DocketNumber: 30911
Judges: Ingram
Filed Date: 5/18/1976
Status: Precedential
Modified Date: 11/7/2024
Defendant American Fidelity Fire Insurance Company and intervenor-defendant PMS Construction, Inc., appeal from the grant of an interlocutory injunction which orders them to perform certain duties under a performance bond. The bond was executed by PMS as
Shortly after commencement of the construction, disputes began arising between PMS and DeKalb County concerning the timeliness and quality of PMS Company’s performance, and eventually, in August, DeKalb County gave notice to both PMS and American Fidelity that PMS was in default under the construction contract and its services were being terminated. DeKalb County also made a demand upon American Fidelity to complete the construction contract.
In October, PMS Company filed suit against DeKalb County charging that the county had unjustifiably and illegally terminated its contract with PMS. Thereafter, DeKalb County filed the present litigation against American Fidelity seeking an injunction to compel American Fidelity’s performance of its obligations under the bond and also seeking damages for American Fidelity’s alleged breach of its obligations under the bond. The performance bond provides, in pertinent part: "Whenever contractor shall be, and declared by owner to be in default under the contract, the owner having performed owner’s obligations thereunder, the surety may promptly remedy the default, or shall promptly (1) complete the contract ... or (2) obtain a bid or bids for completing the contract . . , and upon determination by surety of the lowest responsible bidder, or, if the owner elects, upon determination by the owner and the surety jointly of the lowest responsible bidder, arrange for a contract between such bidder and owner, and make available as work progresses... sufficient funds to pay the cost of completion less the balance of the contract price...”
PMS Company moved to intervene as a party defendant in the present case, alleging that it had entered into a contract with American Fidelity indemnifying the insurance company from any and all liability incurred by it under the terms of the performance bond. At the
Thereafter, the trial court, on the basis of the pleadings, affidavits and certain documentary evidence, entered its order granting DeKalb County’s application for an interlocutory injunction. The court held that the laws of "novation, suretyship and otherwise do not serve as a basis of nullifying the performance bond on the evidence before this court at this time.” Despite the defendants’ contentions that the conditions precedent to American Fidelity’s performance had not been met, the trial court also held that, "this court does not need to make a finding of fact that PMS Construction Company, Inc., was in default under the terms of its contract with DeKalb County ... , or that DeKalb County . . . has performed its obligation under the terms of said contract prior to the enforcement of the performance bond in question.” The trial court then ordered American Fidelity and PMS to perform their duties as set forth in the performance bond. The order also provided that, "[i]n the event that the performance bond which serves as the basis for DeKalb County’s petition for mandatory injunction is subsequently declared to be null and void, then DeKalb County . . . shall become responsible for reimbursing American Fidelity Fire Insurance Company for any sums which they may have expended in performing the terms of the bond under this order from the date hereof.”
Appellee DeKalb County has filed a supplemental
Appellants have filed a supplemental brief in which they argue against a dismissal of the appeal on grounds of mootness. However, they do not deny the alleged fact that American Fidelity executed the above described contract. Consequently, the effect of the contract will be considered by the court in ruling on the issue of mootness in this appeal. Grizzel v. Grizzel, 190 Ga. 219 (1) (9 SE2d 247) (1940). The particular question to be decided is whether, by executing the contract, and arranging for the completion of the construction project, American Fidelity has acquiesced in the trial court’s interlocutory order and performed the acts commanded by the injunction. If so, this appeal would serve no effective purpose and under such decisions as Blackshear v. Blackshear, 232 Ga. 312, 315 (206 SE2d 429) (1974); City of Lilburn v. C & E Builders, 231 Ga. 189 (200 SE2d 764) (1973); Bd. of Commrs. of Walton County v. Dept. of Public Health, 229 Ga. 173 (2) (190 SE2d 39) (1972); and City of East Point v. Gatewood, 225 Ga. 696 (171 SE2d 496) (1969), should be dismissed as moot.
Appellants argue that Item 1 of Art. 5 of the new CFI contract prevents the issues concerning the interlocutory injunction from becoming moot despite the execution of the contract and thus preserves their right to appeal the trial court’s order. Item 1 provides, "[i]t is understood and agreed that in the event that American Fidelity Fire Insurance Company is successful in having its bond declared null and void, or PMS Construction Company, Inc., prevails in its suit against DeKalb County, or if
A review of the new CFI construction contract persuades us that American Fidelity has performed its obligations under the interlocutory injunction. Therefore, appellants can obtain no benefit from a reversal of the interlocutory injunction and the appeal must be dismissed as moot. Of course, this dismissal "does not constitute an adjudication that the order granting the [interlocutory] injunction was proper and it leaves the issues as to the merits of the case still pending in the trial court.” Bd. of Commrs. of Walton County v. Dept. of Public Health, 229 Ga. 173 (3), supra.
Appeal dismissed.