DocketNumber: No. 2015-CA-0915
Citation Numbers: 217 So. 3d 566, 2015 La.App. 4 Cir. 0915, 2016 La. App. LEXIS 521
Judges: Bagneris, III, Jenkins, Ledet, Lobrano, McKay
Filed Date: 3/16/2016
Status: Precedential
Modified Date: 10/19/2024
Iiln this public bid case, appellant Durr Heavy Construction (“Durr”) appeals the portion of the district court’s judgment of July 30, 2015 denying Durr’s petition for injunctive relief to enjoin the awarding of a public work contract. For the reasons which follow, the district court’s order denying injunctive relief is reversed, and this matter is remanded to district court for proceedings consistent with this opinion.
FACTUAL AND PROCEDURAL HISTORY
On March 24, 2015, the City of New Orleans (“City”) issued an Invitation to Bid on a public work for the paving of streets in Lakeview pursuant to the Louisiana Public Bid Law, La. R.S. 38:2211, et seq. (“Public Bid Law”). On page one of the Invitation to Bid, the City identified the public work with Proposal Number 500C-01811 and with the Project Name as “Lakeview Quad 2 Pavement-2012FEMA-1C-2A.” On the same page, the City instructed that bids should be | ¡¡submitted either online or in sealed envelopes bearing the Proposal Number and a Louisiana State Contractor’s License Number.
Durr filed a protest with the City, arguing that the two lower bids were non-responsive, because they did not include the Proposal Number on the front of their submission envelopes as required by the Invitation to Bid. The City denied Durr’s protest, and Durr sought injunctive and other relief in district court which was denied. Durr appeals, arguing that the district court committed legal error by allowing the City to waive a non-waivable provision of the bidding documents, and requesting that we reverse the district court’s denial of the preliminary injunction, and remand this matter to district court. In its appeal, Durr identifies two assignments of error/issues for review: (1) whether the district court erred in | concluding that a requirement stated in the bidding documents was waivable; and (2) whether under the Public Bid Law, the City has any discretion to waive a stated requirement for “good reason.”
DISCUSSION
When a petitioner seeks to enjoin conduct in direct violation of a prohibitory law, it must demonstrate the following: “first, that the conduct violates a prohibitory law (ordinance or statute) or the constitution; second, that the injunction seeks to restrain conduct, not order it; and third, that the plaintiff has met the low burden of making a prima facie showing that he is entitled to the relief sought.” Yokum v. Pat O’Brien’s Bar, Inc., 2012-0217, pp. 8-9 (La.App. 4 Cir. 8/15/12), 99 So.3d 74, 81. Generally, “[i]n reviewing the denial of a preliminary or permanent injunction, an appellate court uses the abuse of discretion standard of review.” Smith v. Tsatsoulis, 2014-0742, p. 5 (La.App. 4 Cir. 1/14/15), 158 So.3d 887, 890. This deferential standard is “based upon the conclusion that the trial court committed no error of law....” Smith v. Brumfield, 2013-1171, p. 7 (La.App. 4 Cir. 1/15/14), 133 So.3d 70, 75.
This appeal calls for us to interpret Louisiana’s Public Bid Law, La. R.S. 38:2211 et seq. As it is a matter of statutory interpretation, our standard of review of the district court’s legal conclusion is de novo. Dynamic Constructors, L.L.C. v. Plaquemines Par. Gov’t, 2015-0271, p. 4 (La.App. 4 Cir. 8/26/15), 173 So.3d 1239, 1243.
^Louisiana’s Public Bid Law governs the manner by which all contracts for public works are to be awarded. Id. at pp. 5-6, 173 So.3d at 1243-44. It was enacted in the interest of the taxpaying citizens, to protect against favoritism in contracting by public officials resulting in exorbitant and extortionate prices. Id., citing Haughton Elevator Div. v. State Div. of Admin., 367 So.2d 1161, 1164 (La.1979); Concrete Busters of Louisiana, Inc. v. Board of Comm’rs of the Port of New Orleans, 10-1172, p. 4 (La.App. 4 Cir. 2/2/11), 69 So.3d 484, 486. As such, it is “a prohibitory law founded on public policy,”
Relevant to the case at bar is La. R.S. 38:2212, which provides:
A. (1) All public work exceeding the contract limit as defined in this Section, including labor and materials, to be done by a public entity shall be advertised and let by contract to the lowest responsible and responsive bidder who had bid according to the bidding documents as advertised, and no such public work shall be done except as provided in this Part.
(2) The term “bidding documents” is defined in R.S. 38:2211(A).
B. (1) The provisions and requirements of this Section and those stated in the bidding documents shall not be waived by any entity.
La. R.S. 38:2212 (emphasis added).
“ ‘Bidding documents’ means the bid notice, plans and specifications, bid form, bidding instructions, addenda, special provisions, and all other written instruments prepared by or on behalf of a public entity for use by prospective bidders on a public contract.” La. R.S. 38:2211(A)(2).
IfiThus, according to the plain language of the statute, the provisions and requirements stated in the City’s Invitation to Bid are not waivable.
Notwithstanding these provisions, the City maintains that in choosing to disregard the provision in the Invitation to Bid directing bidders to include the Proposal Number on the front of the bid envelope, it did not waive a requirement, but rather made a reasonable, good-faith interpretation of an unclear term in its bidding documents.
We disagree. Applying the plain language of the Public Bid Law, we find that the City did not have the discretion to waive the provision in its Invitation to Bid which directed bidders to include the Proposal Number on the front of the bid envelope.
We have also considered TKTMJ’s argument that the Proposal Number is waiva-ble because it is not a “requirement” of the bidding documents as set forth in La. R.S. 38:2212(B). That statute provides in part:
*570 (2) Any public entity advertising for public work shall use only the Louisiana Uniform Bid Form as promulgated in accordance with the Administrative Procedure Act by the division of administration, office of facility planning and control. The bidding documents shall require only the following information and documentation to be submitted by a bidder at the time designated in the advertisement for bid opening: Bid Security or Bid Bond, Acknowledgment of Addenda, Base Bid, Alternates, Signature of Bidder, Name, Title, and Address of Bidder, Name of Firm or Joint Venture, Corporate Resolution or written evidence of the authority of the person signing the bid, and Louisiana Contractors License Number, and on public works projects where unit prices are utilized,, a section on the bid form where the unit price utilized in the bid shall be set forth including a description for each unit; however, unit prices shall not be utilized for the construction of building projects, unless the unit prices and them extensions are incorporated into the base bid or alternates. (Emphasis added.)
TKTMJ contends that the foregoing suggests that the non-waivable require-, ments of the bidding documents are limited to the exclusive list of items set forth in the above provision, and a public entity may impose no further non-waivable requirements upon bidders.
However, we note that the broad, mandatory non-waiver language of La. R.S. 38:2212(B)(1) is not limited to the statutory requirements of 38:2212(B)(2). Rather, it states that “[t]he provisions and requirements of this Section and those stated in the bidding documents shall not be waived by any entity.”' La‘. R.S. 38|2212(B)(1) (emphasis added). Thus, even if we were to adopt the view that the non-waivable requirements of the bidding documents are limited to those specifically listed in 38:2212(B)(2), that does not negate the fact that under La. R.S. 38:2212(B)(1), any other provisions stated in the bidding documents are also non-waivable. In the case sub judice, the Invitation to Bid clearly provided that the bid envelope must contain the Proposal Number. TKTMJ’s and Roubion’s did not. Construing the Public Bid Law strictly (as we must), TKTMJ’s and Roubion’s bids are non-responsive.
We acknowledge that this analysis results in the lowest bidders being rejected on a technicality, with the unfortunate consequence that the City may have to incur additional expense to complete this public work. However, we are constrained by the statute as written, and we recognize that the trend of the numerous revisions to the Public Bid Law and to case law interpreting it has been to limit the discretion of public entities reviewing bids in order to ensure a fair and level playing field for all bidders. As the Louisiana Supreme Court has stated, “[t]he language of .., 38:2212(A)(l)(b)
We are aware 'that it has been suggested that the 2008 amendments
While under the present facts the result may well be that the City incurs additional expense to complete this public work, adopting a scheme in which a public entity can waive the provisions of its bidding documents at its discretion would create an opening for public entities to create and then waive provisions at whim in order to select a favored contractor, undermining the policy behind the Public Bid Law. We also note that this is not the first, instance of a bid being rejected because of an issue with the labeling of the bid envelope. See Barriere Constr. Co., LLC v. Terrebonne Par. Consol’d Gov’t, 99-2271 (La.App. 1 Cir. 2/18/00) 754 So.2d 1123 (affirming district court’s holding rejecting a bid which did not include the project name and number on the outside of the envelope, as required by the bid documents, stating that the public bid law had been changed to remove the discretion previously given to public to waive formal irregularities).
Accordingly, we find merit in Durr’s assignments of error, and conclude that the City’s waiver of a provision of its bidding documents is in violation of the Public Bid Law, and that all other requirements for the injunctive relief sought have been met. The district court therefore abused its discretion in denying injunctive relief, and thus the portion of the judgment of the district court denying injunctive relief enjoining and restraining the City of New Orleans from awarding the contract for the public work to TKTMJ or Roubion is hereby REVERSED, and the City is enjoined from awarding the contract for the public work to TKTMJ or |nRoubion.
. Also, on the Invitation to Bid document, the City notified bidders that "[f]ailure to satisfy instructions may render bids non-responsive and remove them from the competition.”
. We also note that the case relied upon by the City for its contention that it has the discretion to interpret its bid documents in a way that effectively waives a requirement of its instructions, Haughton Elev. Div. v. State of La., through Div. of Admin., 367 So.2d 1161 (La. 1979), pre-dates the series of revisions to the Public Bid Law beginning in 1984 which explicitly codify the lack of discretion to waive bidding provisions and requirements, even formal ones.
. Currently recodified at La. R.S. 38:2212(B)(1).
. La. Acts 2008, No. 727.
. La. Acts 2014, No. 759,
. If the legislature intended to alter this broad rule, we invite it to clarify.
.As acknowledged by Durr in its brief, the City has not yet reviewed Durr’s bid, nor received required post-bid documents, Accordingly, a reversal of the district court’s denial of a writ of mandamus ordering it to award the contract to Durr would be premature.