DocketNumber: Nos. CV 86 0080843, CV 87 0087967, CV 87 0088037
Judges: LEWIS, JUDGE.
Filed Date: 3/8/1995
Status: Non-Precedential
Modified Date: 4/17/2021
The defendant filed an answer denying the material allegations of the complaint, and two special defenses. The first such defense contends that the plaintiff seeks to recover for services rendered and material furnished that were not contained in the written contract between plaintiff and defendant, in violation of General Statutes §
In the second of the above captioned cases, the defendant Hammermill is the plaintiff, and Brian M. McHugh individually is the only defendant, and not the corporation, McHugh Construction, Inc., of which he is the president. Hammermill alleges in the first count of an amended complaint dated September 21, 1987, that McHugh failed to construct the house on the premises in question in a good and workmanlike manner, but rather was negligent and thereby breached its contract with Hammermill. In the second count, Hammermill alleges that McHugh engaged in fraudulent and reckless misrepresentations by forging the names of subcontractors to waivers of mechanics liens. In the third count, this plaintiff claims that McHugh's conduct violated General Statutes §
In the third of the above cases, the plaintiff, Vincent CT Page 2487 Gaita, an electrician, sues both Hammermill and McHugh, and alleges that he rendered services and furnished material to the Hammermill premises as a subcontractor for McHugh. Gaita further claims that he is owed $9,000 and that he filed a mechanics lien on the subject premises and seeks to foreclose this lien. Hammermill filed four special defenses to Gaita's action. The first such defense is that the mechanics lien is defective because it was filed more than ninety days after the work had been performed and materials had been delivered. In the second special defense, Hammermill states that it had paid the original contractor, McHugh, before receiving notice of plaintiff's lien. Hammermill contends in its third special defense that Gaita had executed a lien waiver. In its fourth special defense, Hammermill claims that Gaita failed to foreclose its lien within the statutory one year deadline. McHugh denied the material allegations of Gaita's complaint and filed a counterclaim in which it alleged that the electrical work performed by Gaita was defective and unworkmanlike.
Hammermill filed a cross claim against McHugh in the third on contending that if it is ultimately found liable to the plaintiff, McHugh is responsible for reimbursing Hammermill for all such sums found to be due. McHugh filed a special defense to this cross claim, alleging that Hammermill could not maintain such an action because of General Statutes § 33-396, which prohibits foreign corporations from transacting business in this state unless they first obtain a certificate of authority from the secretary of the state. McHugh also filed a cross claim against Hammermill in this same action alleging that it was owed $95,586 pursuant to its contract with Hammermill, and that as a result it had been unable to pay certain of its subcontractors, including Gaita. Hammermill filed two special defenses to this cross claim which duplicate the special defenses filed against the plaintiff in the first action.
The case was referred to Attorney Matthew J. Forstadt, an attorney trial referee in accordance with General Statutes §
The attorney trial referee reached the following conclusions as a result of his findings of fact: (1) that the plaintiff had been wrongfully terminated by the defendant for reasons of convenience, and that when terminated, the plaintiff had substantially completed the project; (2) that any damage sustained to the subject premises after the plaintiff had been terminated and left the premises was not the fault of the plaintiff; (3) that the plaintiff should recover a total of $73,661, which is the contract price of $250,000, plus extras of $27,945, less $191,418 previously paid to the plaintiff, and less approximately $13,000 for remedial work required to be performed by the defendant to remedy certain aspects of the job that had not been performed in a workmanlike manner; (4) that judgment should enter for the plaintiff on defendant Hammermill's counterclaim because the defendant, not the plaintiff, breached the contract; (5) that Hammermill did not prove it suffered any ascertainable loss from the forgery of Gaita's name to the mechanics lien waiver, and should recover only nominal damages of $100 against McHugh, pursuant to CUTPA; and (6) that Gaita is owed $9,000 by the plaintiff, not by the defendant, and that Gaita's mechanics lien on the Hammermill property should be vacated. CT Page 2489
The plaintiff did not file any motions with respect to the attorney trial referee's report, but the defendant Hammermill moved, pursuant to Practice Book § 438, to correct the report. The defendant contends that the findings of fact should be amended to reflect that: (1) the contract provides that time is "of the essence" and that "substantial completion" means that the owner can occupy and use the premises; (2) the parties agreed that the project would be substantially complete by November 1, 1985, and that it was not substantially complete by the plaintiff as of that date; (3) the plaintiff breached the contract by not completing the project by that date and therefore it was not entitled to any damages; (4) the defendant Hammermill had sustained damages of approximately $30,000 because it had to pay other contractors to complete the work that the plaintiff had commenced but not finished; (5) certain aspects of the work performed by the plaintiff were defective and were not done in an acceptable and workmanlike fashion; and (6) the value of the extras performed by the plaintiff was $22,745, not $27,945.
In response to the defendant's motion to correct, the referee declined to make any changes in his findings of fact or recommendation that judgment enter for the plaintiff McHugh for $73,661, less $100 for the forgery, for the plaintiff with respect to the defendant's counterclaim, and for Gaita against McHugh for $9,000. The referee did, however, reiterate that the proposed date of completion of the project was known to the parties as impractical and unfeasible, and, in any event, the delay in completion was not the fault of the plaintiff.
With respect to this court's standard of review of an attorney trial referee's findings of fact in a given case, the Supreme Court has stated that: (1) the trial court may not "retry the case"; and (2) a court may not find additional facts or reject facts found by the referee unless, in the words of Practice Book § 439, "a material fact has been found without evidence or the [referee] has failed to find an admitted or undisputed fact, or has found a fact in such doubtful language that its real meaning does not appear." Dills v. Town ofEnfield,
In the present case, the defendant filed a combined "objection/exception" on September 13, 1994, but did not file a transcript with its exceptions. Practice Book § 439.1 It follows therefore that the factual findings by the referee must stand uncorrected because, without a transcript, these findings cannot possibly be evaluated. Hence, the referee's report must be viewed as if no exceptions had been filed. A failure to file valid exceptions constitutes in effect a waiver of the right to "attack the subordinate factual findings contained in the report." See Bernard v. Gershman,
The defendant did file the following objections to the, acceptance of the referee's report pursuant to Practice Book § 440: (1) that the referee ignored the provision of the contract that made time of the essence, that the agreed completion date was extended by agreement to November 1, 1985, and that the project was not substantially complete on that date; and (2) that after the plaintiff was terminated in December of 1985, the defendant hired other contractors to complete the project, and is owed approximately $31,000, as alleged in its counterclaim in the first action and in its complaint in the second action.
Since the trial court must accept the referee's findings of fact in the absence of valid exceptions to the report, its task is limited to determining whether the legal conclusions "are legally and logically correct and whether they find support in the facts found by the referee." Bernard v. Gershman, supra,
The attorney trial referee's conclusions appear to be legally and logically correct, and thus the court agrees with his recommendation that judgment should enter in favor of the plaintiff. No material error in the referee's report has been found, nor any other sufficient reason why the report is unacceptable. Practice Book § 443. The court finds that, in the words of Practice Book § 440, the referee's recommendations were "properly reached on the basis of the subordinate facts found."
Accordingly, judgment is entered in favor of the plaintiff in the first of the above actions to recover from the defendant Hammermill the sum of $73,661, less $100 for the CUTPA violation; that in the second action, judgment enters in favor of the plaintiff; and that in the third action, judgment is entered in favor of Gaita against the plaintiff in the amount of $9,000, and the mechanics lien is to be released.
No costs are to be taxed.
So Ordered.
Dated at Stamford, Connecticut, this 8th day of March, 1995.
William B. Lewis, Judge