DocketNumber: 56327
Judges: Banke
Filed Date: 10/16/1978
Status: Precedential
Modified Date: 11/8/2024
The appellant, Norair Engineering Corporation, was the general contractor for the construction of a hospital. The appellee, Pass Painting Company, subcontracted to do painting and other work on the interior of the building. This litigation arose from a complaint filed by the hospital against Norair. Norair joined Pass as a co-defendant and then filed a cross claim against it, alleging that the paint had peeled and flaked due to faulty workmanship on Pass’ part, necessitating the repainting of a large portion of the building. Pass in turn filed a cross claim against Norair for the balance due under the subcontract.
The case was referred to an auditor, who exonerated Pass from liability for defective workmanship and recommended that Pass receive judgment against Norair for the balance due under the contract. The trial court entered judgment in accordance with this recommendation, and it is from this judgment that Norair appeals. Held:
1. The court did not err in disallowing a
2. The evidence supported the auditor’s finding that Norair had accepted responsibility for paying Pass for certain work which the latter had done on behalf of another subcontractor..
3. There is no evidence to support Norair’s contention that Pass had primary liability for any cleanup work. The only evidence on this issue was that. Pass had agreed to pay a certain portion of this expense as part of a compromise settlement. However, the settlement was never accepted by Norair.
4. The auditor’s finding that the peeling and flaking of the paint was caused by the acts and omissions of Norair rather than by any lack of diligence on the part of Pass was supported by evidence and will not be disturbed on appeal. See generally Bettis v. Leavitt, 236 Ga. 213 (2) (223 SE2d 88) (1976).
Judgment affirmed.