DocketNumber: No. 12-P-403
Citation Numbers: 83 Mass. App. Ct. 280, 983 N.E.2d 249
Judges: Green
Filed Date: 2/14/2013
Status: Precedential
Modified Date: 10/18/2024
After a jury-waived trial, a Superior Court judge found that the defendants had erected a stone and earthen berm that blocked the path of a deeded drainage easement serving the plaintiffs’ property, but that the berm’s continued existence for more than forty years barred the plaintiffs from relying on the rights granted by the easement. The judge nonetheless ordered the defendants to remove the berm, based on his conclusion that its presence constitutes a continuing nuisance. Because the defendants erected the berm before the doctrinal change to
Background. We summarize the findings of fact entered by the trial judge. The plaintiffs purchased 42 Deep Run Road in Cohasset on July 13, 2004. Abutting the plaintiffs’ property to the rear, and down gradient, is property owned by the defendant Virginia M. Riley, as trustee of V.M.R. Nominee Realty Trust (trust). Riley initially purchased the property with her husband, the defendant John J. Riley, on May 20, 1966; the couple built a home on the property that year and have resided there from that time to the present.
Both properties slope downward in an easterly direction toward Jerusalem Road, and then to the Atlantic Ocean. Accordingly, surface water naturally flows from west to east across both properties, from the plaintiffs’ to the defendants’ property. A 1953 subdivision plan shows a drainage easement that begins on the westerly side of Deep Run Road, opposite the plaintiffs’ property, and then runs under the road and across the plaintiffs’ property onto the defendants’ property. Thereafter, the easement continues across Haystack Lane and ultimately to the ocean.
Around the time the defendants built their home, they constructed an earthen berm, topped by stones, along the boundary line between their property and the property now owned by the plaintiffs.
Shortly after moving into their home in 2004, the plaintiffs
In an effort to devise a solution to the ponding problem, the plaintiffs retained an engineering firm in 2006. At or about the same time, the town initiated its own effort to improve the drainage in the area of the parties’ properties. The town obtained easements from various affected property owners, but did not successfully complete negotiations with the defendants for an easement across their property. The plan devised by the plaintiffs’ engineer has been reviewed by the Cohasset Conservation Commission and meets with its satisfaction, but will not be approved until it provides for connection to the newly designed town drainage system.
After negotiations between the town and the defendants failed to produce an easement across the defendants’ property, the plaintiffs commenced an action in the Superior Court seeking relief under various theories, and both parties appealed from the resulting judgments.
Discussion. The trial judge correctly recognized that the
At the time the defendants constructed the berm, Massachusetts followed the so-called “ ‘common enemy’ approach to surface water problems. See, e.g., 6A American Law of Property § 28.63, at 189-190 (A.J. Casner ed. 1954).” Tucker v. Badoian, supra at 913. Under then applicable law, “one landowner [was] free to stop surface water from entering his land despite harm to his neighbor.” Id. at 912. In addition, such a landowner could “with impunity grade and improve his land for a lawful purpose even though he thereby diverts surface water onto his neighbor’s land.” Ibid. Accordingly, though construction of the berm interfered with the rights of the plaintiffs’ predecessors in interest under the drainage easement (an infraction against which the limitations period has long since expired), it did not constitute a common-law nuisance.
In Tucker v. Badoian, supra, six Justices of the Supreme Judicial
In concluding that the berm constituted an actionable continuing nuisance, the trial judge applied the reasonable use standard. However, the berm was fully completed and in place in 1966, more than ten years before adoption of that standard. There is no indication in the record that the defendants altered or expanded the berm in any manner after 1978.
Conclusion. The “Judgment on Finding of the Court Re: Count I (Nuisance)” is reversed. The remaining judgments are affirmed.
So ordered.
We decline the defendants’ request that we order the plaintiffs to comply with an order issued by the Cohasset Conservation Commission that, they contend, the plaintiffs continue to violate. The trial judge found that the plaintiffs have complied with the order, and the defendants cite no record evidence to demonstrate that the judge’s finding in that respect was clearly erroneous.
At some point following their initial purchase, the couple conveyed title to the trust.
The defendants denied having built the berm, but the judge’s finding that they did is not clearly erroneous.
Though drainage across the defendants’ property is necessary for implementation of the proposed system, we note that the order imposed by the judgment does not appear to achieve that objective. That is to say, the proposed system envisions connection to a particular outlet on the defendants’ property, and continuation of the drainage from that outlet to its eventual discharge into the Atlantic.
The plaintiffs’ complaint sets forth three counts, based on nuisance, negligent trespass, and “trespass/interference with an easement,” respectively. The defendants counterclaimed, asserting damages to their property caused by the plaintiffs. The docket reflects that the defendants also filed a third-party complaint, asserting claims against various other parties, who are not parties to this appeal; the record does not include a copy of that pleading.
Four separate judgments were entered: (1) “Judgment on Finding of the Court Re: Count I (Nuisance)”; (2) “Judgment on Finding of the Court Re: Count II (negligent trespass) and Count III (trespass/interference with Easement)”; (3) “Judgment on Finding of the Court Re: Counterclaim”; and (4) “Judgment Re: All remaining claims.” The judgment on count one of the complaint included the order to remove the berm and is the principal subject of this opinion. The judgment on counts two and three of the complaint, and the judgment on the counterclaim, dismissed those counts and the counterclaim. The judgment on “all remaining claims” recites that it was based on an agreement by the parties to dismiss them.
There is no merit to the plaintiffs’ contention, based principally on the defendants’ attempts at trial to deny having built the berm, that the judge erred in concluding that the defendants’ interference with the easement was open and notorious. The trial judge’s finding that the defendants erected the berm relied in significant part on testimony by the son of the couple who owned the plaintiffs’ property in 1966, to the effect that the berm was not in place on the defendants’ property, and water did not pond on the plaintiffs’ property, before the defendants purchased their property. The berm is a significant physical alteration of the natural grade of the property, which the plaintiffs acknowledge has caused significant ponding on their property since its installation.
To the extent that the judge expressed the view that, though the plaintiffs were barred from asserting rights under the easement, the easement was not extinguished by the defendants’ continued interference with it, he was incorrect.
Though the trial judge referred to other more recent conduct of the defendants he viewed as “unreasonable,” it was not of a character that qualifies under our law as nuisance. Specifically, the judge referred to the defendants’ refusal “to cooperate with the town in implementing a solution at no cost to them,” and “stonewalljmg] the issue.” Though the judge was understandably frustrated with the uncooperative posture adopted by the defendants to a seemingly reasonable solution to a community-wide problem, it is not the role of the courts to exert “a general power of equitable adjustment and enforced good neighborliness.” Goulding v. Cook, supra at 280.
Our decision does not foreclose implementation of the town’s proposed solution. Unlike the plaintiffs (and the court), the town has the power and authority to require the defendants to grant an easement to facilitate completion of the proposed new drainage system for public benefit, upon payment of just compensation. Though previous attempts to negotiate mutually acceptable terms apparently were unsuccessful, the defendants cannot hold the town hostage to unreasonable demands: “[t]he power of eminent domain is granted just to prevent private property owners from extracting such strategic rents from the public.” Goulding v. Cook, supra at 279.