Citation Numbers: 448 Mass. 45, 858 N.E.2d 294, 2006 Mass. LEXIS 701
Judges: Greaney
Filed Date: 12/18/2006
Status: Precedential
Modified Date: 10/18/2024
The Energy Facilities Siting Board (board)
1. The background necessary to decide this appeal is as follows. The board is an independent review board estabhshed within the department of telecommunications and energy and charged by the Legislature with administering the provisions contained in G. L. c. 164, §§ 69H through 69Q. See G. L. c. 164, § 69H. The approval of the board is required prior to the commencement of construction of any “facility”
“review the need for, cost of, and environmental impacts of transmission lines, natural gas pipelines, facilities for the manufacture and storage of gas, and oil facilities; provided, however, that the board shall review only the environmental impacts of generating facilities, consistent with the [C]ommonwealth’s policy of allowing market forces to determine the need for and cost of such facilities. Such reviews shall be conducted consistent with [§ 69J ¼ ]for generating facilities and with [§ 69J] for all other facilities.”
G. L. c. 164, § 69H.
The Legislature significantly altered the scope of the board’s governing mandate when it enacted St. 1997, c. 164 (1997 Restructuring Act). Prior to that time, the board was charged to “provide a necessary energy supply for the [C] ommonwealth with a minimum impact on the environment at the lowest possible cost.” G. L. c. 164, § 69H, as amended through St. 1992, c. 141, § 9. Consistent with this charge, the board’s review typically focused on whether there was a “need” for the proposed energy facilities. In 1988, the board developed an analysis specific to determining the “need” for transmission lines that connect to generating facilities that fall outside the board’s jurisdiction. That standard, set forth in the board’s decision relative to a petition to construct a 1.2 mile overhead electric transmission line submitted by Turners Falls Limited Partnership, directed the board to consider whether the energy from the new generator was needed to improve the reliability of the power supply system, or to increase economic efficiency, by analyzing (1) whether there was a need within New England for the power generated by the non-jurisdictional generating fácil
As indicated, in 1997, the Legislature eliminated language in § 69H requiring the board to review the “need” for power to be generated by proposed facilities. The 1997 Restructuring Act also added a new provision to G. L. c. 164 to govern the board’s review of proposed generating facilities. That provision, § 69J 1U, explicitly states that “[n]othing in this chapter shall be construed as requiring the board to make findings regarding the need for, the cost of, or alternative sites for a generating facility” (except in limited circumstances not relevant here) and prohibits the board from seeking data relative to “the necessity for, or cost of, [a] proposed generating facility.”
2. We now recite the facts leading to this appeal. On September 17, 2002, the applicants filed the joint petition to construct and operate transmission lines consisting of two parallel electrical circuits, each made up of two cables and six conductors. The transmission lines would begin at an existing 115 kilovolt switching station in Barnstable and run underground through Barnstable and Yarmouth. The lines then would run under the sea floor from Lewis Bay in Yarmouth, through Nantucket Sound, to the site of the proposed wind farm. The route is approximately eighteen miles in length. Approximately twelve miles of each circuit would be undersea, buried in a trench in the sea bottom about twenty feet apart. At landfall, both circuits would feed into a single underground duct bank for the remainder of the route (approximately six miles), which would terminate at the utility switching station in Barnstable. About half of the undersea portion of the transmission lines would be located outside the three-mile offshore Massachusetts boundary and so under waters controlled by the United States government.
The area in which the wind farm itself is proposed to be built is located in Federal waters and, thus, falls beyond the scope of the board’s jurisdiction and this case. As described in the record, the wind farm would consist of 130 wind turbine generators and an electrical service platform. The wind turbines each would be approximately 420 feet in height from the water to the
On December 20, 2002, the board granted intervener status to five entities, including the Alliance.
In its decision, the board concluded that the applicants had successfully demonstrated that (1) the transmission lines will be needed if the wind farm is built; (2) the proposed transmission line project was superior to alternative approaches in terms of cost, environmental impact, reliability, and ability to address the identified needs; and (3) the proposed primary route was superior to the alternative routes in terms of cost, environmental impact, and reliability of supply. Only the first conclusion, concerning the need for the transmission lines, is at issue.
With respect to that conclusion, the board found that “the total capacity of all existing transmission cable in Nantucket
3. Alliance does not contest the accuracy of the board’s determination that, if Cape Wind receives the necessary permits from Federal and State agencies and if, therefore, its proposed construction of the wind farm goes forward, there will be a “need” for the transmission lines, as that term is used in the board’s authorizing statute. The Alliance objects, however, to (a) the timing of the board’s decision to deviate from the Turners Falls standard to arrive at the determination of “need,” and (b) the contingent nature of the board’s decision. On the basis of these objections, the Alliance requests that we vacate the board’s decision and remand the matter for further proceedings.
a. The decision to announce a new approach by which it would henceforth determine the need for proposed transmission lines, and the timing of that decision, was within the board’s discretion. “It is a recognized principle of administrative law that an agency may adopt policies through adjudication as well as through rulemaking.” Arthurs v. Board of Registration in Medicine, 383 Mass. 299, 312-313 (1981), citing Securities & Exch. Comm’n v. Chenery Corp., 332 U.S. 194, 201-203 (1947). See Massachusetts Elec. Co. v. Department of Pub. Utils., 383 Mass. 675, 679 (1981). The parties in this case were aware that the 1997 Restructuring Act had changed the rules with respect to the manner in which the board evaluates the need for proposed energy facilities. All agreed that the approach adopted
An agency conducting an adjudicatory proceeding is required to give all parties “sufficient notice of the issues involved to afford them reasonable opportunity to prepare and present evidence and argument.” G. L. c. 30A, § 11 (1). See LaPointe v. License Bd. of Worcester, 389 Mass. 454, 458 (1983) (“Due process requires that, in any proceeding to be accorded finality, notice must be given that is reasonably calculated ... to afford [an interested party] an opportunity to present his case”). If the board had created a new standard that required substantive fact finding, it clearly could not have done so without giving notice to the parties and granting each a fair opportunity to prepare arguments and submit evidence in order to meet that standard. See Boston Gas Co. v. Department of Pub. Utils., 405 Mass. 115, 120-121 (1989). That is not what happened here. The Alliance cannot seriously claim that it lacked reasonable notice of the substance of the issues or a chance to prepare its case. See Strasnick v. Board of Registration in Pharmacy, 408 Mass. 654, 660-661 (1990); Fitchburg Gas & Elec. Light Co. v. Department of Pub. Utils., 395 Mass. 836, 844-846 (1985); New England Tel. & Tel. Co. v. Department of Pub. Utils., 372 Mass. 678, 686 (1977).
b. There was nothing improper in the board’s decision to issue a conditional permit. See Mello v. License Comm’n of Revere, 435 Mass. 532, 534 (2001). On the contrary, the board’s decision was an effective method to accomplish its statutory obligation to determine whether there was a need for the proposed transmission lines. See Andover v. Energy Facilities
In circumstances such as the present case, when the proposed generating facility is beyond the board’s jurisdiction, the board determined, “the showing may be made on a case-by-case basis based on indicators of project progress (e.g., progress in permitting or in obtaining project financing).” This approach is particularly appropriate if the generating facility (here, the wind farm) is within the jurisdiction of the United States government, and Federal agencies will be making critical decisions about its permitting. An attempt by the board to predict the decisions of Federal agencies would constitute an exercise in administrative inefficiency and waste the time and effort of the board and the applicants. If the board incorrectly predicted that the wind farm would not get its permits, then the transmission lines would have been unnecessarily rejected. If it incorrectly predicted that the wind farm would get its permits, then it would have permit
The Alliance attacks the board’s decision as an “improper delegation of its statutory duty to make an independent finding of need.” We disagree. Based on the evidentiary record, the board made clear findings, which the Alliance does not challenge, that the “total capacity of all existing transmission cables in Nantucket Sound would be insufficient to transmit the output of the proposed wind farm, even if they could be totally dedicated to that purpose” and that “the existing transmission system is inadequate to interconnect the proposed wind farm.” At that point in time when Cape Wind submits to the board copies of all permits required to commence construction of the wind farm, the need for the proposed transmission lines will be conclusively established. Rather than improperly delegating its responsibilities, the board has, in effect, imposed a heightened standard of proof on the applicants.
The Alliance relies on our decision of Point of Pines Beach Ass’n v. Energy Facilities Siting Bd., 419 Mass. 281, 285-286 (1995), as support for its position that the conditional nature of the board’s decision was unlawful. This reliance is misplaced. In the Point of Pines Beach Ass’n case, the board had approved a petition for the construction of a gas-fired power generating facility by Altresco Lynn, Inc. (Altresco). The statutory language
It is, of course, true that “[a] party to a proceeding before a regulatory agency, such as the [board,] has a right to expect and obtain reasoned consistency in the agency’s decisions.” See Tofias v. Energy Facilities Siting Bd., 435 Mass. 340, 349 (2001), quoting Boston Gas Co. v. Department of Pub. Utils., 367 Mass. 92, 104 (1975). We have stated that the requirement of “reasoned consistency” means only “that any change from an established pattern of conduct must be explained.” Robinson v. Department of Pub. Utils., 416 Mass. 668, 673 (1993). Here, the board carefully, and adequately, explained its reasons for its decision, including its adoption of the new standard for determining need and the conditional nature of its approval. The board’s decision, in our view, is an eminently reasonable and practical approach to the uncommon jurisdictional issues presented by the petition.
4. Judgment shall enter in the county court affirming the decision of the board.
So ordered.
The single justice granted intervener status to Cape Wind Associates, LLC (Cape Wind). In its brief to this court, Cape Wind makes arguments substantially similar to those made by the Attorney General on behalf of the Energy Facilities Siting Board (board).
The definition of a “facility” contained in G. L. c. 164, § 69G, includes, in relevant part, “(1) a generating facility; (2) a new electric transmission line having a design rating of [sixty-nine] kilovolts or more and which is one mile or more in length on a new transmission corridor; [and] (3) a new electric transmission line having a design rating of 115 kilovolts or more which is [ten] miles or more in length on an existing transmission corridor except reconductoring or rebuilding of transmission lines on the same voltage.”
A “generating facility” is defined in G. L. c. 164, § 69G, as “any generating unit designed for or capable of operating at a gross capacity of [one hundred] megawatts or more, including associated buildings, ancillary structures, transmission and pipeline interconnections that are not otherwise facilities, and fuel storage facilities.”
The town of Yarmouth, the Massachusetts Department of Environmental Management Ocean Sanctuaries Program, Save Popponesset Bay, Inc., and the Massachusetts Audubon Society also were granted intervener status, but they take no part in this appeal.
The Alliance asserts that the board committed two other errors that should be corrected on remand. These alleged errors are that the board erred (1) in denying the Alliance’s motion to reopen the record to include the draft environmental impact report (DEIR) on the wind farm project; and (2) in failing to require Cape Wind to produce specific financial information as required by G. L. c. 164, § 69J. The Alliance makes these assertions without citation or convincing argument, and we consider them only briefly. As for the first, a
In Andover v. Energy Facilities Siting Bd., 435 Mass. 377 (2001), we affirmed the board’s approval of a petition to construct and operate an electrical generating facility in the town of Dracut. The board’s decision in that case deferred setting emission limits for the proposed facility until the department of environmental protection issued its final air plan approval. See id. at 380. Opponents argued that the board’s decision constituted an improper abdication of its statutory responsibility, under G. L. c. 164, § 69J ¼, to establish “final, binding emissions limits for the proposed facility.” We concluded that, far from being improper, the board’s decision reflected “an accurate observation of the different roles of the board and [other Federal and State] agencies in the over-all permit process.” Id. Such is the case here.
Recognizing that its analysis ventured into new territory, and cognizant of the value of precedent in its past decisions, the board conducted a lengthy alternative review of the proposed wind farm and concluded that the applicants had established a need for the proposed transmission lines consistent with the Turner Falls standard. Although the board’s cautioned approach is understandable, its analysis under the Turner Falls standard has no legal effect. This is so because, as has been discussed, G. L. c. 164, §§ 69H and 69J ¼, explicitly prohibit the board from seeking data regarding the need for, or cost of, a proposed generating facility, except in certain narrowly defined circumstances.
The board issued its decision in 1993, well before the enactment of the electric utility restructuring act, St. 1997, c. 164 (1997 Restructuring Act), changed the board’s mandate from providing “a necessary energy supply for the commonwealth” to providing “a reliable energy supply for the commonwealth,” St. 1997, c. 164, §§ 204 and 205, and added the provisions of § 69J ¼, inserted by St. 1997, c. 164, § 210, which now apply to petitions for the construction of new and expanded generating facilities and which expressly do not require a finding of need for the approval of such petitions.