DocketNumber: No. CV99 036 45 S
Citation Numbers: 1999 Conn. Super. Ct. 8668
Judges: SKOLNICK, JUDGE.
Filed Date: 6/15/1999
Status: Non-Precedential
Modified Date: 4/18/2021
"The guidelines for interpreting mechanic' s lien legislation are well established. Although the mechanic's lien statute creates a statutory right in derogation of the common law;. its provisions should be liberally construed in order to implement its remedial purpose of furnishing security for one who provides services or materials." (Citations omitted; internal quotation marks omitted.) Ceci Bros., v. Five Twenty-One Corp. ,
Assuming arguendo that Mohican has established probable cause to sustain the validity of its lien, the lien may nevertheless be discharged or reduced. Pursuant to General Statutes §
Where "a general contractor receives progress payments that are not turned over to those who have done the work represented by the progress payments, and ultimately defaults entirely, the owner making such payments and completing such a job is protected as long as the owner acts in good faith and reasonably, as defined by the statutes." Rene Dry Wall Co. v. Strawberry HillAssociates,
The Friedmans have submitted copies of two $50,000 checks, bearing the dates of May 27, 1998 and June 19, 1998, paid to Calabrese Construction Corporation in accordance with the CT Page 8670 parties' progress payment schedule. (plaintiff's Exhibits B, A 1). The Friedmans had also paid to Calabrese an additional $25,200 for extra work in regards to blasting and excavation. A narrative drawn up by the architect handling the Friedman's contract with Calabrese delineates that the work performed by Calabrese and its subcontractors including the additional surveying, excavation, earth removal and relocation was worth $71,700 and "was well short of the work necessary to be completed for the contractor to obtain the next progress payment." (Plaintiff's Exhibit A). Mohican argues that the Friedmans never made a third payment to Calabrese. Based on the contract between Calabrese and the Friedmans, the Friedmans' third payment was not due until completion and inspection of the excavation, foundation and concrete work by the architect. Because the aforementioned work was not inspected by the architect prior to the Friedmans' termination of the contract with Calabrese on November 5, 1998, the Friedmans were in no way responsible for the third progress payment. (Plaintiff's Exhibits A A-1). Furthermore, the Friedmans did not receive notice of Mohican's lien until November 10, 1998. (Application to Discharge Lien, ¶ 3)
Based on the foregoing, the court finds that the Friedman's payments to the general contractor constituted all sums due the defaulting general contractor and were made in good faith. Therefore, the court orders the discharge of Mohican's mechanic's lien.
SKOLNICK, J.