DocketNumber: [No. 68, October Term, 1937.]
Citation Numbers: 197 A. 123, 173 Md. 554, 1938 Md. LEXIS 336
Judges: Bond, Urner, Offutt, Parke, Sloan, Mitchell, Shehan, Johnson
Filed Date: 2/3/1938
Status: Precedential
Modified Date: 11/10/2024
The Maas Construction Company sued the University of Maryland in the Superior Court of Baltimore City and recovered a judgment for $11,000 damages for breach of contract, from which the defendant appealed. The questions here presented for review of this court arise on the ruling on a demurrer to a second amended declaration, and brings into question the immunity of this university from suit by reason of its status as a governmental agency of the State, and also a question on the ruling on a prayer relating to an alleged breach of contract by the appellees, which, by their own wrong, it is claimed, precluded a recovery. The prayer was rejected on the theory that the plaintiff had not violated the terms of the contract by ceasing work in the construction of a dormitory, as provided in the contract. The University of Maryland urged upon the lower court, as it does here, that because of the relationship it bears to the State, it was entitled to immunity from suits of this character; and, further, that all of its funds being appropriated by law for the purposes of such agency are, therefore, charged with the public trust, and it is restricted in its expenditures to legislative appropriations and to those purposes expressly designated by law, and without any inherent authority to raise money for the payment of claims against it.
The questions before us are: First, is the University of Maryland, as a governmental agency, protected and immune from suits for damages unless legislative authority has been given to sue it, and has such authority been given; second, does it possess funds with which to pay the judgment if recovered against it, and if not, does this suit fail for that reason; and, third, did the construction *Page 556 company abandon the work under the contract without legal justification or excuse? We will consider these questions in the order named, first reviewing briefly the facts.
The contract in question provided for the construction of a dormitory for the University of Maryland. Under its terms, the construction company was entitled to receive ninety per cent of the value of the work done up to the first day of the month, less the sum of such payments previously made, and this payment was to be made on or about the tenth day of the succeeding month. The architect was required to certify, on or before the tenth day of each month, the amount of the work completed. Upon the failure of the University of Maryland to pay the construction company within seven days after the certificate was issued, the appellee had the right, upon seven days' written notice by them to the University of Maryland, to stop work and terminate the contract, and to recover from the University payment "for all work executed and any loss sustained upon any plant or materials and reasonable profits and damages."
In May, 1934, the work was commenced. A certificate, under the provisions of said contract, was issued on the 9th day of July, for $10,101.91, representing ninety per cent of the work actually done. The construction company, on the 11th day of July, demanded of the University of Maryland the payment of this sum, and notified it, unless the payment was made in accordance with the amount certified by the architect, pursuant to the terms of the contract, on or before seven days from the date of receiving the letter, they would stop work and terminate the contract.
The first difficulty between the parties grew out of a notice to the appellant, from the National Casualty Company, surety on the construction company's bond, requesting the university to withhold payments pending arrangements or assurances whereby the money paid would be used to pay subcontractors. Dr. H.C. Byrd, then vice-president of the university, notified the appellees *Page 557 of this request from the surety company, and suggested that they communicate with the surety company and endeavor to reach an agreement with respect to the application of payments, and, on July 17th, consent was had from the surety company that the university pay the amounts certified by the architect. On the 18th of July, the foreman of the company was advised that the money would be available for the payment at any time. This information was given to the foreman because neither of the appellees could be found. On July 20th, counsel of the appellees was advised that the surety company had withdrawn its objection and that the money would be paid as soon as the check could be cleared through the comptroller's office, but on the next day, the 21st of July, the construction company wrote the regents of the university as follows: "You are hereby advised that all work on said contract is being terminated as of this date, the equipment removed, and from and after this date all materials on the job are there at your risk. Our watchman will not remain on the premises after tonight." With this exchange of communications and assertions of rights, work under the contract was finally terminated. The construction company brought this suit to recover damages for the breach of contract, and the demurrer raises the question first above mentioned.
It has been decided in University of Maryland v. Murray,
In the case of State v. Rich,
These conclusions are supported in the case of Weddle v.School Commissioners,
The decisions in this state go further than holding that without legislative sanction an arm of the state government, such as the University of Maryland, may not be sued, and are to the effect that, even though there is a legislative authorization to sue, such suits may not be *Page 559
maintained unless funds are available or may be made available by the agency itself for the purpose of paying the claim for damages that may be established by the suit. And this is supported by the case of Fisher Carrozza Bros. Co. v. Mackall, supra. This court there said, quoting from Weddle v. School Commissioners,
So it is established that neither in contract nor tort can a suit be maintained against a governmental agency, first, where specific legislative authority has not been given, second, even though such authority is given, if there are no funds available for the satisfaction of the judgment, or no power reposed in the agency for the raising of funds necessary to satisfy a recovery against it.
It is conceded that the case of University of Maryland v.Murray, supra, is authority for the proposition that the University of Maryland is distinctly a state agency, but the doctrine that suits may not be maintained for the recovery of damages for tort, or breach of contract, could not be ascribed to that case, because that was not a suit for the recovery of money and did not involve the question whether funds were appropriated for specific purposes, or the right of the university to raise money for the purpose of paying damages. That case decided: "That the corporation thus created is an instrumentality or agency of the State is plain, and we do not understand it to be disputed. ``When the corporation is said, at the bar, to be public, it is not merely meant, that the whole community may be the proper objects of the bounty, but that the government has the sole right, as trustees of the public interests, to regulate, control and direct the corporation, *Page 560
and its funds and its franchises, at its own good will and pleasure.'" Dartmouth College v. Woodward, 4 Wheat. 518, 671, 4 L. Ed. 629; Regents of University of Maryland v. Williams, 9 G. J. 365, 397; Finan v. Cumberland,
Under the Laws of 1916, ch. 372, the State College of Agriculture was declared to be "capable in law suing and being sued" (section 1), and the University of Maryland, under the Laws of 1812 (chapter 159), was declared to "be able in law to sue and to be sued, plead and interplead, answer and be answered, in any Court or Courts, before any judge or judges within this State, and elsewhere, in all manner of suits, pleas, cases and demands of whatever kind, nature or form that may be, and to do all and every other matter and thing hereby contemplated to be done, in as full and effectual a manner as any other person or persons. bodies corporate or public in like cases can or may do." Thus was the University of Maryland by legislative enactments rendered liable to be sued, but even so, this does not fully satisfy the requirements of the rule, because it is definitely alleged and clearly shown that the University of Maryland has only such funds as are appropriated for its use by the Legislature of Maryland, to be distributed by another arm of the state government, namely, the Comptroller and Treasurer of the State, for definite and limited purposes, nor has the University of Maryland power or authority, in itself, to raise moneys for the payment of damages. Therefore, this suit can no more be maintained against the appellant than suits can be maintained against the State *Page 561
Roads Commission (Fisher Carrozza Bros. Co. v. Mackall,supra); the State Normal School (Williams v. Fitzhugh, supra); the School Commissioners for Frederick County (Weddle v. SchoolCommissioners, supra); or the House of Refuge. See Perry v.House of Refuge,
This doctrine is supported in other jurisdictions in which there was a denial of the right to bring actions of tort against state agencies existing and operating under statutory and other authority or conditions analogous to those here presented.Minear v. State Board of Agriculture,
It is, nevertheless, strongly urged that the appropriation for the construction of the dormitory had already been made, to be paid out of federal and state funds in hand, and that there was available money with which to pay the appellee's claim for work done and materials provided and for reasonable profits thereon. The undisputed testimony of Dr. H.C. Byrd does not bear this out, but is to the contrary. He states that the University of Maryland did not have a penny with which, on its own account, to make such payments, or to pay a judgment recovered therefor. The manner in which payments, for the use or benefit of the University, were *Page 562 made was clearly stated, as above. Even the tuitions received are paid into the state treasury and disbursed like other state funds.
The money, both state and federal, was appropriated for a certain and definite public need and for no other, and thus was impressed with a trust for the use of the public. The diverting of these funds, or any part thereof, for other uses, would be in violation of the purpose of this appropriation and cannot be sanctioned.
The plaintiffs, while asserting that these funds were available to pay their claim, offered no evidence to substantiate their contentions and it may be inferred that the entire fund appropriated has long since been expended in the construction of the proposed building. More than three and one-half years have elapsed since this project was inaugurated and the Attorney General, acting for the university, in his letter of August 13th, 1934, wrote counsel for the contractors, "Because of the refusal of the contractor to carry out its obligations under the contract * * * for no good cause, we are making other arrangements for the completion of the work"; and it is common knowledge that this dormitory has been completed and thus the funds in question have been expended. The prayer designed to withdraw the case from the jury should have been granted.
This being our conclusion, it is unnecessary to consider the other points raised by the prayers as to the right of recovery in the plaintiffs because of their own failure to comply with the terms of the contract in giving the notice provided for in the contract, before suit may be brought.
Judgment reversed without a new trial, with costs.
URNER, PARKE, and JOHNSON, JJ., dissent. *Page 563
State Ex Rel. Weddle v. Board of County School Commissioners , 94 Md. 334 ( 1902 )
Williams v. Fitzhugh , 147 Md. 384 ( 1925 )
University of Maryland v. Murray , 169 Md. 478 ( 1936 )
Mayor of Baltimore v. State Ex Rel. Blueford , 173 Md. 267 ( 1937 )
Finan v. M. C.C. of Cumberland , 154 Md. 563 ( 1928 )
County Commissioners v. Love , 173 Md. 429 ( 1938 )
University of Maryland v. Coale , 165 Md. 224 ( 1933 )
Stanley v. Mellor , 168 Md. 465 ( 1935 )
State Ex Rel. Watkins v. Rich , 126 Md. 643 ( 1915 )
Kee v. State Highway Administration , 68 Md. App. 473 ( 1986 )
Board of Trustees of State Universities & Colleges v. ... , 75 Md. App. 289 ( 1988 )
Lohr v. Upper Potomac River Commission , 180 Md. 584 ( 1942 )
Comptroller of the Treasury v. Panitz , 267 Md. 296 ( 1972 )
Charles E. Brohawn & Bros. v. Board of Trustees of ... , 269 Md. 164 ( 1973 )
O & B, Inc. v. Md.-Nat'l Cap. P. & P. Commission , 279 Md. 459 ( 1977 )
Department of Natural Resources v. Welsh , 308 Md. 54 ( 1987 )
Condon v. State , 332 Md. 481 ( 1993 )
Stern v. Board of Regents , 380 Md. 691 ( 2004 )
Magnetti v. University of Maryland , 171 Md. App. 279 ( 2006 )
Bugg v. Maryland Transportation Authority , 31 Md. App. 622 ( 1976 )
Mta Lodge No. 34 v. Mta , 195 Md. App. 124 ( 2010 )
Gardner v. State , 77 Md. App. 237 ( 1988 )
Jackson v. Housing Opportunities Commission , 44 Md. App. 304 ( 1979 )
Katz v. Washington Suburban Sanitary Commission , 284 Md. 503 ( 1979 )
Maryland State Highway Administration v. Kim , 353 Md. 313 ( 1999 )
Magnetti v. University of Maryland , 402 Md. 548 ( 2007 )
American Structures, Inc. v. Mayor of Baltimore , 278 Md. 356 ( 1976 )
Frosburg v. State Department of Personnel , 37 Md. App. 18 ( 1977 )