DocketNumber: No. 12-P-968
Judges: Meade
Filed Date: 2/25/2013
Status: Precedential
Modified Date: 11/10/2024
Cameron Painting, Inc. (Cameron), appeals from a judgment dismissing its complaint for breach of contract
1. Background. The facts are not in dispute. On May 9, 2006, Cameron submitted a general bid to the University for a contract for painting services valued at $500,000. The State contract was for “campus painting services” and labor at the University’s Amherst campus.
On May 26, 2006, Cameron and the University entered into a one-year contract for the same project. The contract estimated the volume of business would be $500,000, and guaranteed Cameron a minimum payment of $1,000 under the contract. All work pursuant to this contract was to be completed on or before May 31, 2007. The parties executed the contract as a sealed instrument.
The terms of the contract required that prior to the commencement of a particular painting project, both Cameron and the University must reach an agreed-upon price for the particular project. Over the course of the contract period, the parties could not agree upon any quotes submitted by Cameron for any painting projects at the University. The University therefore authorized no work for Cameron under the contract terms, and notified Cameron on February 16, 2007, it would not renew the contract. Cameron also alleges the University put projects out to bid between May, 2006, and May, 2007, that would have normally fallen within the scope of Cameron’s contract with the University.
Cameron filed its complaint against the University in Superior Court on November 21, 2011, approximately five years after the contract was executed, and four years after the contract ended, and alleged the University breached the implied covenants of good faith and fair dealing during the periods between May, 2006, and May, 2007. A judge of the Superior Court dismissed the complaint as untimely, and Cameron appeals.
2. Discussion, a. Standard of review. We review the grant of a motion to dismiss de nova, and in reviewing the sufficiency of a complaint under Mass.R.Civ.P. 12(b)(6), 365 Mass. 754
b. Limitations periods. When interpreting a statute, a court’s primary duty is to “effectuate the intent of the Legislature in enacting it.” International Org. of Masters v. Woods Hole, Martha’s Vineyard & Nantucket S.S. Authy., 392 Mass. 811, 813 (1984). In interpreting a statute, we look first to its language as “the principal source of insight into legislative intent.” Water Dept. of Fairhaven v. Department of Envtl. Protection, 455 Mass. 740, 744 (2010), quoting from Providence & Worcester R.R. v. Energy Facilities Siting Bd., 453 Mass. 135, 142 (2009). Statutes should be interpreted in accordance with the plain meaning of the statutory language, see Sullivan v. Brookline, 435 Mass. 353, 360 (2001), and “the courts enforce the statute according to its [plain] wording.” Martha’s Vineyard Land Bank Commn. v. Assessors of W. Tisbury, 62 Mass. App. Ct. 25, 27-28 (2004), quoting from Weitzel v. Travelers Ins. Cos., 417 Mass. 149, 153 (1994). Where the meaning of the language is plain and unambiguous, “we simply end our analysis and give effect to the legislative intent.” Adams v. Boston, 461 Mass. 602, 609 (2012). See Halebian v. Berv, 457 Mass. 620, 628 (2010).
At the outset, we note that as a component of the Commonwealth, the University cannot be sued unless the Commonwealth has consented to a waiver of its sovereign immunity. See Morash & Sons v. Commonwealth, 363 Mass. 612, 614-616 (1973); Irwin v. Commissioner of the Dept. of Youth Servs., 388 Mass. 810, 812 (1983).
Section 1 of G. L. c. 75 does not give the University the express authority to contravene the laws of the Commonwealth regarding the Commonwealth’s consent to be sued. “In this Commonwealth, public officials cannot make a binding contract without express authority, and have authority to bind their governmental bodies only to the extent conferred by the controlling statute.” Dagastino v. Commissioner of Correction, 52 Mass. App. Ct. 456, 458 (2001) (citations omitted). Only the Legislature may enact laws that set aside the traditional protections of sovereign immunity and allow claims to proceed against the Commonwealth. The University, pursuant to its admittedly broad powers under G. L. c. 75, § 1, has no such power. “[T]hose who contract with the officers or agents of a governmental agency must, at their peril, ‘see to it that those officers or agents are acting within the scope of their authority.’ ” Bowers v. Board of Appeals of Marshfield, 16 Mass. App. Ct. 29, 34 (1983), quoting from Sancta Maria Hosp. v. Cambridge, 369 Mass. 586, 595 (1976).
Chapter 260 of the General Laws governs the limitations of actions brought in Massachusetts courts. In general, G. L. c. 260, § 2, provides a six-year statute of limitations for contract claims, absent exceptions listed in G. L. c. 260, § 1, such as contracts under seal: “Actions of contract, other than those to recover for personal injuries, founded upon contracts or liabilities, express or implied, except actions limited by section one . . . shall,
A plain reading of the text of G. L. c. 260, § 3A, conveys the explicit intent of the Legislature that all claims against the Commonwealth for breach of contract must be brought within three years of their accrual, regardless of whether the contract was made under seal. The use of the word “only” in § 3A explicitly limits the scope of sovereign immunity that the Legislature has consented to waive in contract claims brought against the Commonwealth. Wong v. University of Mass., 438 Mass. 29, 35 (2002). Unlike G. L. c. 260, § 2, § 3A contains no explicit exception for contracts brought under seal, instead requiring all contract claims against the Commonwealth be brought “only” within three years. See Wong v. University of Mass., supra at 36. Because the Legislature could have carved out a similar exception for contracts under seal in § 3 A, but did not, we must conclude the Legislature intended to require all claims against the Commonwealth be brought within three years. See General Elec. Co. v. Department of Envtl. Protection, 429 Mass. 798, 803 (1999), quoting from King v. Viscoloid Co., 219 Mass. 420, 425 (1914) (“we do not ‘read into the statute a provision which the Legislature did not see fit to put there, whether the omission came from inadvertence or of set purpose’ ”).
As the judge properly noted, Cameron could not bring this suit unless the Commonwealth consented to waive sovereign immunity in contract cases. “When the Commonwealth consents to be sued, it may define the terms and conditions on which it may be sued.” Wong v. University of Mass., supra at 35-36. The
c. Estoppel. Cameron also claims that even if G. L. c. 260, § 3A, applies to its breach of contract claim, the University should be estopped from asserting the three-year statute of limitations because in knowingly executing a contract under seal, the University induced Cameron to hold off bringing suit until after § 3A’s statute of limitations had passed. In other words, because Cameron relied upon the language of G. L. c. 260, § 1, it now argues it would be inequitable to apply the shorter statute of limitations to its claim. The judge properly rejected this claim because estoppel is inapplicable in the circumstances of this case.
Courts have traditionally been “reluctant to apply principles of estoppel to public entities where to do so would negate requirements of law intended to protect the public interest.” Phipps Prods. Corp. v. Massachusetts Bay Transp. Authy., 387 Mass. 687, 693 (1982). See LaBarge v. Chief Admin. Justice of the Trial Ct., 402 Mass. 462, 468 (1988). See also Sullivan v. Chief Justice for Admin. & Mgmt. of the Trial Ct., 448 Mass. 15, 30-31 (2006) (“A common thread underlying our reluctance to apply principles of estoppel to public entities has been the idea that deference to legislative policy should trump individual acts or statements of a government official that may be contrary to such policy”). “This traditional reluctance had been justified by the need to protect the public from improper collusion by public officials, deference to legislative policy, concern about the public
Even if Cameron were able to establish the elements of estoppel,
Judgment affirmed.
Cameron claimed a breach of the covenant of good faith and fair dealing. See Nortek, Inc. v. Liberty Mut. Ins. Co., 65 Mass. App. Ct. 764, 768-769 (2006) (actions for breach of implied covenants are actions for breach of contract).
“For purposes of the Commonwealth’s consent to be sued, the University of Massachusetts and the Commonwealth are ‘one and the same party, namely
In pertinent part, G. L. c. 75, § 1, as amended by St. 1991, c. 142, § 16, provides: “In addition to the authority, responsibility, powers and duties specifically conferred [on the University] by this chapter, the board of trustees shall have all authority, responsibility, rights, privileges, powers and duties customarily and traditionally exercised by governing boards of institutions of higher learning.”
Cameron also claims that even if the three-year statute of limitations under § 3A applies to this contract, the University waived § 3A by executing a contract under seal. We disagree. The University has no authority to waive statutory requirements. See Dagastino v. Commissioner of Correction, 52 Mass. App. Ct. at 458. “[P]ersons who deal with a governmental agency must take notice of limitations upon that agency’s contracting power and cannot recover upon a contract which oversteps those limitations.” White Constr. Co. v. Commonwealth, 11 Mass. App. Ct. 640, 648 (1981).
The elements of estoppel are as follows: “(1) a representation intended to induce reliance on the part of a person to whom the representation is made; (2) an act or omission by that person in reasonable reliance on the representation; and (3) detriment as a consequence of the act or omission.” Sullivan v. Chief Justice for Admin. & Mgmt. of the Trial Ct., 448 Mass. at 27-28, quoting from Bongaards v. Millen, 440 Mass. 10, 15 (2003). The party asserting estoppel must also prove that its reliance upon the other party was indeed reasonable. O’Blenes v. Zoning Bd. of Appeals of Lynn, 397 Mass. 555, 558 (1986) .