DocketNumber: No. CA 2712
Judges: Garrison, Redmann, Schott
Filed Date: 7/9/1985
Status: Precedential
Modified Date: 10/18/2024
Plaintiff appeals from a judgment that, while awarding him $8,834, denied him three items of alleged other damages from breach of contracts. Defendant did not appeal nor answer the appeal by plaintiff. We amend to allow part of the other damages claimed.
Defendant is an agency whose nature is not disclosed by the record. It contracted with the city of New Orleans to supervise housing rehabilitation in which federal funds would supplement a private homeowner’s own funds to repair a home to meet minimum standards. Although some contractual specifics may have been lacking, defendant and plaintiff did enter upon contractual arrangements, first including one building contractor selected by defendant and then another. Neither contractor finished the job.
The trial judge’s award of $8,834 damages was based on the cost of completion, a correct measure under the circumstance of plaintiff’s having already delivered to defendant the entire contract price. This award is not disputed by defendant by appeal or by answer to plaintiff’s appeal, and we therefore accept both that defendant is liable for the damage plaintiff suffered by incompletion of the two contracts and that the amount awarded is correct except insofar as the three other items claimed by plaintiff may also be due to plaintiff.
Two of plaintiff’s claims, however, are duplicative: he asks both stipulated (equall-ing $450 a month) and actual (allegedly $350 a month) damages for delay in completion of the contracts.
We first reject, on other grounds, the claim for the $15 daily liquidated damage that the contracts provide defendant was “authorized” to deduct from the contractors’ payments. Penal clauses must be strictly construed, and this clause does not provide that defendant is in whatever circumstances obliged to deduct the $15 a day. Apparently the contract intended to allow defendant some discretion, and we find no abuse of that, discretion in view of some uncertainty in the specifications of the work and some disputed evidence that plaintiff may have himself contributed to the delay. We cannot say that the trial judge was clearly wrong, Arceneaux v. Domingue, 365 So.2d 1330 (La.1978), in rejecting this claim.
Plaintiff’s claim for $350 monthly rent lost from the rental half of his double house is, in effect, a claim for the actual damage from delay. Plaintiff did not prove, however, either the market rental value of this unit or the reasonable period of loss of rent attributable to the defaulting contractors and to defendant. Plaintiff can in no case collect delay damages forever; he can at best collect for such time after defendant’s default as was reasonably necessary to complete the improvement contract. Yet there is no doubt that performance was delayed substantially beyond the 90-day contractual term, and that an award of zero for damages for delay is wrong. We estimate damages because of delay by defendant and the contractors at $1,000 and award that amount.
The judgment is amended to increase its award to $11,183.19 with interest from judicial demand and all costs.