Citation Numbers: 292 S.W. 790, 219 Ky. 279, 1927 Ky. LEXIS 311
Judges: McCandless
Filed Date: 3/25/1927
Status: Precedential
Modified Date: 10/19/2024
Reversing.
This is a suit to condemn a strip of land 100 feet wide and 2,000 feet long over the farm of Tom Shanklin for the purpose of acquiring an easement upon and over which to erect a transmission line. In the county court Shanklin recovered $800.00 in damages. On appeal to the circuit court the jury returned a verdict and the court entered a judgment in his favor for $850.00. The condemnor, Kentucky-Tennessee Light Power Company, appeals. *Page 280
Pending the proceedings the line has been constructed. Appellee owns a farm of 100 acres. The strip of land condemned passes through three fields at the back of his farm and within 80 feet of his stable. It does not appear that any crops were destroyed in the construction of the line though three strings of fence were severed and gates erected thereon. Seven posts were planted and the workmen hauled material back and forth along the line while it was being constructed. Shanklin has not been required to build any additional fences or make any improvements on the easement, which is in other respects similar to those usually condemned for the purpose mentioned. Appellee fixed the value of his farm, with the easement upon it, at $3,500.00, and its value without the easement at $4,500.00, and does not claim the land taken differs in value from that remaining. A number of other witnesses corroborated him in this. All of those witnesses were under the impression that the easement would divide the farm into two tracts. They disregard the right of the owner to any use of it, and seem to think it would constitute a turning point in the cultivation of the adjacent lands, though when the character of the use is explained to them they adhere to their original estimate of damages. They also lay some stress on broken wires and lightning.
On the other hand, the commissioners appointed in the county court fixed the damage at $100.00, and testified to the same effect on the trial. It thus appears that there is a conflict in the evidence as to the amount of damages based on the opinion of the witnesses, but when analysed the opinions of appellee's witnesses were largely based on a misconception of fact. It is uniformly held that the opinion of witnesses who are familiar with land values is competent evidence in cases of this character, but the value of their testimony depends on the facts upon which their opinions are based; and we have held that unless based on sufficient facts the probative weight of their testimony is weakened and the court will more readily set aside a verdict based thereon, as being against the weight of the evidence, than it will in cases where there is a conflict of evidence upon primary facts. See Ky. Hydro-Electric Co. v. Reister,
3. On another trial the court will not authorize a majority verdict. L. N. R. R. Co. v. Lang,
4. As given, instruction No. 1 describes the easement and No. 3 defines the rights of both parties under the easement. Number 1 also embraces the measure of damage. On another trial this element will be omitted from instruction No. 1; instruction No. 3 will be marked No. 2, and a separate instruction may be given substantially as follows:
You will find for the defendant such a sum in damages as you may believe from the evidence is the fair and reasonable market value of the strip of land taken for the easement, less the reasonable market value of such strip of land for use and occupancy, subject to the easement, as defined in instructions No. 1 and No. 2. And will further award him such direct damages, if any, as you may believe from the evidence will result to the remainder of the tract of land by reason of the condition in which it is left by the placing of the easement on the strip above described, but the total amount found shall not exceed the difference between the fair and reasonable market value of the entire farm immediately before and immediately after taking by the plaintiff of the easement, nor the amount claimed in the petition, $1,400.00.
Wherefore, the judgment is reversed and cause remanded for proceedings consistent with this opinion. *Page 282
City of Hazard v. Combs , 213 Ky. 750 ( 1926 )
Logan County v. Davenport , 214 Ky. 845 ( 1926 )
Kentucky Hydro-Electric Co. v. Reister , 216 Ky. 303 ( 1926 )
Warfield Natural Gas Company v. Wright , 233 Ky. 378 ( 1930 )
Kentucky Utilities Company v. Hunt , 221 Ky. 723 ( 1927 )
Petroleum Exploration v. McGeorge , 225 Ky. 131 ( 1928 )
Saulsberry v. Kentucky & West Virginia Power Co. , 226 Ky. 75 ( 1928 )
Kentucky & West Virginia Power Co. v. Saulsbury , 231 Ky. 788 ( 1929 )
Franklin County v. Bailey , 250 Ky. 528 ( 1933 )
Salt River Rural Electric Cooperative Corp. v. Thurman , 275 S.W.2d 780 ( 1955 )
Kentucky & West Virginia Power Co. v. May , 245 Ky. 333 ( 1932 )