DocketNumber: No. 2082
Citation Numbers: 35 App. D.C. 41, 1910 U.S. App. LEXIS 5863
Judges: Robb
Filed Date: 4/5/1910
Status: Precedential
Modified Date: 10/18/2024
delivered the opinion of the Court:
There are but two assignments of error, both relating to the court’s instruction to the jury as to the measure of damages. Since the question as to whether the appellee was guilty of a breach of the contract was submitted to the jury at the instance of the appellee, it is estopped to deny the propriety of
As to the rule of damages to be applied to the ties actually in possession of the contractor when the breach occurred, there is no controversy. The contractor admits that, as to them, damages based on the difference between the contract price and the market value would be proper. Our inquiry, therefore, narrows to the ties not in the possession of the contractor at that .time.
The Supreme Court of the United States appears squarely to have met this issue in Roehm v. Horst, 178 U. S. 1, 44 L. ed. 953, 20 Sup. Ct. Rep. 780. In that case, the plaintiff had contracted with the defendant to supply him with hops for a period of five years, at a fixed price.- There was a breach by the defendant after partial performance by the plaintiff. The plaintiff introduced evidence showing at what prices he could have made subcontracts for the sale of the hops which defendant refused to take, these prices being considerably lower than those named in the.original contract. After reaffirming the prevailing and undoubted doctrine that after refusal to perform by one party to a contract, the other party need make no further attempt to carry out its provisions, but may consider it at an end, the court said: “As to the question of damages, if the. action is not premature, the rule is applicable that plaintiff is entitled to compensation, based, as far as possible, on the ascertainment of what he would have suffered by -the continued breach of the other party down to the time of complete performance, less any abatement by reason of circumstances of which he ought reasonably to have availed himself. If a vendor is to manufacture goods, and, during the process of manufacture, the contract is repudiated, he is not bound to complete the manufacture,. and estimate his damages by the difference between the market price and the contract price, but the measure of damage is the difference between the contract price and the cost of performance.
“In this case, plaintiffs showed at what prices they could have made subcontracts for forward deliveries according to the contracts in suit, and the difference between the prices fixed by the contracts sued on and those was correctly allowed.”
In the recent case of River Spinning Co. v. Atlantic Mills, 155 Fed. 466, the plaintiff contracted to sell, and the defendant to buy, a quantity of wool. It was contemplated that plaintiff would manufacture same at its mills, but there was no limitation to that effect, and the court found that “its [plaintiff’s] obligation would have been fully performed by the tender of yarn of like quality, spun at other mills.” When the breach took place, the plaintiff had manufactured and had on hand but a portion of the undelivered yarn. As to this yarn, the court held that the measure of damages “should he the difference between the contract price and the value of the yarn in plaintiff’s hands.” But, as to yarn not manufactured and on hand, the court said: “While this is a just rule to determine a loss of profits on goods ready for delivery at the time of the breach, as was pointed out in Kingman & Co. v. Western Mfg. Co. 34 C. C. A. 489, 92 Fed. 486, 490, it is not the true rule as to goods not then made and ready for delivery. It is a just rule
“That there is in a suit by the seller no proper basis for a distinction between goods which he is to manufacture (whether bound to manufacture or-not) and goods which he is to buy, instead of to manufacture, is apparent from the reasoning of the Supreme Court in Roehm v. Horst, 178 U. S. 1, 21, 44 L. ed. 953, 961, 20 Sup. Ct. Rep. 780.” See also: Tufts v. Weinfeld, 88 Wis. 647, 60 N. W. 992; Olyphant v. St. Louis Ore Steel Co. 28 Fed. 729; Eckenrode v. Chemical Co. 55 Md. 51.
The decisions cited leave no room for doubt as to the rule to be applied here in determining damages. We therefore hold that the contractor is entitled to recover the difference between the contract price of the ties which the company refused to take, but which the contractor .did not have on hand when the breach occurred, and the amount which it would have cost the contractor to supply them. As to the ties actually on hand at the date of the breach, we have already stated that the measure of damages should be the difference between the contract price and the market value.
The unjustness of the rule contended for by appellee is obvi
As above stated, the just and true rule is to visit upon the party responsible for a situation not contemplated in the contract the embarrassment and damage occasioned by his own conduct. He has agreed that the contract shall cover a certain period, and without reason he has abruptly terminated that contract.' We see no reason in law or in equity why the damage occasioned by the breach should not be adjusted as of that date. If the seller has part of the goods on hand, the damages as to those goods will be the difference between the contract price and the market price. As to the goods not on hand, the damages will be the difference between the contract price and the cost of performance;, that is, the difference between what the purchaser had agreed to pay for the goods and what it would have cost the seller to supply them. This rule, as previously pointed out, discourages the repudiation of contractual obligations, protects the innocent party, and visits upon the offending party the natural consequences flowing from his misconduct.
The company has placed much reliance on the case of Yellow Poplar Lumber Co. v. Chapman, 20 C. C. A. 503, 42 H. S. App. 21, 74 Fed. 444. The incompleteness of the report of that case leaves the facts in some doubt. Whether Chapman owned or was in possession of all or only a part of the timber which the company refused to accept after having contracted therefor is somewhat uncertain. At all events, even if the case were in point, and authority for the contention of the com.pany, it would be contrary to the decided weight of authority on this question, as already indicated.
The company now contends that even though it did break the contract, the contractor had all the undelivered ties on hand when the breach occurred; hence, as the contract price and the market price of those ties were the same, he suffered no damage. We have examined the record with care, and find no evidence to substantiate the contention that the contractor had all the undelivered ties on hand when the breach took place. On the contrary, the testimony tends strongly to a conclusion
The decision is therefore reversed with costs and the case remanded with directions to grant a new trial. Reversed.
A motion by the appellee to restore certain words stricken from the opinion was overruled April 18, 1910.