Citation Numbers: 214 N.W. 687, 203 Iowa 1324
Judges: Vermilion, Stevens, Faville, De Graff, Albert, Morling, Kin-Dig, Evans
Filed Date: 1/19/1926
Status: Precedential
Modified Date: 10/19/2024
The plaintiff is the assignee of certain paving certificates issued by the city of Marshalltown in 1918 to the Western Construction Company, a paving contractor, for the payment of a portion of the cost of a street improvement constructed under contract with the city. *Page 1326
The defendants, other than the city and the county treasurer, are owners of property against which assessments were levied, who appeared before the city council and filed objections to the assessments. The objections were overruled by the council, the assessments were confirmed, and the certificates issued. Such property owners purported to appeal in due time to the district court from the action of the city council. The city appeared in the district court, where the appeals were consolidated for the purpose of trial, and upon a trial, the property owners prevailed. There were decrees sustaining the objections, finding that the paving contract had not been substantially performed, and canceling the certificates.
By this proceeding the plaintiff challenges the validity of the decrees, for want of jurisdiction in the court to entertain the appeals and enter the decrees. This attack is upon two grounds: (1) That the property owners waived their right to file objections before the city council, in that the objections were not filed within the 20-day period provided by Section 823, Code of 1897, and that the city council had no jurisdiction to hear objections filed after the expiration of that period; (2) that the property owners failed to perfect valid appeals to the district court, in that the notices of appeal, though served upon the mayor, as required by statute, were addressed only to the "city of Marshalltown," and that the district court, therefore, acquired no jurisdiction to pass upon the appeals.
I. Section 823, Code of 1897, required the city council to give at least 10 days' notice, by publication and posting, that, within 20 days after the first publication, all objections to the assessments must be made in writing and filed 1. MUNICIPAL with the clerk. The council caused to be CORPORA- published and posted a notice that notified TIONS: property owners to file their objections on or special before January 6, 1918. The first publication assessments: was on December 13, 1917. The notice published timely departed from the letter of the statute, in that objections. the date therein fixed as that on or prior to which objections must be filed, was more than 20 days after the first publication. The objections were filed on January 5th, before the date fixed in the notice, but after the expiration of 20 days from the first publication. The action of the property owners was strictly responsive to the notice, according to its terms. It cannot be *Page 1327 said that, notwithstanding the terms of the notice, property owners must have filed their objections within 20 days after the first publication, or be held to have waived objections to the assessment; that the council could publish a deceptive notice, and thereby mislead the property owners, and induce them to delay filing their objections until after the lapse of the statutory period, and yet assert the validity of the notice and a waiver of objections by property owners whom the notice deceived.
Again, if the council had no jurisdiction, as contended by appellant, it was because there was no notice. Unless the notice given was valid, there was no notice. But if no notice was given, there was no waiver of objections by the property owners; for they were not required to file their objections or suffer the consequences of a waiver until the notice was given, and without notice, they were not required to file them within any given time. If the council had no jurisdiction, it had no power to approve the assessments or issue the certificates. It is apparent that the variance between the requirement of the statute and the terms of the notice cannot avail the appellant. No prejudice resulted; and, in any event, only the property owners could complain of the invalidity of the notice.
II. Special reliance is put upon the contention that the notice of appeal to the district court was insufficient in form to confer jurisdiction on the court. Each property owner purported to appeal from the assessment ordered by the 2. MUNICIPAL council. Notice of each appeal was served in due CORPORA- time, service being accepted by the mayor of the TIONS: city in due form. The notice was addressed to special the city of Marshalltown. The complaint is that assessments: it was not addressed to the mayor; and appellant appeal: relies upon In re Paving Assessments, 193 Iowa notice: 1234; and Farmers' St. Sav. Bank v. Town
proper Council,
In Lundy v. City of Ames,
"In the absence of some specific statutory requirement, the *Page 1328 general rule undoubtedly is that, where a notice of appeal is properly addressed to the adverse party by name, it is sufficient in form; and if such adverse party be an artificial or corporate body, service of such notice upon officials or agents specified by the statute is a good service upon the adverse party, and confers jurisdiction over it, even though the name of the official or agent be not included as an addressee."
Section 839, Code of 1897, provided that an appeal might be taken by any person affected by the levy of a special assessment, "by serving written notice thereof upon the mayor or clerk." That statute, in force at the time of the instant appeals, contained no requirement as to the addressee of the notice. It is to be noted, however, that Section 6064, Code of 1924, provides that the notice of appeal in such cases shall be "directed to the defendant." We are of the opinion that the notices in question come within the rule announced in Lundy v. City of Ames, supra, rather than that of the cases relied upon by appellant, and that the notices of appeal addressed to the city of Marshalltown were sufficient in form to confer jurisdiction upon the district court to hear and determine the appeals. No appeal was taken from the decrees of the district court canceling the assessments, and they became final. The conclusion so reached is determinative of appellant's claim against the defendant property owners, unless the further contention that, since neither the appellant nor its assignor, the contractor, was a party to the appeals, the judgments therein are not conclusive as to it, must be sustained.
III. The appellant, as assignee of the certificates, does not claim to stand in the attitude of a holder in 3. MUNICIPAL due course of negotiable paper. It stands in the CORPORA- shoes of its assignor, the contractor. It took TIONS: the assignment while the appeals were pending. special The certificates appear to have been prematurely assessments: issued, before the determination of the appeals, appeal: but the rights of the parties cannot be affected effect on by that fact. The appellant took them subject to assignee of the outcome of the appeals. prematurely issued certifi- cates.
The contractor's rights, as against the property owners, were subject to a proper exercise of the power of the city council to make the assessments. The exercise of this power was subject to review on appeal in the district court. Appeal from the *Page 1329
action of the city council in levying an assessment for street improvements is the method provided by statute for contesting the amount and validity of the assessment. Section 839, Code of 1897 (Sections 6063 and 6065, Code of 1924). While the property owner and the city are the only necessary parties to the appeal, the final judgment is conclusive as to the liability of the property assessed for the assessment, not only as against the city, but as against the contractor, who, in that respect, claims only through or under the procedure of the council. This must be true; for the rights of the contractor against the property assessed are created by statute (Snouffer Ford v. City of Tipton,
The rights of the appellant as the holder of the certificates are those of a mere assignee, and rise no higher than the rights of the contractor. The final decrees of the district court on the appeals were conclusive as to the rights of the appellant against the property assessed.
IV. The defendant property owners filed cross-petitions, wherein they tendered the same issues as were tried on the original appeals, alleging the failure of the contractor to substantially perform the contract. The only 4. PLEADING: proper function of these cross-petitions was to irrelevant quiet the title of the defendants, in so far as matter: the claims of the appellant operated as a cloud motion to upon their titles. And this result depended on strike. the binding effect of the original decrees as respects the right to enforce the assessments against the property, and not upon a readjudication of the facts pleaded in avoidance of the assessments. If the original decrees were valid, the property owners had no need of a readjudication on the facts. If they were not valid, then these defendants had lost their day in court.
The decree below sustained all the allegations of the cross-petitions, and canceled again the assessments which had been first canceled by the original decrees. The decree in this respect, viewed merely as quieting title, as against the cloud of appellant's asserted claim, was not prejudicial to appellant, save only in the matter of costs; for, as we have seen, the *Page 1330 adjudication of the original decrees was binding on the appellant, so far as the right to subject the property to the payment of the assessments was concerned.
A large amount of testimony was, however, taken, over appellant's objection, on the question whether the contract had been substantially performed by the contractor. This issue was not properly in the case, as between appellant and the property owners. It had been adjudicated in the original decrees; and, as we have said, that adjudication was binding on the appellant, as against the property owners; and the latter in this action must stand or fall on the validity of that adjudication. Whether costs of the appeals should be apportioned in this court because of the record upon this issue will be considered, upon proper motion.
In view of our conclusion upon another branch of the case, the claim of appellant against the city, to be presently considered, it should be said further that, for the reasons stated, and also because the petition had been dismissed as against the city, upon the appellant's election to stand on the ruling sustaining the city's demurrer, the adjudication upon the cross-petitions is not conclusive, as between the appellant and the city.
V. In the amended and substituted petition it was alleged that, after completion of the work, the city engineer and the city council inspected the work covered by the contract, and found that it had been completed according to the 5. MUNICIPAL contract, and the city council by resolution CORPORA- accepted the same. It was alleged that "the TIONS: Western Construction Company completed and special performed its contract, and did all the things assessments: required to be done in making said improvement fraudulent under its contract." It was also alleged that failure of "the fact that the Western Construction Company city to had thus performed its contract was well known defend to the defendant city and its officers;" that assessments: "the defendant city and its officers knew and effect. had evidence within possession of said officers that the Western Construction Company had fully completed and complied with its contract;" that "the defendant city and its attorney deliberately and designedly failed to introduce in the attempted trial on said appeals any evidence whatever;" that, "on the contrary, the city attorney deliberately refrained from so doing, although evidence was within the *Page 1331 knowledge and control of the mayor and city council * * * to show that the Western Construction Company had completely and fully complied with its contract;" and that the city attorney "wrongfully, willfully, and fraudulently, for the purpose of enabling the appellants to succeed in said alleged appeals, refrained from introducing any evidence and refrained from making any argument in the case."
The plaintiff prayed in the alternative that, if the court should hold that the decrees canceling the assessments were valid, and that the assessments had been legally canceled, then, because of the fraud of the city in its failure to properly defend the appeals, it should be decreed, as against the city, that the plaintiff's assignor had completed and performed its contract, and that plaintiff should recover from the city the amount of the assessments so levied, with interest. The demurrer of the city admitted the well pleaded allegations of the pleading assailed. Was a cause of action pleaded, as against the city?
This question must be determined on the allegations of the amended and substituted petition, and quite apart from the evidence introduced on the trial between the appellant and the other parties defendant after the demurrer was sustained.
While, as has been said, the adjudication on the appeals from the assessments was binding on the appellant as to the validity of the assessments against the property, it is to be remembered that neither the contractor nor the appellant was a party to the appeals. An adjudication is binding only upon parties and privies to the action. It is urged on behalf of the city that, notwithstanding this general rule, the appellant is bound by the adjudication on the appeals that the contract was not substantially performed, and reliance is put upon certain of our decisions, as sustaining the position. A brief consideration of the cases cited will show that they afford no support for the contention.
Wingert v. City of Tipton,
Mason v. City of Des Moines,
Atkinson v. City of Webster City,
As between the contractor or the appellant, its assignee, and the city, the rights of the parties arise out of, and depend upon, the contract. The appeals from the assessment made by the city council involved only the statutory right of the city to levy an assessment against the property. While the exercise of this right might be defeated by the failure of the contractor to perform, the contractor was neither a party nor a privy to the proceedings on the appeals, and was not bound or estopped, as against the city, by the adjudication on the appeals that the contract had not been performed.
We may add that the pleadings do not disclose that any action was taken by the city to require the contractor to appear and defend against the claims of the property owners on the appeals or suffer the consequence of being bound by the judgments to be therein rendered, if by appropriate action such a result might have been brought about.
The contract provided that the cost of the improvement was assessable against private property, and that the duty and liability of the city to the contractor, or any person claiming under him, should be confined to its power to impose the assessment and deliver the assessment certificates to the contractor, or person entitled thereto, unless an amount legally assessable should be insufficient, in which case the difference should be made up from the general or other appropriate fund or funds of the city, and that any "deficiencies of any character whatever which are not legally assessable against privately owned property * * * *Page 1333 shall be payable in accordance with the provisions of the resolution ordering the improvement."
In Bucroft v. City of Council Bluffs,
"When the city admitted the existence of a debt, and issued certificates of assessment, to the end that the plaintiff could be paid out of a particular fund created by the city, it must be assumed that it guaranteed, or by implication contracted, that such fund existed, or that it had taken, and had the power to take, the steps necessary to create such fund. Now, when it turns out that there was no such fund, and that the power to create it did not exist, it seems to us that the city should not and cannot escape all liability under the contract, and it has been so held."
In Ft. Dodge E.L. P. Co. v. City of Ft. Dodge,
In Turner Imp. Co. v. City of Des Moines,
Gilcrest Co. v. City of Des Moines,
"This defect is chargeable to the city or its officers and not to the contractor, and, in the event that upon further hearing it is found that the contract has been substantially performed, then, so far as the cost of the improvement would otherwise have been chargeable upon these lots, the contractor will be entitled to judgment against the city."
It was subsequently determined that there had been a *Page 1334
substantial compliance with the contract. Gilcrest Co. v. Cityof Des Moines (Iowa), 161 N.W. 645 (not officially reported). Thereafter, a recovery by the contractor from the city to the amount of the invalid assessment was affirmed in Barber A.P. Co.v. City of Des Moines,
"The failure of the city to create and issue a valid certificate of assessment * * * was a breach of the contract between it and the Barber Asphalt Paving Company, entitling the contractor to damages sustained by such failure on the part of the city."
The doctrine of these cases would seem to be controlling here, under the allegations, admitted by the demurrer, that the contract was performed and the work accepted by the city, and that the failure of the city to make valid assessments was the result of the fraudulent failure of the city and its officers to make proper defense in the appeals. If, as alleged, there was a substantial performance of the contract, — a proposition upon which the appellant was entitled to its day in court, as against the city, — the invalidity of the assessments against the property resulted wholly from the fraudulent failure of the city to defend its assessments on appeal.
If a city cannot escape liability for a loss of interest occasioned to a contractor by its negligent delay in making an assessment, or for the amount of an assessment which is invalid because of its failure to take proper proceedings, or for its failure to assess the total cost of the improvement against property subject to assessment, we see no sound reason why it can avoid liability where the failure of the assessment was brought about by its own fraud. We are of the opinion that the amended and substituted petition stated a good cause of action against the city, and that the demurrer should have been overruled.
The judgment in favor of the city is reversed, and that in favor of the other defendants is affirmed. One tenth of the costs on appeal will be taxed to the city, and the remainder to the appellant, subject to apportionment, upon motion, as between appellant and the other appellees. — Affirmed in part; reversedin part.
STEVENS, FAVILLE, De GRAFF, ALBERT, MORLING, and KINDIG, JJ., concur. *Page 1335
EVANS, C.J., dissents in part.