DocketNumber: No. 317
Judges: McWilliams
Filed Date: 6/27/1969
Status: Precedential
Modified Date: 11/10/2024
delivered the opinion of the Court.
Appellant (Raine), a Silver Spring plumbing contractor, replaced the coils, ruptured by freezing, in two (#1 and #2) “air handlers,” in a large office building in Bethesda owned and operated by appellees (Friedman). When Friedman refused to pay the bill (stipulated to be $1,646.47) Raine filed suit. From the judgment in favor of Friedman for costs, entered by Loveless, J., sitting without a jury, Raine has appealed. Prior to the incident out of which this dispute arose Raine had done several jobs for Friedman and their relationship had been mutually satisfactory.
In October 1966 Friedman was anxious to increase the flexibility of his heating and cooling system. He telephoned Raine and asked him for an estimate of the cost of installing several gate valves in the pipes which supplied hot and cold water to the system. To accomplish this the entire system had to be drained because of the
At 8 a.m. on the appointed day Willis Washington, Friedman’s resident engineer, arrived at the building. He was two hours late, having been directed to report at 6 a.m. He shut down the boiler, opened the drain valves in the basement and the relief valves in the penthouse. It was very cold. Saturday’s temperature had averaged 26 degrees; Sunday was even colder. On neither day did the thermometer rise above 32 degrees. Raine’s men, led by Hildebrand, the foreman, arrived at 9 a.m. Water was still draining from the system, a process which requires from an hour and a half to two hours. Washington said he “had a few things to do upstairs” so he took Hildebrand to the boiler room and showed him where the water was running out. He said there was nothing Hildebrand had to do to complete the draining of the system except to wait until the water stopped running out. When that happened Hildebrand and his men began the work.
To properly comprehend the crux of this dispute it becomes necessary, at this point, to understand the function and the operation of the two (of five) air handlers that had been placed between the first floor ceiling and the underside of the second floor. Their function, of course, is the exchange of heat. A length of coiled tubing to which fins are attached is arranged within the air handler so that a fan driven by an electric motor blows a stream of air across the tubing. If hot water is running through the tubing the air will be heated. If the
There appears to be no dispute about the fact that the fans in all of the air handlers were operating when Washington left the building at 9 a.m. He said he “had no reason to turn them off.” It is undisputed also that they continued to operate during the day. When Washington returned to the building at 6 p.m. (Saturday) Hildebrand told him one of the welders had complained about cold air “blowing in on him” and he asked him (Washington) “to cut the fans off.” He could have accomplished this by tripping a circuit breaker in the boiler room but Washington did not know about that. He was not familiar with the air handlers as they had been installed at a time when he had been employed elsewhere. Hildebrand helped him remove the ceiling panels beneath each of the five air handlers so as to gain access to the switch which was affixed to each one. In this manner each of the fans was stopped.
The job did not move along as rapidly as Raine hoped
Friedman testified that on Monday, 5 December, he told Raine that he was “in terrible jeopardy * * * and it was absolutely necessary to have everything possible done to replace these coils and put these air handlers back into operation.” After Raine had inspected the coils he told Friedman that repair was impossible; the coils would have to be replaced. Price was not discussed. Friedman said he was not “concerned about a price” at that time. Friedman, to expedite matters, guaranteed the payment of the bill for the new coils. Two weeks later, upon the delivery of the coils, Raine did the work and in due course submitted his bill. It ought to be noted that, in the meantime, his bill for the installation of the gate valves (on 3 and 4 December) had been paid, apparently without question.
We think the record makes it quite clear that when Friedman instructed Raine to replace the ruptured coils with new ones, he expected eventual reimbursement from his insurance company (Lumbermens), but we think it is equally clear that Raine did not agree to make his bill subject to such a contingency. Friedman testified “that if the insurance company had paid * * * [him, he] would have
“Dear Mr. Green:
“We are enclosing the invoice from Gerald Raine in the amount of $1,646.47 for repairing the two air handling units which froze on the night of December 4, 1966. As discussed with you, this building damage is covered under our Lumbermen’s Insurance Policy #60-56193, and payment for this invoice will be forthcoming as soon as it is processed by you and Lumbermen’s Insurance Co.
Very truly yours, BETHESDA AVENUE ASSOCIATES /s/ Harry D. Friedman”
Indeed, it seems to us to be somewhat more than likely that Friedman’s subsequent disinclination to pay Raine was prompted by Lumbermens. Such an attitude would seem to be consistent with Lumbermens’ suit (as subrogee) against Raine to recover for the damage caused by the water which leaked out of the ruptured coils.
The two cases, filed originally in the Circuit Court for Montgomery County but later removed to the Circuit Court for Calvert County, came on for trial before Judge Loveless on 22 October 1968, having been consolidated for that purpose. At the conclusion of the evidence Judge Loveless announced from the bench that Lumbermens was not entitled to recover from Raine. He found “no evidence * * * that Raine * * * had any knowledge of this other system [the air handlers] in the rest of this building.” He found also that “the primary obligation * * * to drain” the system rested with Friedman. He commented on Washington’s ignorance of the existence of the “drain cocks” on the air handlers. “While Raine may
Judge Loveless also found that Raine was not entitled to recover against Friedman. He seems to have been of the opinion that there was no agreement that Friedman would pay Raine for the work. On 21 November 1968, following a motion filed pursuant to Maryland Rules 18 c and 564 b 2, he filed a written opinion in which he restated his reasons for deciding against Lumbermens. In Raine’s case, however, he added something, namely, that he “felt that the Raine Company had been negligent in not recognizing that under the circumstances and situation which existed, the freezing would occur.” He said he accepted the testimony of Houghton (called by Friedman as an expert) “that a prudent plumber should have recognized this danger.”
We shall set aside the judgment of the lower court because we think, on the evidence in this record, it is clearly erroneous. Rule 886 a. Houghton (the expert) described himself as a mechanical contractor with 27 years of experience in the field of plumbing, heating, air conditioning and specialty piping. He is a licensed plumber; he has a master refrigeration license; he helped set up the code (refrigeration) for the District of Columbia; he actually installed the air handlers in which Raine replaced the ruptured coils. We did not find in his testimony any statement to the effect that “a prudent plumber should have recognized this danger.” His own words put it somewhat differently:
“Q. At any rate, it £air handlers] is something that an experienced plumber would know was present in the building?
“A. An experienced mechanic, not necessarily a plumber.” (Emphasis added.)
In our judgment there is nothing in this' record which
Friedman presses the argument that Raine and Hildebrand, knowing how cold it was, should somehow have discovered or suspected that water might be trapped in the coils and that it might freeze. In this regard we think it is highly significant that, although the fresh water system, the wash basin traps, and the toilet tanks and bowls had not been drained, there was no freezing anywhere else in the building despite the fact that it had been without heat for nearly 24 hours. The trapped water in the coils of the other three air handlers did not freeze. We think it is an obvious conclusion that the water in #1 and #2 air handlers froze because the air being blown over the coils, before the fans were turned off, was below
We are not impressed with the contention that Friedman neither expressly nor impliedly agreed to pay Raine for the replacement of the damaged coils. They were not strangers dealing at arm’s length. Raine had done other work for Friedman. Apparently it had been done satisfactorily; his bills were paid. In this instance Friedman was “in terrible jeopardy” and he pressed Raine “to have everything possible done to replace the coils and put these air handlers back into operation.” Raine said he would do it. They did not discuss price. Friedman said he wasn’t “concerned about a price.” It might be noted parenthetically that the reasonableness of Raine’s bill is not disputed and that the job is conceded to have been well done. If at that time Friedman had in mind holding Raine responsible for the freezing of the coils and the damage
On the evidence in this record we are fully persuaded that Friedman ordered the work, that Raine agreed to do the work and that Friedman impliedly agreed to pay for it and our holding does not require the citation of authorities. As we have indicated we shall reverse the judgment entered by the learned trial judge.
Judgment reversed.
Judgment entered in favor of appellant against appellees for $l,6/+6.47, with costs.