DocketNumber: No. CV87-245158
Judges: THIM, JUDGE.
Filed Date: 6/4/1991
Status: Non-Precedential
Modified Date: 4/17/2021
The parties' contract provides for the payment of the plaintiff's cost and a fee of $140,000.00. When the plaintiff stopped working on the project, it had furnished work and materials with a value of $2,523,257.00. The defendants paid $2,078,000.00 to the plaintiff and various sub-contractors. Hence, the plaintiff is owed $585,257.00 for the unpaid cost and fee.
At the time the plaintiff ceased working on the project, the project was substantially completed. The plaintiff left the project because it realized it would no longer be paid.
The parties' contract provides for the establishment of a guaranteed maximum price. The parties, however, never established a guaranteed maximum price. Their failure to do so was in part attributable to the fast pace of construction. The project progressed in a rapid but piecemeal fashion. The construction documents were continuously changed. The establishment of a guaranteed maximum price was not a critical issue until the parties terminated their relationship.
I have considered the defendants' argument with respect to the architect establishing a guaranteed maximum price after the termination of the plaintiff's services. I have also considered the defendants' argument with respect to the value of the work and materials supplied to the plaintiff. I find the issues for the plaintiff.
I have concluded that the evidence does not show wrong doing or bad faith on the part of the defendants. Accordingly. I declined to award pre judgment interest to the plaintiff.
At the conclusion of the hearing in damages, a motion to reopen the default was filed. The motion is denied.
Judgment for the plaintiff to recover $585,277.00 from defendants Herman Taub and REAG I Limited Partnership.
THIM, JUDGE.