DocketNumber: No. X05 CV-98-0167154 S
Judges: TIERNEY, JUDGE.
Filed Date: 2/1/2001
Status: Non-Precedential
Modified Date: 4/18/2021
In response thereto, the plaintiff filed a Second Amended Complaint dated November 12, 1999. On January 10, 2000, VP filed this motion to strike five counts. These five counts are: Count 17, negligent interference will business relations; Count 24, unfair acts in violation of Connecticut Unfair Trade Practices Act (CUTPA); Count 25, deceptive acts in violation of CUTPA; Counts 29, substantial assistance/aiding and abetting liability; and Count 30, civil conspiracy. VP has moved to strike these five counts on the basis of the economic loss doctrine asserting they seek tort remedies, which are prohibited in contract commercial litigation. VP claims that the economic loss doctrine should be applied in Connecticut. VP recognizes that no appellate court has applied the economic loss doctrine in a building contract dispute.
In addition, VP has moved to strike Count 17, negligent interference with business relations, because Worldwide has failed to plead a legally sufficient cause of action. VP correctly notes that a similar motion was denied by this court. VP now claims that there are new facts; therefore, it wishes the court to revisit this issue. CT Page 1853
The parties briefed the issues and presented oral argument. So too, did a companion defendant, Needham and Associates, Inc., an engineering firm, on its motion to strike dated January 26, 2000, which also addressed the economic loss doctrine. This court will deal with the issues raised in the Needham motion in a separate decision.
The complaint alleges that on January 17, 1997, the IVth Shea individually and as agent of VP, entered into a written purchase order to engineer, manufacture and deliver to a specified site, a pre-engineered building, pursuant to design and specifications of Worldwide's architect. The architect is not party to this lawsuit. Worldwide further alleges that VP then entered into a contract with Needham to design and engineer the steel components to be used to manufacture the building. The complaint further alleges that VP then entered into a contract with PKM to manufacture the steel components. The plaintiff alleges that it was the intended beneficiary of both the VP/Needham and VP/PKM contracts. The defendants were not to erect the building.
The original complaint contained nineteen counts. Those counts alleging contract or quasi contract are: breach of contract, breach of personal guarantee, breach of duty of good faith and fair dealing, breach of express warranty, breach of warranty of workmanlike condition, breach of warranty of merchantability, breach of warranty of fitness for a particular purpose and unjust enrichment. The remaining eleven counts sounded in variety of tort claims: fraud, intentional misrepresentation, reckless misrepresentation, negligent misrepresentation, innocent misrepresentation, duress, negligence, tortious interference with business relations, negligent interference with business relations, CT Page 1854 recklessness, and violation of CUTPA.
The complaint against VP has been distilled to twelve counts. Worldwide withdrew the following tort claims against VP: fraud, intentional misrepresentation, reckless misrepresentation, negligent misrepresentation, innocent misrepresentation, duress, negligence and recklessness. The two new counts of substantial assistance/aiding and abetting liability and civil conspiracy were added against VP. The seven referenced contract and quasi contract counts remain. VP was not sued in the personal guarantee count. The remaining five tort counts are the subject of this motion. In the event that VP's Motion to Strike is granted, the remaining seven counts against VP will sound only in contract or quasi contract.
"The economic loss rule is that, in the absence of privity of contract between the plaintiff and the defendant, or, in the absence of an injury to the plaintiff's person or property, the plaintiff may not recover in tort for a purely economic loss." Amity Regional School District v. AtlasConstruction, Superior Court, judicial district of Waterbury, Docket No. X06-CV99-0153388 S (July 26, 2000, McWeeney, J.) (6 Conn. Ops. 895);Connecticut Mutual Life Ins. Co. v. New York New Haven R. Co.,
This court, in its decision from the bench from May 12, 1999, recognized the economic loss doctrine and applied it to the facts of this case, striking the various tort claims. This court did so in reliance on language used in Flagg Energy Development Corp. v. General Motors Corp.,
Flagg Energy dealt with a Uniform Commercial Code claim by a buyer of allegedly defective energy goods, gas turbine generators, manufactured by the defendant for a construction project in a co-generation plant in Hartford, CT. The plaintiff sought damages for breach of express and implied warranties and added tort claims against the defendants for misrepresentation and CUTPA. The court determined that the plaintiff's complaint did not state a valid cause of action for misrepresentation and CUTPA, holding that actions for commercial losses arising out of a contract for the sale of goods cannot be combined with actions for negligent misrepresentation. "We agree with the holdings of cases in other jurisdictions that commercial losses arising out of the defective performance of contracts for the sale of goods cannot be combined with negligent misrepresentation." Flagg Energy Development Corp. v. GeneralMotors Corp., supra,
Although the claims by Worldwide in this case arise out of a building construction contract it has common features with the facts of FlaggEnergy. The Flagg Energy case involved the off site manufacturing of gas turbine generators to be later installed within a building. Portions of the building in this case were pre-manufactured and pre-engineered for a specific construction site. In addition, the Supreme Court relied on thePrincess Cruises case which involved the obligation to inspect and repair turbines in a large cruise ship. Although a cruise ship is not a building, it contains all the components of a building and in fact is substantially larger than the plaintiff's structure.
The plaintiff argues that the economic loss holding in Flagg Energy is only limited to the sale of goods, stating that it is a UCC case. This court does not see that limitation in Flagg Energy. Flagg Energy involved not a pure contract sale of goods, but the manufacturing off-site of large components to be later construed as part of a large building. Product liability law was also referred to in portions of the decision.Flagg Energy cited a Pennsylvania case, Duguesne Light Co. v.Westinghouse Electric Corp.,
The economic loss doctrine has been well settled in many jurisdictions for over 50 years. Three rationales have been used to eliminate tort liability based on the economic loss doctrine in construction contracts: (1) it maintains the fundamental boundaries of tort and contract law by limiting the economic loss arising in construction projects to the remedies provided by the parties' contracts; (2) the doctrine is essential to the dynamics of the construction arena. If tort and contract remedies were permitted to overlap, uncertainty and unpredictability in allocating risk would increase and impede future business activity; and (3) the law of tort is primarily concerned with the protection of persons and property from losses resulting from injury while the policy considerations underlying contract law is the protection of expectations bargained for, such as profits." Louis R Pepe and James Budinetz, "The Death Knell of the Economic Loss Doctrine in Connecticut," 17 CTLA Forum, January/February 1999.
The economic loss doctrine had its genesis in California in 1965. Seelyv. White Motor Co.
The District Court in Connecticut had an opportunity to review this trend. Ins. Co. of North America v. Town of Manchester,
A number of Superior Court decisions have refused to apply the economic loss doctrine. Darien Asphalt Paving, Inc. v. Town of Newton, supra, Superior Court, Docket No. CV 98-04878; SCALP Motors, Inc. v. RevcoSystems International, Inc., Superior Court, judicial district of Fairfield at Bridgeport, Docket No. CV 97-034846 is (August 12, 1999, Melville, J.) (
Despite the seeming trend in the United States toward rejecting the CT Page 1859 economic loss rule, a number of Superior Court judges have adopted the rule. This court adopted it on May 12, 1999 in this case in a unreported oral decision from the bench. It was adopted in a construction dispute involving the Amity Regional High School in Woodbridge, CT. AmityRegional School District #5 v. Atlas Construction Co., Superior Court, judicial district of Waterbury, Docket No. X06-CV99-0153388 S (July 26, 2000, McWeeney, J.) (6 Conn. Ops. 895); DeVillegas v. quality Roofing,Inc., Superior Court, judicial district of Fairfield at Bridgeport, Docket No. 294190 (November 30, 1993, Freedman, J.) (
Of the five counts sought to be stricken, four set forth tort allegations: Count 24, CUTPA by unfair acts ("attempting to use IVth Shea as a subterfuge to deceive Worldwide and conceal Varco's own unfair acts and practices recited herein"; "when it knew such representations to be false"; "coercing Worldwide into lending this money to Varco under duress"); Count 25, CUTPA by deceptive acts (same allegations as in Count 24); Count 29, Substantial Assistance/Aiding Abetting Liability ("Varco attempted to use IVth Shea as a subterfuge to deceive Worldwide and conceal Varco's own unlawful acts described herein." The allegations of Counts 24 and 25 are also restated in this Count 29); Count 30, Civil Conspiracy (the above language of Counts 24, 25 and 29 are restated in this Count 30).
These four counts set forth claims distinct from a contract, quasi contract or UCC claim. They are denominated torts by the plaintiff's complaint and utilize tort phrases in the allegations. If the economic loss doctrine is applied to this lawsuit, these four counts must fall as they allege pure tort.
The plaintiff further argues that in the event that the court adopts the economic loss doctrine, its amended complaint has pled exceptions to the doctrine. The plaintiff points to the following new allegations contained in their Second Amended Complaint as against VP: "Using Change Orders ``squeeze' additional monies from Worldwide to help cover Varco's expenses related to the project"; "the value of the CLP Energy Incentives of which Worldwide has been deprived"; "Varco attempting to use IVth Shea as a subterfuge to deceive Worldwide and conceal Varco's own unlawful acts described herein"; "V.P. represented to Worldwide that CT Page 1860 they would issue to Worldwide a credit to account for the work not performed on the east lean to. Despite these representations, no credit has been issued"; and "Varco representing to Worldwide that Varco would reimburse Worldwide $11,000 for the cost of the pour stops, and IVth Shea directing Varco not to issue an $11,000 credit to IVth Shea, which credit was not passed on to Worldwide."
Other jurisdictions that recognize the economic loss doctrine have found a number of exceptions: (1) damages that were not reasonably foreseeable at the time of contracting. SNA Inc. v. Hartzell Propeller,Inc., No. 95-1397, 1996 WL 283646 (E.D. Pa. May 29, 1996); (2) damages that far exceed the plaintiff's contractual expectations, such as damage to property other than that property that was the subject of the contract. Laidlaw Waste Systems, Inc. v. Mallinckrodt, Inc.,
The plaintiff's argue that its Second Amended Complaint fits within these recognized exceptions. Unfair and deceptive acts of squeezing additional money out of plaintiff by submitting false and improper change orders has been alleged. The plaintiff also alleges in the substantial assistance count, the failure to issue a $11,000 credit for pour stops and numerous discharges and overcharges for products and services not provided. As to the civil conspiracy count the plaintiff again points to the failure to issue a $11,000 credit for pour stops and the squeezing of additional money out of the plaintiff by submitting false and improper change orders. The plaintiff argues that the first three exceptions are applicable to these allegations. The plaintiff claims that these damages: (1) were not reasonably foreseeable at the time of contracting; (2) the harm far exceeded the plaintiff's contract losses; and (3) there are independent allegations of fraud and misrepresentation not connected with the defendant's breach of contract.
The plaintiff's Second Amended Complaint has alleged with the greatest CT Page 1861 specificity possible, the actual acts: (1) failure to give $11,000 pour stops credit; (2) failure to price properly, thus leading to discharging and overcharging; and (3) failure to give other contract credits. All of these claims are essentially contract claims, remedies for which the parties could have negotiated in their agreement. Plaintiff's contract contains an adequate source of remedy. These remedies were known at the time of the contract. These are not sufficient allegations of fraud.Seiling v. D'Esopo Co., Superior Court, judicial district of Hartford, Docket No. CV 96-0561422 (November 22, 1996, Wagner, J.T.R.) (
VP further argues that this lawsuit is not a construction contract dispute but more akin to a product liability action. Flagg Energy in footnote 46 referenced the product liability statute where it sets forth Connecticut public policy, that an action for commercial loss caused by a product may be brought only under the UCC. Although the product liability statute, General Statutes §
Prior to 1984, commercial losses sustained by a plaintiff were "harm" under the PLA. Verdon v. Transamerica Ins. Co.,
The type of loss claimed is a factor that distinguishes Coburn andManchester from this case. The Manchester court relied on Coburn's claim of "property damage." In this court's opinion, Coburn involves pure property and personal injury damages. The plaintiff was a residential homeowner suing the installer of a defective septic system installed under contract with his predecessor in title. There appears to be no commercial type damage loss in Coburn, such as lost profits or loss of the benefit of the bargain.
The Flagg Energy court also turned to the UCC to determine if it set forth any public policy consistent with the economic loss doctrine. Noting that General Statutes §
The public policy established by the above mentioned statutes is further foundation for this court's belief that the economic loss doctrine will be fully adopted by our appellate courts and not just limited to the narrow facts of Flagg Energy.
This court strikes Counts 24, 25, 29 and 30 against the defendant, Varco-Pruden Buildings, Inc. This court will discuss Count 17 later.
The allegations of interference with business relations in Count 17 are more in the nature of a breach of contract claim. The damages sought are the loss of the benefit of a contractual bargain with Connecticut Light Power Company (CLP). The steel was to be manufactured to meet specifications that conformed to CLP quality design standards. This would have enabled the plaintiff to obtain energy incentives from CLP, a benefit worth hundreds of thousands of dollars. Although phrased in the form of "interference with contract," this count actually seeks a contract remedy. Thus, Count 17 is not in the nature of a tort claim but CT Page 1863 is a contract or quasi-contract claim. VP was alleged to have knowledge of the CLP insulation requirements, to have designed the job to meet those standards, failed to design and manufacture to those standards and as a result, cost the plaintiff the loss of the in future energy incentives. As such, Count 17 is not subject to the economic loss doctrine.
VP has asked to strike Count 17, negligent interference with business relations, both on the economic loss doctrine and other grounds. This court previously denied VP's Motion to Strike on May 12, 1999. This court held that Worldwide's complaint was sufficient to withstand the motion to strike. The complaint alleges that there is a contractual relationship between the plaintiff and a third party, who is not a party to this case, to wit, CLP. The complaint indicates the nature of that contract and the fact that the contract between the plaintiff and CLP was impacted. The complaint further alleges that Worldwide did not receive the energy incentives from CLP that it was entitled to had the building contract been properly performed.
Connecticut recognizes two causes of action for interference with contract: tortious interference and negligent interference. Blake v.Levy,
The Motion to Strike claims that Count 17 is a tortious interference claim. A tortious interference is an intentional or wilful interference with a contract. There must be an allegation of fraud, misrepresentation, intimidation, molestation or that the defendant acted maliciously. There must be allegations of some improper motive or improper means and that there was an injury to the holder of the contract. Robert S. Weiss Associates v. Wiederlight,
Privity of contract is necessary to sustain a claim for negligent CT Page 1864 interference with contract. Fidelity Casualty Ins. Co. v. Sears.Roebuck Co.,
After reviewing the Second Amended Complaint and the changes made therein with the prior amended complaint that was subject to the previously denied motion to strike, this court believes that Count 17 states a claim for negligent interference with business relations. Blakev. Levy, supra,
This court has already decided this issue in favor of the plaintiff on May 12, 1999. Upon review, insufficient new information or legal arguments have been presented to persuade this court to change its May 12, 1999 ruling. "New pleadings intended to raise again a question of law which has been already presented on the record and determined adversely to the pleader are not to be favored." Suffield Bank v. Berman,
The Motion to Strike Count 17 is DENIED.
The Motion to Strike Count 24, 25, 29 and 30 is GRANTED.
SO ORDERED.
BY THE COURT,
TIERNEY, J.
duquesne-light-company-the-cleveland-electric-illuminating-company-the ( 1995 )
Verdon v. Transamerica Insurance ( 1982 )
irving-widett-co-assignee-for-the-benefit-of-creditors-of-bw ( 1987 )
Coburn v. Lenox Homes, Inc. ( 1977 )
Fidelity & Casualty Insurance v. Sears, Roebuck & Co. ( 1938 )
Seely v. White Motor Co. ( 1965 )
Kakadelis v. DeFabritis ( 1983 )
Trans States Airlines v. Pratt & Whitney Canada, Inc. ( 1997 )
2314 Lincoln Park West Condominium Ass'n v. Mann, Gin, Ebel ... ( 1990 )
East River Steamship Corp. v. Transamerica Delaval Inc. ( 1986 )