Judges: Nolan
Filed Date: 5/15/1991
Status: Precedential
Modified Date: 10/18/2024
In 1986, Tocci Building Corporation (Tocci) entered into a contract with 280 Summer Street Associates to serve as the general contractor on a construction project at that address in Boston. Thereafter, Tocci, as principal, executed a payment bond with the Aetna Casualty and Surety Company (Aetna) as surety to secure payment for all labor and materials used in the project. Ebony Development Corporation (Ebony) entered into a subcontract with Tocci to
Tocci issued five checks to Ebony, payable jointly to Ebony and Suffolk. Ebony negotiated the fifth check, dated April 1, 1987, in the amount of $66,693.87, with the endorsement of a Suffolk salesman. The value of goods supplied but not paid for on April 1, 1987, was $49,610.54. From the fifth check Suffolk took $9,517.04. The ultimate value of the unpaid goods and materials which were delivered to Ebony and incorporated in the project is $41,786.81.
Suffolk filed a complaint against Tocci and Aetna under G. L. c. 149, § 29A (1988 ed.).
A surety bond had been obtained by Tocci from Aetna in connection with the construction contract. The relevant provision of the bond reads: “The above named Principal and Surety [Tocci and Aetna, respectively] hereby jointly and severally agree with each other that every claimant . . . who has not been paid in full before the expiration of . . . ninety (90) days after the date on which . . . materials were furnished by such claimant, may sue on this bond for the use of such claimant, prosecute the suit to final judgment for such sum or sums as may be justly due such claimant and have execution thereon” (emphasis added).
Under the terms of the bond, a supplier who has not been paid in full may recover only “such sum or sums as may be justly due.” Tocci claims, in effect, that the sum claimed by Suffolk is not “justly due” because a check in an amount exceeding the amount claimed by Suffolk was issued jointly to Suffolk and Ebony and endorsed by Suffolk. By endorsing the check, Tocci asserts, Suffolk waived its right to sue on the bond for the amount it should have taken from the check. There is support for the proposition that a supplier ought to take what it is owed from a joint check and will be barred from recovering against the issuer of such a check if it does not. See Iowa Supply Co. v. Grooms & Co. Constr., 428 N.W.2d 662 (Iowa 1986); Anchor Concrete Co. v. Victor Sav. & Loan, 664 P.2d 396 (Okla. 1983).
It is undisputed that on the date of the joint check, April 1, 1987, the total value of goods supplied to Ebony by Suffolk but not yet paid for was $49,610.54. It is also undisputed that from the joint check of $66,693.87, Suffolk received only $9,517.04. Suffolk claims that it took all that was then payable to it from Ebony.
Judgment is reversed. This case is to be remanded to the Superior Court for further proceedings consistent with this opinion.
So ordered.
Suffolk also brought an action for breach of contract against Ebony. Ebony never responded and a default judgment was entered for Suffolk.
We addressed a similar problem under the mechanics’ lien statute in Valentine Lumber & Supply Co. v. Thibeault, 336 Mass. 407 (1957). There we held that where a homeowner issued a joint check for the sole purpose of protecting itself from liability under the mechanics’ lien statute, the underlying contract between the contractor and the supplier was irrelevant. Where the principal is a general contractor rather than a homeowner, the rule is different.
We note that materials valued at $1,120.90 were supplied by Suffolk during the month of April, 1987, after the joint check had been negotiated. As to this amount, summary judgment would have been proper, because Tocci cannot claim that Suffolk should have taken compensation for materials which had not yet been supplied on the date of the check.