DocketNumber: Nos. 13,749-13,751.
Citation Numbers: 173 N.E. 651, 95 Ind. App. 649, 1930 Ind. App. LEXIS 185
Judges: Nichols, McMahan
Filed Date: 7/3/1930
Status: Precedential
Modified Date: 10/18/2024
On May 11, 1927, Charles F. Hanley and J. Howard Laughlin, doing business under the name *Page 652 of Peerless Constructing Company, entered into a contract with the city of Tell City for the improvement of certain streets, and in that connection, they, as principals, with appellee insurance company as surety, executed a bond in the sum of $119,000, in which the city is named as obligee, conditioned that the construction company should faithfully and fully perform the contract according to the strict terms thereof, and expressly stipulating that "any person or persons, firm or corporation having unpaid claims for labor performed on the improvements required by this contract and required by these specifications, or for tools or materials furnished them to be used in or upon said improvement, may recover the same in an action or actions in their own names on this bond."
The Concrete Steel Company, appellant in No. 13,749 and the Truscon Steel Company, appellant in No. 13,751, each furnished said contractors steel and iron required and used in constructing said streets under said contract. The Hermitage Portland Cement Company, appellant in No. 13,750, furnished cement. Each appellant, as plaintiff, filed a complaint against said contractors and said insurance company on said bond to recover the balance owing each of them for the material so furnished and used in the construction of said streets. A demurrer was sustained to each complaint. This was followed by an appeal by each plaintiff and a consolidation of the three appeals for briefing and decision.
The complaint neither alleges that the plaintiff within sixty days after the last item of material was furnished nor at any other time, filed with the common council of the city or with any other board or office of the city, a verified statement of the amount due and owing plaintiff by said contractor. Each complaint was filed within one year from the date when the material was furnished.
Section 10284 Burns 1926, Clause 25, § 53, Acts 1905, *Page 653
p. 246, gives the common council of every city the power "to compel persons about to undertake dangerous improvements to 1. execute bonds, with sufficient surety, conditioned that the owner or contractor will pay all damages that may be sustained by any person from such work." Section 10342 Burns 1926, § 95 of the Municipal Code of 1905, Acts 1905, p. 281, gives the council authority to "impose further conditions upon bidders with regard to bond and surety, guaranteeing the good faith and responsibility of such bidders, or insuring the faithful completion of such work according to contract, or for keeping the same in repair for any length of time, or for any other purpose." This section gave the common council of the city of Tell City authority to require a bond for the protection of materialmen and laborers, as well as for the protection of the city, and each appellant was authorized to maintain an action thereon in its own name for materials furnished. Aetna IndemnityCo. v. Indianapolis, etc., Fuel Co. (1912),
Appellee insists there can be no recovery for the reason that neither appellant, within sixty days after the last item of material was furnished, filed with an officer of the city a duplicate verified statement of the amount due and owing in accordance with the provisions of § 6122 Burns 1926, which is section 2, Ch. 173, Acts 1911, as amended in 1925, Acts 1925, p. 129.
Section 1 of the act of 1911, provides that all boards of trustees of state institutions and commissioners appointed *Page 654 for the building of state buildings, county commissioners, township trustees, or any county or township boards authorized to contract for any public building or improvement, and officers or boards of state, county or township authorized to distribute funds and pay contractors, shall withhold full payment to the contractor until such contractor has paid the subcontractors or laborers employed, all bills due and owing them, with provision that if there is not a sufficient amount owing the contractor to pay such bills in full, the same shall be paid pro rata, and that the subcontractors or laborers shall file with the proper officer or board or commission their claim within thirty days from the completion of the work. Section 2 of this act provides that in all contracts for the construction of the state, county or township buildings or other public improvements, provision shall be made in the contract for the payment of labor and subcontractors by withholding funds sufficient from the contract price to pay for all labor and material and subcontractors, and that the bond given by the contractor be conditioned so that the sureties shall be liable for labor, material, and to the subcontractor, provided such parties shall file their claims within thirty days after the labor is performed or the material furnished.
Section 3 is as follows: "This act shall not be construed as conflicting with any other laws for the protection of labor, subcontractors or materialmen, but is supplemental thereto."
In Illinois Surety Co. v. State ex rel. (1911),
These two cases were followed in U.S. Fidelity, etc., Co. v.State, ex rel. (1919),
In 1925, the legislature, with knowledge of the construction which this court had placed on said Act of 1911, amended sections 1 and 2 of said act, Acts 1925, p. 129, §§ 6121, 6122 Burns 1926. Section 1 as amended provides that when any public work or improvement is being made "under contract at the expense of the state or at the expense of any county, city, town, township, school corporation or any other political subdivision or commission created by law" final payment shall be withheld until subcontractors, materialmen and laborers are paid in full. The time for filing claims is extended from thirty days to sixty days, and it is provided that the *Page 657 surety of the contractor shall not be released until the expiration of one year after the final settlement with the contractor. Section 2, as amended, provides that all contracts for the construction, erection, alteration, or repair of any public building or any other public work or improvement of any character whatsoever, as provided in section 1 of the act, shall make provision for the payment of subcontractors, laborers and materialmen by withholding funds from the contract price sufficient to pay such subcontractors, laborers and materialmen; that the contractor shall execute a bond, payable to the state, conditioned among other things for the payment by the contractor of all indebtedness on account of labor rendered and materials furnished; that any person to whom money shall be due on account of labor or materials shall, within sixty days after the labor is completed or after the last item of material is furnished, file with the board, commission, etc., entering into the contract with the contractor, duplicate verified statements of the amount due and owing; that no suit shall be commenced against the sureties on such bond until after the expiration of sixty days after filing such statements; that if the claim is not paid within thirty days, suit can be commenced on the bond, and which suit shall be commenced within one year from date of filing duplicate statements; and unless suit is commenced within such period it shall be barred as to such sureties. Section 3 of the Act of 1911 was not in any way amended or affected by sections 1 and 2 as amended in 1925.
In arriving at the effect of the amendments to sections 1 and 2 of the Act of 1911, we must consider the amendments as a part of the original act, and the entire act, which includes 4. section 3, must be given the same effect as if §§ 1 and 2, as amended, had been a part of the original act, and as to all matters thereafter *Page 658
occurring, such amendments are to be taken and construed the same as if they were a part of the act as adopted in 1911. Blair v.Chicago (1906),
If the rule announced in these cases is correct, and we think it is, it follows that it was the intention of the legislature that sections 1 and 2 as amended in 1925, must be construed 5. so as not to conflict with any other law for the protection of labor, subcontractors or materialmen, but as supplemental thereto as declared in section 3. This can be done only by following the holding of this court in Illinois SuretyCo. v. Lynch, supra.
As heretofore indicated, the city, prior to the enactment of the Acts of 1911 and 1925, had the authority to require the contractor to give the bond which is the basis of this 6. action. Indeed, the city, in the absence of any statute, had that power. The authority given the city to cause the streets to be improved carried with it the incidental power to do all proper acts reasonably necessary to that end. As was said by this court in Title Guaranty, etc., Co. v. State, ex rel.
(1915),
Appellant, in the absence of the Acts of 1911 and *Page 659 1925, had a right to prosecute an action on the bond, and had the absolute right to prosecute such action without filing any 7. claim with the city or any officer thereof. It is clear that the legislature did not intend to deprive a material man or laborer of any legal right they theretofore had. The right theretofore given to prosecute an action on the bond was neither curtailed nor destroyed. The right given by the Acts of 1911 and 1925, in the words of the legislature, "shall not be construed as conflicting with any other laws for the protection of labor, subcontractors or materialmen, but is supplemental thereto."
There can be no doubt but that in the absence of any statute giving appellant a right of action on the bond in controversy it would have had the right to prosecute the common law action 8. of debt thereon. It is well settled that a statute in derogation of the common law, or which affects a common-law right, will be strictly construed, and will not change the common law, or common-law rights, unless an intention to effect such change plainly appears from the express words of the statute or by necessary implication. Trustees, etc., v. New Albany WaterWorks (1923),
The Acts of 1911 and 1925 supplemented prior laws by creating a new right, a right to impound the funds, if desired by filing the claim as provided by the Act of 1911, and by filing the 9, 10. duplicate statements as provided in the Act of 1925. Instead of construing the statute to mean that a laborer or materialman must file duplicate statements of his account as contended by appellee, we hold that such party may, if he desires, file such statements and thus impound the money due the contractor. And if he exercises the right given him by filing the statements and thus impounds *Page 660 the money due the contractor, he takes such right subject to the provisions of the statute limiting and fixing the time within which an action can be prosecuted against the surety on the bond. The right to impound the funds being optional, appellant was not deprived of its right to maintain an action at law for a breach of the condition of the bond by reason of its failure to file the statements as provided in the Act of 1925.
In considering the action of the court in sustaining the demurrer to the complaint, we have assumed that the improvement in question was constructed at the expense of the city, so that appellant could have impounded the money due the contractor by filing the duplicate statements as provided by the Acts of 1925. We call attention, however, to the fact that the complaint contains no allegation as to whether the improvement is to be paid for out of assessments on the lands affected thereby or by the city. As heretofore noted the bond in question designated the city as the obligee. It was given pursuant to §§ 10284 and 10342,supra, and expressly provides that any one who furnished material to the contractors for use in the improvement might recover for the same in an action on the bond.
Our attention has been called to Zeidler Concrete Pipe Co. v.Ryan (1927),
Republic Iron Steel Co. v. Patillo (1926),
The statutes of Iowa and California are not to be compared with the statutes of this state. The statute, §§ 10282 and 10342,supra, authorizing the execution of the bond sued on in the instant case, does not require the filing of any claim, as is necessary when an attempt is made to impound the funds under section 6122, supra.
In harmony with the holding of this court in Illinois SuretyCo. v. State, ex rel., supra; and Equitable Surety Co. v.Indiana Fuel, etc., Co., supra, we hold that appellants not having exercised their right to impound the funds, were not required to file the itemized claims as provided in § 6122,supra, and that the demurrer to each of the several complaints should have been overruled.
Judgment reversed.
Nichols, J., dissents and reserves right to file dissenting opinion.