The parties entered into a written agreement by the terms of which the plaintiff was to construct and install in the defendant’s store certain fixtures in accordance with specifications attached to .and made a part of the agreement. The agreement provided: "All material and workmanship shall be first class in every respect and satisfactory” to the defendant. The contract price to
The auditor in his report dealt separately with the items in the account annexed. As to the nineteenth he found that it was a claim for money due under the written contract; that all the other items were claims for extra work performed by the plaintiff due to changes and additions, alleged to have been ordered by the defendant during the progress of the work under the written contract. He further found that immediately after the written contract was entered into the plaintiff began to prepare in his workshop the fixtures required by the specifications and to install them in the defendant’s store; that during this time the defendant was often present and suggested change’s in the original contract, which need not be described in detail; that while this work was being performed the defendant was present and was told by the plaintiff that the changes would cause additional expense, and the defendant said he would pay for them. During his cross-examination he admitted that all the changes for which an extra charge was made were at his request; he stated that the charges for some of the items were more than he had anticipated and were unfair. There was also testimony of experts called by the defendant respecting the value of the additional work.
The auditor found that the fixtures were built in accordance with the specifications, except as changed by the de
The defendant filed a motion to recommit the report upon several grounds therein set forth. The plaintiff moved that judgment be entered in his favor on the auditor’s report. The foregoing motions were heard together by a judge of the Superior Court who denied the motion to recommit the report and granted the motion for judgment. He ruled that “As to the requirement of the contract that the material and workmanship shall be satisfactory to Siegel, if the auditor’s report is not itself to be construed as finding that Siegel either was, or as a reasonable man ought to have been so satisfied, then I infer such facts from the other facts reported.” The appeal from the order denying the motion to recommit presents no question of law. The appeal from the order allowing the plaintiff’s motion for judgment raises the only question of law before this court. G. L. c. 231, § 96. Samuel v. Page-Storms Drop Forge Co. 243 Mass. 133, 134.
The entry must be
Judgment for the plaintiff for the amount found due by the auditor with interest' from the date of the writ.