractor to complete the project. That contractor testified to a cost of completion of $139,575.00. The subcontractors hired by the defendant have filed mechanics' liens totaling $128,463.51 against the plaintiff. The defendant has filed a mechanic's lien of $214,076.17 against the plaintiff.
The plaintiff argues that the damages arising out of the breach of contract exceed $600,000. It claims as follows:
Cost of completion: $139,575.00
Liens: $128,463.51
Cost of Bonds in lieu of Liens: $7,631.00
Cost of cleanup $5,477.00
Doors $10,065.00
Cost of hiring additional engineers: $2,225.00
Cost of engineers for permit $5,480.00
Liens by Defendant $219,351.17
Attorneys fees $31,000.00
Loss of income $75,413.00
Interest costs on line of credit through May $42,700.00
Prejudgment interest $54,846.73 ____________ Total: $722,227.41
The court finds probable cause that a judgment will enter in the plaintiff's favor on a breach of contract claim, specifically as to time of performance. Millerv. Bougoin,
As to the mechanic's liens, the law precludes a consideration of the subcontractor's liens as an element of damages for the owner plaintiff. General Statute §
The theory of subrogation protects property owners by limiting the recovery of subcontractors to the unpaid claims of general contractors, thereby preventing owners from making double payments to general contractors and subcontractors. Peltier v. Stevenson Lumber Company, Superior Court, judicial district of Middlesex at Middletown, Docket Nos. 090651 and 090652 (Mar. 23, 2000, Arena, J.) (
As to the claim for attorney's fees, the law does not permit the court to allow it under these facts.
The general rule of law known as the ``American rule' is that attorney's fees and ordinary expenses and burdens of litigation are not allowed to the successful party absent a contractual or statutory exception. . . . Connecticut adheres to the American rule.
(Citations omitted; internal quotation marks omitted.) Rizzo Pool Co. v.Del Grosso,
There is no contractual provision for attorney's fees; the statutory provision cited by the plaintiff is the Connecticut Unfair Trade Practices Act (CUTPA), General Statutes §
Based on the credible evidence the court finds probable cause to award a prejudgment remedy in the amount of $150,000.
DiPentima, J.