Citation Numbers: 63 Iowa 152, 18 N.W. 851
Judges: Reed
Filed Date: 4/8/1884
Status: Precedential
Modified Date: 11/9/2024
I. Section 2583 of the Code provides that an action may be brought on a contract relating to the construction of a railway, or for labor performed thereunder, in any county where the contract was made or performed in whole or in part, or where the work was performed. When the motion to transfer the case to Polk county was submitted and disposed of, the pleadings contained no allegation that the contract had been performed, or the work done, in Boone county, but plaintiff was allowed to establish these facts by affidavit, on the hearing of the motion. These facts were not material to plaintiff's right to recover; they related only to his right to prosecute his suit in that county. He is required to set out in his petition only the facts which constitute his cause of action. Code, § 2646. If he had alleged them in his petition, defendants would certainly not have been concluded by the allegation, but on the hearing of their motion they would have been entitled to show by evidence that the suit was brought in the wrong county. It was not error, then, for the court to determine the question on the evidence on which the motion was submitted.
2. ___: motion for change to place of residence: merits of cause not determined by.
It is contended by appellants, however, that, while it may be true that the suit as against Kavanaugh was properly brought in Boone county, as to the sureties on the bond the motion to transfer should have been sustained. The ground of this claim, as we understand it, is that, by the terms of the bond, the sureties are not liable for claims of the character of that sued on; that, while Kavanaugh may be liable for the claim under the original contract with the construction company, by the terms of this bond the sureties are liable only for damages resulting from his failure *Page 155 to complete the work within the time or in the manner provided in the contract.
But this question relates to the right of plaintiff to recover at all as against the sureties, and it could not be determined on this motion. The only question raised by the motion was, whether defendants were entitled to have the question, whether they were liable on the claim which plaintiff was asserting against them, tried in another county.
3. PRACTICE upon demurrer: exception to ruling on: what sufficient.
II. Appellee contends that the ruling on the demurrer to the petition cannot be reviewed, because, first, no exception was taken to the judgment, and, second, defendants waived the demurrer by answering over. Neither of these positions is correct. Defendants excepted to the overruling of the demurrer, and this exception was made matter of record. This preserved the questions raised by the demurrer, and it was not necessary to except again when the final judgment was entered. When a party has once properly made his exception to an adverse ruling, he does not waive it by failing to except to some other decision which involves the same question.
4. ___: waiver of exception by pleading over: facts not constituting.
The rule is that a party waives the demurrer by pleading over and going to trial. The reason of the rule is that by pleading over he puts upon his adversary the burthen of proving the allegations of his pleading, and it would be unjust to permit him, after he has had the advantage of a trial of the issues, to go back and take the benefit of his demurrer. Wilcox v. McCune,
4. BOND to secure performance of contract: construed in light of contract.
III. The grounds of the demurrer to the petition are, that there is no privity of contract between plaintiff and defendants, and that the bond was not intended to secure any party except the obligor named therein; and that plaintiff cannot maintain an action thereon. *Page 156 Copies of the contract and bond are attached as exhibits to the petition. The contract provides that the work shall be done within a specified time, and that it shall be done in a substantial and workman-like manner, to the satisfaction and acceptance of the chief engineer of the construction company.
It also provides that, if any damage is done by the contractor or men in his employ, to lands or property in the vicinity, the engineer shall have the right to estimate the amount of such damages and pay the same to the owner of the property injured, and deduct the same in his first estimate thereafter. It also contains the following stipulation: "The said first party (Kavanaugh) agrees to pay all just claims against them (him) or against any sub-contractor under them (him) for service or labor performed or material furnished in the work under this contract, and to pay or cause to be paid all just claims growing out of said work, whether against them (him) or their (his) sub-contractors, for trespass, injury to lands, destruction of fences, and for land for waste material, and all claims for provisions and supplies, and bills for board of men and teams engaged upon such work, and all similar claims; said damage to be estimated as specified in the preceding clause." It also provides that the contractor shall give a bond in the sum of ten thousand dollars, with sufficient sureties, for the faithful performance of the contract, and for the security of the construction company against all persons performing labor upon or furnishing materials for the work under or by virtue of the contract.
The condition of the bond is as follows: "That whereas, Marcus Kavanaugh, Jr., as principal, has this day entered into a contract with said Narrow Gauge Railway Construction Company, a copy of which is hereto attached and made a part hereof: Now if the said Marcus Kavanaugh, Jr., shall well and truly comply with said contract in the time and manner herein provided, then this obligation shall be void, otherwise in full force and effect." *Page 157
The position of counsel for appellant is, that the sureties on the bond are not liable on the contract further than the express terms of the bond imply, and that, by these express terms of the bond, they have undertaken only that Kavanaugh will do the work within the time and in the manner provided in the contract.
But this position, we think, is not correct. It is provided in the contract that a bond should be given by Kavanaugh in an amount stated, and with certain conditions. The bond recites that Kavanaugh has entered into a contract as principal. A copy of the contract is attached to the bond, and declared to be a part of it, and the undertaking of the bond is that Kavanaugh shall well and truly comply with said contract in the time and manner herein provided. The plainest rules of construction require that the two instruments shall be read together in determining the undertaking of the obligors in the bond. 2 Parsons on Contracts, 503.
We think it clear that the bond was intended as a security that Kavanaugh would not only perform the work in the time and manner provided in the contract, but that he would perform every other covenant contained in it; and this is its effect.
6. ___: third person intended to be secured may sue thereon.
The next position is that the bond was intended only as a security to the obligee named therein, and that plaintiff cannot maintain an action thereon. The argument is that, as the parties who might perform labor or furnish material for the construction of said work would have a lien on the property under the mechanic's lien law for the security of their claims, and as the owners of the property might be compelled to pay such claims for the protection of the property, notwithstanding they had paid the contractors for doing the work, the manifest purpose of the parties was to afford the construction company a remedy against this liability.
It is probably true that the primary object of the construction company in requiring the bond to be given was to secure *Page 158 the protection of its own interest. But the undertaking of Kavanaugh, as expressed in the contract, is not simply that he will repay to it such sums as it may be compelled to pay in the protection of its interests, or that he will pay the claims of such parties as may establish their liens on the property, but "that he will pay all just claims against him, or against sub-contractors under him, for service or labor performed," etc.; and the bond, as we have seen, is a security for the performance of this undertaking; so that, whatever the primary or principal object of the parties may have been, they have undertaken that plaintiff's claim shall be paid, regardless of whether or not the steps have been taken which would have compelled the construction company to pay it. Section 2552 of the Code provides that, "when a bond or other instrument given to the state, or county, * * * * * or to any officer or firm, is intended for the security of the public generally, or of particular individuals, suit may be brought thereon in the name of any person intended to be thus secured, who has sustained an injury in consequence of the breach thereof."
Under the provisions of this section, plaintiff has the right, without doubt, to bring suit on the bond in his own name. We think the demurrer was properly overruled, and the judgment is accordingly
AFFIRMED.
*Page 491
Bourrett v. W. M. Bride Construction Co. , 248 Iowa 1080 ( 1957 )
Builders Material & Supply Co. v. J. B. Evans Construction ... , 204 Mo. App. 76 ( 1920 )
Clinton Bridge Works v. Kingsley , 188 Iowa 218 ( 1920 )
Preston v. Howell , 219 Iowa 230 ( 1934 )
Westinghouse Electric Corp. v. Mill & Elevator Co. , 254 Iowa 874 ( 1962 )
Knight v. Fox Caldwell Theatres Corporation , 70 Idaho 148 ( 1949 )