Citation Numbers: 69 Iowa 693, 25 N.W. 909
Judges: Beck
Filed Date: 12/16/1885
Status: Precedential
Modified Date: 10/18/2024
I.- The petition, after alleging the corporate character of plaintiff, proceeds to state its cause of' action in the following language: “That July 10, 1882, defendant executed and delivered to plaintiff his written contract, in words following, viz.:
“ ‘Villisca, Iowa, July 15, 1882.
“ ‘I hereby agree to build (or cause to be built) on lot' 244, in Villisca,-Iowa, a„ good, substantial brick building, forty feet wide and eighty feet long, two stories high, and to be completed during the year 1883,. and, in case of failure to Wild by the time specified, I hereby agree to pay the directors of the First National Bank of Villisca, Iowa, the sum of five hundred dollars, (forfeit,) provided, the said bauk shall build a banking-house on the opposite side of the street, on lot No. —M. S. Thurman.’
“That said baiik did, at great expense, build a banking-house on said lot No. —, in said town of Villisca, the said lot being on the opposite side of the street from said lot 244, and completed and occupied the same in the early part of the' year 1883, and have ever since occupied the same as a bank. Defendant has wholly failed and neglected to comply with the terms of said contract. He has neither built, nor caused to be built, a building on said lot 244, and has wholly failed to
The demurrer to the petition is in the following words: “ (1) The pretended contract is void, it not being within the scope or powers of a national bank to make or enter into such a contract. (2) The petition shows upon its face that it is an action brought upon a pretended contract which is against public policy, contrary to the law, -and void. (3) Here are no statements or allegations of facts in said amended and substituted petition, or the amendment thereto, constituting a claim for damages on a contract of forfeiture, and said pleading states no facts showing a right to recover.”
II. Without consideration of the first and second grounds of the demurrer, we reach the conclusion that it was rightly sustained'upon the third. As we understand the petition, plaintiff seeks to recover upon two grounds, namely: (1) The banking-house cost plaintiff more than it would have cost if built elsewhere. (2) The house, after its construction, is of less value than it would have been had defendant erected the building in accord with his agreement.
III. The petition does not allege that the plaintiff would
IY. The damage claimed on the ground of the diminished value of the banking-house is extremely uncertain, remote and speculative, and, on account of this character, is not recoverable in an action on the contract. We are unable to discover bow the damages claimed by plaintiff, by reason of the loss on the value of bis bouse, could be determined, except by the most vague estimate, based upon speculation as to possible diminution of business, and the like.
We reach the conclusion that the judgment of the circuit court ought to be
Affirmed.