Judges: Duefly, Lenk
Filed Date: 7/15/2013
Status: Precedential
Modified Date: 11/10/2024
We address in this appeal whether a subcontractor’s amendment of its original complaint to enforce a mechanic’s lien constituted timely commencement of its action to enforce a bond pursuant to G. L. c. 254, § 14, as amended through St. 2002, c. 400, § 2 (§ 14), which sets forth procedures for execution and enforcement of bonds to dissolve mechanic’s liens. The plaintiff, NES Rentals, Inc. (NES Rentals), filed an action
After NES Rentals filed the amended complaint with leave of court, a judge in the Superior Court denied Maine Drilling’s motion to dismiss the amended complaint, explaining that although NES Rentals had not filed the amended complaint within ninety days of receipt of notice of the bond, service of the motion on the defendants within that ninety-day period provided the defendants with actual notice of the action to enforce the bond, and satisfied the § 14 requirement that a claimant have “commenced” a civil action within that period in order to enforce the bond. The defendants sought leave to appeal, which was allowed, and we transferred the case to this court on our own motion.
We affirm the order denying the defendant’s motion to dismiss, but for reasons different from those relied on by the judge. We conclude that the term “commenced” as used in § 14 contemplates the filing of an action in court in accordance with Mass. R. Civ. P. 3, as amended, 385 Mass. 1215 (1982), and that the commencement requirement in § 14 is satisfied on the facts of this case because the amendment to the complaint relates back to the date on which NES Rentals filed its original action against Berkshire Wind under Mass. R. Civ. P. 15 (c), 365 Mass. 761 (1974) (rule 15 [c]).
1. Background and prior proceedings. NES Rentals alleges that McManus Excavating, Inc., contracted with it to rent equipment for construction use on property owned by Berkshire Wind.
On April 29, 2011, Maine Drilling
On November 2, 2011, a judge of the Superior Court allowed both the motion of NES Rentals to amend the complaint and Berkshire Wind’s cross motion to dismiss the underlying complaint against it; NES Rentals then filed its amended complaint with the court. Thereafter, Maine Drilling filed a motion to dismiss the amended complaint on the ground that it was not timely filed in accordance with the terms of § 14, because the amended complaint, which constituted the action to enforce the bond, was not filed within ninety days after NES Rentals received notice of recording of the bond, that is, by September 11, 2011.
The judge denied Maine Drilling’s motion to dismiss the amended complaint. He explained that “even though the amended complaint was actually not ‘filed’ within the 90 day period, the defendants had actual notice of it well within that period,” where NES Rentals had served the motion to amend on Maine Drilling and Berkley within that time, and that, therefore, “the purpose of the statute, i.e., notice to the issuer of the bond within 90 days, was satisfied.”* ***
In this case we consider whether amendment of a complaint, originally brought as an action to enforce a lien, by adding a claim to enforce a lien dissolution bond constitutes timely commencement of an action to enforce the bond within the meaning of § 14. We begin our discussion of the applicable provisions of G. L. c. 254 (mechanic’s lien statute) with the observation that it is the primary purpose of the mechanic’s lien statute “to provide security to contractors, subcontractors, laborers, and suppliers for the value of their services and goods provided for improving the owner’s real estate” through perfection of a mechanic’s lien on the owner’s real estate. Hammill-McCormick Assocs., Inc. v. New England Tel. & Tel. Co., 399 Mass. 541, 542-543 (1987), citing Mitchell v. Packard, 168 Mass. 467, 469 (1897).
“At the same time, the statute contains filing and notice requirements to protect the owner and others with an interest in the property.” Id. at 543, and cases cited. The mechanic’s lien statute is “designed to ensure that a person searching the land records in a registry of deeds can determine with certainty whether or not title to a particular parcel of land is encumbered by a mechanic’s lien.” National Lumber Co. v. LeFrancois Constr. Corp., 430 Mass. 663, 668 (2000) (.National Lumber I), citing Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317-318 (1919). Additionally, because a perfected lien is an encumbrance on the owner’s property, the statute provides for prevention of future liens and dissolution of existing liens by the giving of a bond, see G. L. c. 254, § 12, as amended through St. 2002, c. 400, § 1 (§ 12), and § 14, which benefits “an owner of land (or anyone possessing an interest in that land) by furnishing means to keep his title free from liens” and preventing the sale of the land to satisfy a lien.
We look to the specific provisions governing creation and perfection of a mechanic’s lien, and the procedures for enforcement of a lien dissolution bond, to decide whether NES Rentals has fulfilled the requirements for enforcement of the bond by timely commencing a civil action. Under § 4 of the mechanic’s lien statute, a subcontractor furnishing rental equipment for use on land may record a lien on that property, but under G. L. c. 254, § 11, as amended through St. 1996, c. 364, § 11 (§ 11), “[t]he lien shall be dissolved unless a civil action to enforce it is commenced within ninety days after the filing of the statement required by section eight,” and thereafter “filed in the registry of deeds and recorded.” G. L. c. 254, § 5 (delineating procedures for lien enforcement action). There is no question that NES Rentals recorded its lien and timely commenced and recorded a civil action to enforce it in the Superior Court, after recording a § 8 statement setting forth the amount due for the rental equipment it had furnished.
Section 14 dictates how such a perfected lien may be dissolved by the posting of a bond, and what a subcontractor must do to maintain his security. “Any person in interest may dissolve a lien ... by recording ... a bond ... in a penal sum
“Because a mechanic’s lien is purely a creation of statute, we have consistently required exact compliance with the statute in order to create, perfect, and enforce such a lien.” Golden v. General Bldrs. Supply, 441 Mass. 652, 654 (2004) (Golden), and cases cited. See National Lumber II, supra at 729, citing National Lumber I, 430 Mass, at 666 (just as strict compliance with provisions of statute is required to perfect lien, person in interest may dissolve lien by strictly adhering to statute); Ng Bros. Constr. v. Cranney, supra at 644, citing Mullen Lumber Co. v. Lore, 404 Mass. 750, 752 (1989) (“The [mechanic’s lien] statute is strictly construed against the party claiming the lien”). Relying on these rules of strict compliance, Maine Drilling argues that mere service of an unfiled motion to amend a complaint within ninety days of receipt of notice of a lien dissolution bond does not constitute “commence[ment] ’ ’ of a civil action to enforce the bond under § 14.
According to Maine Drilling, NES Rentals did not “commence []” an action on the bond within ninety days from the date on which it received notice of the recording of the bond, because NES Rentals did not file its amended complaint until November 2, 2011, or even file its motion to amend until October 3, 2011, well beyond ninety days after NES Rentals was served with notice of the bond on June 13, 2011.
The mechanic’s lien statute does not define the phrase “civil action commenced,” but its meaning may be discerned from the legislative history of the statute. See Commonwealth v. Hamil
We adopted the Massachusetts rules of civil procedure earlier that year, see National Lumber I, 430 Mass, at 670-671; Introduction to Mass. R. Civ. & Mass. R. App. R, 365 Mass. 730 (1974), and we assume that the Legislature was aware of the recently adopted rules when it amended § 14 in 1973. See Rhodes v. AIG Domestic Claims, Inc., 461 Mass. 486, 501 (2012), quoting CFM Buckley/North LLC v. Assessors of Greenfield, 453 Mass. 404, 412 (2009) (“it. . . must be presumed that the Legislature knew preexisting law and the decisions of this court”). It is apparent from this history that the Legislature intended the meaning of “civil action commenced” as used in § 14 of the mechanic’s lien statute to be interpreted consistently with the meaning of those terms in the Massachusetts rules of civil procedure.
As provided by Rule 3 of the Massachusetts Rules of Civil Procedure, “A civil action is commenced by (1) mailing to the clerk of the proper court... a complaint and an entry fee . . . or (2) filing such complaint and an entry fee with such clerk.” Mass. R. Civ. P. 3, as amended, 385 Mass. 1215 (1982).
However, this conclusion does not end our inquiry. When Maine Drilling and Berkley recorded the lien dissolution bond and provided notice of the bond to NES Rentals, NES Rentals had already commenced a civil action to enforce its lien against Berkshire Wind, in accordance with the provisions of §§ 5 and ll.
Our adherence to principles of strict statutory construction applicable to the mechanic’s lien statute, “and our insistence on precise compliance with those statutory terms, do[] not mean that the rules of civil procedure are inapplicable to proceedings concerning mechanic’s liens .... Absent some incompatibility between a specific procedural rule and the provisions of the [mechanic’s lien] statute, we will apply and enforce both.” Golden, supra at 655, citing National Lumber I, supra at 670-672.
Under ordinary application of the Massachusetts rules of civil
The language of rule 15 (c) has remained unchanged since the enactment of the Massachusetts rales of civil procedure in 1973, which prompted the amendment of the mechanic’s lien statute to conform to the newly adopted rules. See Mass. R. Civ. P. 15 (c), 365 Mass. 761 (1974); 1973 House Doc. No. 7236. Although we assume that the Legislature was aware of the relation back provisions of rale 15 (c) and knew those provisions generally would apply when it added the language “a civil action commenced” to § 14, see Rhodes v. AIG Domestic Claims, Inc., supra at 501, citing CFM Buckley/North LLC v. Assessors of Greenfield, supra, we will not apply the ordinary relation back provisions of rale 15 (c) in circumstances where application of the rale conflicts with the terms or purpose of the
In National Lumber I, supra at 671-672, we held that a plaintiff who had timely commenced an action to enforce a § 4 lien against a former property owner could amend the complaint to add the present property owner, even after the statutory period for bringing an enforcement action under § 11 had expired. As we explained in that case, under rule 15 (c), the action relates back to the date of the commencement of the complaint, and § 11 does not bar application of rule 15 (c) because § 11 is not a statute of repose blocking later claims against successive property owners. Id.
By comparison, in Golden, supra, we held that a counterclaim to enforce a hen, filed after the § 11 deadline to commence an action on that lien, does not relate back to the date of the complaint filed by the property owner, id. at 661, because “allowing for reinstatement of a dissolved lien by later filing of a counterclaim ‘would effectively give the contractor a period greater than that intended by the Legislature’ in which to enforce the lien.” Id. at 659, quoting Tremont Tower Condominium, LLC v. George B.H. Macomber Co., 436 Mass. 677, 684 (2002). As we noted in Golden, supra at 659-660, quoting National Lumber I, supra at 669, relation back in such a case would “wreak havoc with one of the statute’s important purposes, namely, the provision of ‘an accurate system for recording and identifying encumbrances secured under the mechanic’s lien statute,’ ” because a title examiner who found no complaint recorded on a lien within 120 days
The text and purpose of § 14 and the mechanic’s hen statute support ordinary application of the relation back provisions of rule 15 (c) to the circumstances of this case. Section 14 states in general terms that “[t]he claimant may enforce the bond by a civil action commenced within ninety days after the later of the filing of the statement required by [§] 8 or receipt of notice of recording of the bond.” First, as discussed above, the phrase “civil action commenced,” read in hght of the circumstances of its addition to the statute, permits relation back of an amended complaint to the date of a timely filed original complaint. Moreover, the language “commenced within ninety days after” does not bar commencement of an action before the ninety-day period, as would result from application of the relation back rules in this case. See Mullen Lumber Co. v. Lore, 404 Mass. 750, 754-756 (1989) (under § 11, which provides that hen dissolves unless civil enforcement action is “commenced within [ninety] days after” filing of § 8 statement, ninety-day period establishes “latest time at which a hen could be enforced and does not preclude . . . enforcement” prior to filing of § 8 statement).
Additionally, nothing in the language of § 14 requires that
Moreover, application of the relation back provisions of rule 15 (c) in this context is consistent with, rather than repugnant to, the objectives of the mechanic’s lien statute.
Permitting bond enforcement actions to relate back to the date of a timely-filed lien enforcement action does not frustrate the statutory objective of ensuring a reliable recording system. See National Lumber I, supra at 668, citing Pratt & Forrest Co. v. Strand Realty Co., 233 Mass. 314, 317-318 (1919). Once a bond is recorded in accordance with § 14, the hen is dissolved on the record, and any concern about uncertainty of title arising from that lien is eliminated.
We therefore conclude that the ordinary relation back provisions of rule 15 (c) apply to § 14 bond enforcement actions, and that a claimant may, in accordance with rule 15, amend a timely filed complaint seeking enforcement of a lien to add a claim to enforce a lien dissolution bond against the holder of the bond after the ninety-day period set forth in § 14.
Judgment affirmed.
A judge allowed a motion of Berkshire Wind Power Cooperative Corporation (Berkshire Wind) to dismiss.
General Laws c. 254, § 4, as amended through St. 1996, c. 364, § 5 (§ 4), provides, in relevant part:
“Whoever. . . furnishes rental equipment, appliances or tools, under a written contract with a contractor, or with a subcontractor of such contractor, may file or record in the registry of deeds for the county or district where such land lies a notice of his contract.... Upon filing or recording a notice, as hereinbefore provided, and giving actual notice to the owner of such filing, the subcontractor shall have a hen upon such real property, land, building, structure or improvement owned by the party who entered into the original contract as appears of record at the time of such filing, to secure the payment of all labor and material and rental equipment, appliances or tools which he is to furnish or has furnished for the building or structure or other improvements. . . .”
GeneraI Laws c. 254, § 8, as amended by St. 1996, c. 364, § 9, provides:
“Liens under section[]. . . four shall be dissolved unless the contractor, subcontractor, or some person claiming by, through, or under them, shall[, within a specified time frame,] file or record in the registry of deeds in the county or district where the land lies a statement, giving a just and true account of the amount due or to become due him . . . .”
Maine Drilling states that it is another subcontractor on the Berkshire Wind property. The record is silent on the point, but Maine Drilling’s role as a subcontractor is not material to our decision in this case.
General Laws c. 254, § 14, as amended through St. 2002, c. 400, § 2 (§ 14), provides, in relevant part:
“Any person in interest may dissolve a lien under this chapter by recording ... a bond ... in a penal sum equal to the amount of the lien sought to be dissolved conditioned for the payment of any sum which the claimant may recover on his claim for labor or labor and*859 materials. . . . The claimant may enforce the bond by a civil action commenced within ninety days after the later of the filing of [the G. L. c. 254, § 8, statement of account] ... or receipt of notice of recording of the bond. . . .”
As an additional ground for denying the motion on the basis of notice, the judge stated that Maine Drilling and Berkley were represented by the same counsel as Berkshire Wind, the defendant in the original action. Maine Drilling and Berkley assert that this was a factually incorrect assumption based solely on the fact that counsel in the two firms share a surname. Nothing in the record supports the statement that the firms, or the attorneys, are “the same.” Our disposition of the matter, however, does not depend on a resolution of this issue.
NES Rentals made no claim in the Superior Court that Maine Drilling is
Maine Drilling does not argue that an amended complaint to enforce a bond could not, if filed in the Superior Court by September 11, 2011, have qualified as a timely filed “civil action” within the meaning of § 14.
The relevant language of rule 3 has not changed since its original adoption. Compare Mass. R. Civ. R 3, as amended, 385 Mass. 1215 (1982), with Mass. R. Civ. P. 3, 365 Mass. 733 (1974).
We are not concerned here with a situation in which a bond preceded and thus precluded attachment of a lien, governed by G. L. c. 254, § 12, as amended through St. 2002, c. 400, § 1 (§ 12), or where, at the time that the bond was recorded, a lien claimant already had perfected a lien but had not yet commenced an action to enforce it. In accordance with §§ 12 and 14, both of those situations require a claimant to commence a new action to enforce the bond.
An amended complaint is a pleading that qualifies as a civil action within the meaning of § 14. See Mass. R. Civ. R 15 (a), 365 Mass. 761 (1974) (“a party may amend his pleading only by leave of court or by written consent of the adverse party”). Cf. Golden v. General Bldrs. Supply, 441 Mass. 652, 655 (2004) (Golden) (counterclaim to enforce lien may be “civil action” under § 5 and G. L. c. 254, § 11, as amended through St. 1996, c. 364, § 11 [§ 11], because Mass. R. Civ. P. 13 [b], 365 Mass. 758 [1974], permits party to “state as a counterclaim any claim against an opposing party” [emphasis in original]).
The amendment of a complaint to enforce a lien, by adding a claim seeking enforcement of a lien dissolution bond against a person who executed the bond, complies with the threshold requirement of Mass. R. Civ. R 15 (c), 365 Mass. 761 (1974), that the added claim or claims arise “out of the same conduct, transaction, or occurrence set forth in . . . the original pleading.” A lien dissolution bond is inextricably connected to the underlying lien. It is based on and has the effect of dissolving the lien, and it may be enforced only to the extent that the claimant would have been able to recover on the claim for labor or labor and materials that served as the basis of the lien. G. L. c. 254, § 14.
Because a lienholder has ninety days to file a complaint under § 11, and thirty days to record the complaint thereafter under § 5, the lienholder has a maximum of 120 days within which to commence and provide record notice of a claim to enforce a lien.
This interpretation is consistent with the legislative history of § 14. The 2002 amendments to § 14 added “the later of the filing of the statement required by section 8 or” to the statute, see St. 2002, c. 400, § 2, which previously had required only that a civil action be commenced “after the receipt of notice of recording of the bond.” Compare G. L. c. 254, § 14, as amended through St. 1996, c. 364, § 14, with G. L. c. 254, § 14, set forth in note 6, supra. A December, 2002, memorandum to then Governor Jane M. Swift from the Director of Legislative Research regarding 2002 Senate Doc. No. 931, the bill that was enacted as St. 2002, c. 400, §§ 1-2, explained that, under this bill, “the final deadline for either type of bond [under § 12 or § 14] will be [ninety] days after the claimant files a ‘Statement of Claim,’ in accordance with c. 254, § 8 ... . The effect of the change is to afford contractors who rely on bonds the same amount of time to commence an action on that claim as contractors who rely on liens currently have to file an action to enforce the lien.” See also R.V. Lizza, Massachusetts Mechanic’s Lien Law § 5.5, at 5.5.1 (Mass. Cont. Legal Educ. 2006) (“The 2002 Amendment also addressed a procedural ‘trap for the unwary’ ” under which claimants bringing actions to enforce bonds under §§ 12 and 14 may have “a shorter period of time than would be available for making a normal lien claim”). It thus appears that, in adding more detail to the § 14 timeline, the Legislature was concerned with
General Laws c. 254, § 5, provides, in pertinent part: “All other parties in interest may appear and have their rights determined in such action, and at any time before entry of final judgment, upon the suggestion of any party in interest that any other person is or may be interested in the action, or of its own motion, the court may summon such person to appear in such cause on or before a day certain or be forever barred from any rights thereunder. The court may in its discretion provide for notice to absent parties in interest.”
Compare § 5 (“The terms ‘party in interest’ and ‘person in interest,’ as used in this chapter, shall include mortgage[e]s and attaching creditors” [emphasis added]), with § 12 (“The bond may be enforced by a civil action in the superior court or district court brought by any party in interest” [emphasis added]), and § 14 (“Any person in interest may dissolve a lien under this chapter by recording ... a bond” [emphasis added]).
Cf. Nett v. Bellucci, 437 Mass. 630, 635-636 (2002) (relation back rule of Mass. R. Civ. P. 15 [c] inapplicable where literal application would be contrary to purposes underlying seven-year statute of repose for medical malpractice tort claims); Tindol v. Boston Hous. Auth., 396 Mass. 515, 516, 519 (1986), citing James Ferrera & Sons v. Samuels, 21 Mass. App. Ct. 170, 173 (1985) (relation back rule of Mass. R. Civ. P. 15 [c], inapplicable where application “would have the effect of reactivating a cause of action that the Legislature
The dissent, post at 870, 873, expresses concern that application of the ordinary rules of relation back in the context of § 14 would introduce uncertainty into the mechanic’s lien statute. However, concerns about uncertainty appears to relate primarily to reliability of title. See Golden, supra at 660 & n.8 (discussing interest in certainty of recording system). As described above, once a bond is posted, the lien encumbering the property is dissolved, and any uncertainty of title arising from the lien disappears. Moreover, the principal on the bond — the party with a continuing interest in certainty — would be on record notice of any pending lien enforcement actions, back to which an amendment could relate, when undertaking to post a bond in the first place. See G. L. c. 254, § 5 (requiring recording of copy of complaint seeking enforcement of lien).
Although the rule provides that “leave shall be freely given when justice so requires,” see Mass. R. Civ. R 15 (a), 365 Mass. 761 (1974), undue delay in amending an existing complaint asserting a hen enforcement claim to add claims to enforce a hen dissolution bond would be a basis for a judge to deny a claimant’s motion to amend. See Castellucci v. United States Fid. & Guar. Co., 372 Mass. 288, 289-290 (1977), quoting Forman v. Davis, 371 U.S. 178, 182 (1962).
A claimant is of course not precluded from filing a separate, timely complaint to enforce a bond under § 14. See National Lumber II, supra at 725; LaCentra v. Jackson, 245 Mass. 14, 19-20 (1923).
NES Rentals argues that Maine Drilling and Berkley did not properly give service of notice of the bond to NES. We do not address this argument, which was not raised below and therefore has been waived. See Mass. R. A. R 16 (a) (4), as amended, 367 Mass. 921 (1975). Because of the conclusion we reach, we also do not address NES Rentals’s argument that a procedural conflict exists between rule 15 and Superior Court Rule 9A.