Citation Numbers: 38 Idaho 306, 222 P. 292
Judges: Budge, Dunn, Lee, McCarthy
Filed Date: 11/27/1923
Status: Precedential
Modified Date: 10/19/2024
— This is an action against appellant county to recover the balance of the contract price for the erection of a courthouse. 'The complaint alleges that the respondent copartnership and appellant county entered into a written contract by which the former agreed to erect a courthouse for the latter for the contract price of $152,525; that said building was erected and completed in accordance with the contract and was accepted by the architects; that in accordance with a provision of the contract authorizing such alterations as might be ordered by the architect, certain alterations were made at a cost of $6,816.73, making the total cost $159,341.73; that appellant has paid respondent $140,461.08, leaving a balance of $18,880.65; that respondent presented a claim for this balance to the board of county commissioners, which was rejected. Within the sis months allowed by the statute respondent sued for the balance. To this complaint appellant demurred generally' and specially. It also answeréd alleging that the contract was ultra vires and void under the provisions of Const., VIII, 3, and C. S.,
‘1 That at the time the said contract was made and entered into by the plaintiffs and the defendant, and delivered to the plaintiffs, there was in the courthouse construction fund of said County out of which the expenditures to be made under the terms of said contract, were to be paid, the sum of $167,810.00, all of which was unappropriated and no contracts had been made by defendant payable out of said unappropriated balance of said fund; that said sum had been raised through the sale of bonds of the said County, authorized by vote of the qualified electors of said County for the purpose; and that all formalities in respect to advertising for bids and letting said contract were complied with prior to the execution and delivei*y of said contract.”
Respondent had judgment for the balance of $18,880.65, with interest, from which this appeal is taken.
Appellant assigns the overruling of the demurrer as error, claiming the complaint was insufficient because it did not negative the idea that the contract was in violation of the constitutional and statutory provisions above mentioned. The court did not err in this respect. These matters were affirmative defenses and properly treated as such.
The vital question in the case is whether the evidence is sufficient to support the finding that there was sufficient money available, properly appropriated, for the payment- of respondent’s claim at the time it was presented. Respondent contends that this question cannot be considered, because appellant does not properly specify in its brief the particulars in which the evidence is insufficient. While we do not commend the form in ^hich the question is presented, yet we think that, in substance and effect, the specifications of error in the findings may be considered as specifications of the insufficiency of the evidence.
The facts shown by the evidence are as follows: On June 3, 1919, the people of appellant county at an election authorized the issuance and sale of $250,000 of county bonds to build a courthouse and jail. These were sold at a premium of $3,175. Nighty-five dollars was added to the fund through the auction sale of some county property. The total available was thus $253,260. Approximately $12,500 was paid the architects. Thirty-one thousand six hundred and fifty dollars was paid for the foundation. Thirty-seven thousand five hundred dollars was paid for the site. All this happened before respondent’s contract was let. At the time of the letting of that contract there was only $167,810 in the courthouse fund. May 1, 1920, the board of commissioners ordered a call for bids for the erection and completion of the courthouse and jail. June 7th, at a meeting of the board the bids were opened and acted upon as shown by the following quotation from the minutes:
“June 7th, 1920. ‘This being the time heretofore fixed for receiving proposals for the erection and completion of a court house pursuant to an order and call for bids for the same made and entered on the first day of May, in the pursuance to the same the following bids and proposals under said order were submitted to this board at 2:00 p. m. on*311 tbe above named date. The board proceeded to open said proposals which were found to be as follows, to wit: For the erection and completion of said buildings less furniture and fixtures, as per plans and specifications as prepared by Fisher & Akin: D. J. Sweeney, $158,000; Salih Brothers, $162,320; North Pacific Construction Company, $152,525. The North Pacific Construction Company bid being the lowest and best bid," Andrew Burkman made a motion seconded by Christian Anderson that the contract for the erection of the court house be awarded to the North Pacific Construction Company, and a contract be • drawn to that effect. In the matter of bids for plumbing and heating for said court house, Bonneville County, Idaho, the following bids were submitted: George Tway, $23,165; Tarbet Heating & Plumbing Company, $20,900. The Tarbet Heating & Plumbing Company’s bid being the lowest and best bid, Andrew Burkman made a motion seconded by Christian Anderson, that said contract be awarded to the Tarbet Heating & Plumbing Company, and said contract be drawn to that effect.”
December 13, 1920, the county commissioners decided, on the advice of the architect, that certain additions should be made, to wit, an iron cornice and a fire wall. They asked only respondent to bid and accepted his bid of $5,975. It thus appears that June 7th the amount of money in the fund was $167,810 and the commissioners let contracts for the erection of the building and installing of the plumbing and heating totaling $173,425, and the addition of the extras brings the amount up to $179,400, being $11,590 in excess of the amount available. It certainly cannot be denied that both respondent’s contract and that of the heating and plumbing company were necessary for the erection and completion of the courthouse as authorized by the election and as contemplated by the call for bids and by the resolution authorizing the contracts. It is clearly proved that the cost of erecting the courthouse exceeded the income and revenue available for such purposes, and that therefore the indebtedness could not be incurred unless the necessary funds were
The district court acted upon the theory that there was enough money in the fund at the time the contract was let to pay the amount of respondent’s contract, because there was $167,810 available and the amount of respondent’s contract, even including the extras, was only $158,500; this in spite of the fact that immediately afterward, and as a part of the same transaction, the plumbing and heating contract was let in the amount of $20,900. In other words, it was held the county commissioners were properly exercising their power if they used practically all the money for the erection of the building and left nothing for the plumbing and heating. We cannot concur in this view of the matter. Naturally one contract had to be signed at least a few moments before the other. But, considering the
Under no possible view of the facts, or the law applicable thereto, was the trial court justified in adding the amount of the extras to the original contract price and making the whole amount a preferred claim. By the court’s own logic the plumbing and heating company’s contract for $20,900 had precedence of respondent’s claim for the extras.
The mone3r available was paid out as the work progressed until the fund was exhausted. If it had been misappropriated by the commissioners, that would constitute no defense to the county. But there is no evidence of misappropriation or improper use; on the contrary, the record shows a proper use and application of the fund. When respondent’s claim was presented to the board of commissioners, and this action was brought, the money available had been exhausted. The claim was properly denied by the board and respondent could not recover in assumpsit.
For the reasons given above the judgment is reversed, with costs to appellant.