The only matter in dispute between the parties in this case is, whether the plaintiff has a lien on the store-house of the defendant which can be enforced as valid and binding. The plaintiff lives and does business in sawing lumber in Gadsden, Alabama, and the defendant wanted lumber to build a store in Rising Fawn, Georgia, where he resided. So he made a contract in Gadsden with the plaintiff to furnish him the lumber, as it should be ordered by him from Rising Fawn, Georgia—the places being connected by rail. It was ordered at different times in January and February, and sent to defendant at Rising Fawn, and used in building the store. The lien was duly recorded; and the questions made are, first, is it an Alabama contract, made with a citizen of that state, and can he, on such contract, have a lien on property in Georgia, under sections 1979 and 19S0 of the Code? The language of 1979 is, among other things, “ all contractors, material, men, and persons furnishing material for the improvement of real estate * * * shall each have a special lien on such real estate.”
So in 78 N Y. (Court of Appeals), much relied on by plaintiff in error, the entire work on the machine was done in New Jersey, and it was, when finished, there delivered, and there became the property of the defendant. The ruling of the court was simply that the mechanic’s lien law of New York, for the counties of Rings and Queens, had no extra territorial effect, but was intended for the protection of those who perform labor or furnish materials within the state. The court say “ when this engine was brought into this state and put into this factory, it belonged to the defendant. The plaintiff did not furnish any material in this state;” as much as to say, if he had, his lien would have been valid. And in that case, too, the oourt leave it an open question whether that engine did not improve real estate where erected, intimating that if it had, the lien, even in that case, would be good.
In 45 Ga., 541, the case was that of a foreign contract executed in this state, and the point was made that it was so, and therefore no lien attached but it was unnoticed by the court; the decision turning on another point.
In the case at bar, no complete contract was made in Alabama. The witness says: “A verbal contract was made between Kyle and Curry as to prices of lumber * * which Curry said he wanted for the purpose of building a store in Rising Fawn, Georgia. No quality of lumber was at that time agreed on, Curry taking memorandum of prices, and said he would forward bills for what he wanted on his return home. The lumber was to be sent to Rising Fawn, Georgia,” and then the witness proves the account attached to the declaration, which shows when it was sent, at different times in January and February, the agreement as to prices having been made in December or early in January.
So that in this case the contract was completed in Georgia, the lumber furnished in Georgia, and it improved real estate in Georgia.
Judgment affirmed.