Judges: DOUGLAS F. GANSLER, Attorney General.
Filed Date: 3/23/2010
Status: Precedential
Modified Date: 7/5/2016
The Honorable George C. Edwards
You have asked about the responsibilities of the Department of Natural Resources ("DNR"), the Public Service Commission ("PSC"), and other agencies with respect to the protection of endangered species. Citing Animal Welfare Institute v. Beech Ridge EnergyLLC,
In comparison to the federal statute, the State endangered species law provides similar, although not identical, protections for State-listed threatened and endangered species. Given that the State law was patterned after the federal statute, Maryland courts construing the State statute are likely to apply the standards developed under the federal statute. In Beech Ridge, the federal district court granted an injunction against a wind energy project in West Virginia after it was demonstrated that the project was "reasonably certain" imminently to harm, kill, or wound a listed endangered species and the developer of the project had not obtained a permit allowing the incidental taking of an endangered species. This opinion describes generally the roles of DNR, the PSC, and certain other State agencies under the State endangered species law s. In addition, it discusses possible consideration by DNR and the PSC of impacts on endangered species when those agencies implement statutes governing new power generating facilities. *Page 85
Regulations defining "harm" and "harass"
The regulations implementing the federal ESA define the activities that constitute an impermissible "take." For example, "harass" means "an intentional or negligent act or omission which creates the likelihood of injury to wildlife by annoying it to such an extent as to significantly disrupt normal behavioral patterns which include, but are not limited to, breeding, feeding, or sheltering."
A person who knowingly takes an endangered species in violation of the federal ESA is subject to significant civil and criminal penalties.
Incidental take permits
Congress amended the federal ESA in 1982 to provide a "safe harbor" from these penalties. In particular, that amendment
established an "incidental take permit" ("ITP") process that allows an entity or other person to lawfully take an endangered species "if such taking is incidental to, and not the purpose of, the carrying out of an otherwise lawful activity."
Beech Ridge Energy,Congress established this process to reduce conflicts between species threatened with extinction and economic development activities, and to encourage "creative partnerships" between public and private sectors.
§ 1538(a)(1)(B). Beech Ridge Energy had not obtained an ITP.
The question before the court was whether Beech Ridge Energy should have obtained an ITP because the wind turbines potentially would take the Indiana bats present at the project site. In assessing this claim, the court observed that the federal ESA is silent on the requisite degree of certainty for establishing a "take."
Standard for showing that a project would "harass"
With respect to the standard for demonstrating whether a project would "harass" an endangered species — a question left open inBeech Ridge — there are few cases that construe that term. InBabbitt v. Sweet Home Chapter,
. . . if the statutory term "harm" encompasses such indirect means of killing and injuring wildlife as habitat modification, the other terms listed in [the definition of "take"] — "harass," "pursue," "hunt," "shoot," "wound," "kill," "trap," "capture," and "collect" — generally retain independent meanings. Most of those terms refer to deliberate actions more frequently than does "harm," . . . In addition, most of the other words in the definition describe either actions from which habitat modification does not usually result (e.g., "pursue," "harass") or effects to which activities that modify habitat do not usually lead (e.g., "trap," "collect"). . . .
The lower court decisions that construe the term "harass" generally paraphrase the definition in the federal regulation. The Ninth Circuit has stated that a party attempting to prove a "take" in the form of harassment must demonstrate "by a preponderance of the evidence that the proposed construction would . . . more likely than not harass [the endangered species] by annoying it to such an extent as to disrupt its normal behavioral patterns." SeeDefenders of Wildlife v. Bernal,
In Marbled Murrelet v. Pacific Lumber Co., 880 F.Supp.1343, 1367 (N.D. Cal. 1995), the federal district court granted injunctive relief in part because it found that a proposed timber harvest during the breeding season of an endangered species "creates the likelihood of injury [to the species] by annoying them to such an extent that it will significantly disrupt their normal behavior patterns." On appeal, the Ninth Circuit affirmed the grant of injunctive relief, but did not discuss the harassment standard or the sufficiency of the evidence under that standard, as it determined *Page 88
that the timber harvest would "harm" the endangered species.Marbled Murrelet v. Babbit,
If, as suggested in the Sweet Home Chapter decision, the term "harass" refers only to deliberate efforts to affect wildlife and does not ordinarily include habitat modification, it may not apply to a wind turbine project. In any event, it appears from the extant case law that, to obtain relief on the basis that a project would "harass" an endangered species, a plaintiff would have to demonstrate, by a preponderance of the evidence, that it was "more likely than not" that the project would annoy the endangered species to such an extent as to disrupt normal behavior patterns.
Definitions of key terms similar to federal law
The definition of "take" is the same as the federal ESA definition. See NR §
No Maryland appellate court has construed the terms "take," "harm," or "harass" as they appear in the State ESA. However, these are the same key terms that appear in the federal ESA and the State ESA is designed specifically to coordinate with the federal ESA.See NR §
Creation of lists of species
The State ESA encompasses any species which is considered endangered or threatened under the federal ESA. NR §
Remedies
A person who takes an endangered species protected by the State ESA is subject to a fine of not more than $1,000, imprisonment for not more than one year, or both. NR §
The State ESA authorizes the Secretary of Natural Resources to issue permits for activities otherwise forbidden by the statute "for scientific purposes" or "to enhance the propagation or survival of the affected species." NR §
DNR may enter into conservation agreements with political subdivisions, other states, federal agencies, and even individuals concerning conservation of threatened or endangered species. NR §
Finally, DNR's Natural Resources Police are authorized to make arrests, conduct searches, and seize evidence and contraband related to criminal violations of the State ESA. NR §
This provision applies to all State agencies. It can come into play, for example, when the Maryland Department of the Environment ("MDE") issues permits in connection with its review of projects under the Nontidal Wetlands Protection Act, Annotated Code of Maryland, Environment Article ("EN"), § 5-901 et seq. If a landowner proposes to carry out regulated activities within nontidal wetlands, the landowner must first apply for and obtain a permit from MDE. When reviewing applications, MDE determines, through consultation with DNR, whether the proposed project will have an adverse impact on a listed species or its habitat. If it will, MDE evaluates options for reconfiguring the project to avoid the impact, and if the impact is unavoidable, requires mitigation measures that ensure that the project will not "jeopardize the continued existence of" a listed species or "result in the destruction or modification of" the species' critical habitat. See NR §
You specifically asked about the responsibilities of the PSC with respect to endangered species. The State ESA itself does not assign any particular responsibility to the PSC that is distinct from other agencies. Like other agencies, the PSC is to consult with DNR as necessary to ensure that its actions do not jeopardize the existence or habitat of an endangered or threatened species. In addition, under a law that predates the State ESA — the Power Plant Siting Act of 1971 ("Siting Act")3 — the PSC is obligated to consult with DNR concerning the environmental ramifications of certain matters before it. That consultation may include the impact of a proposal on endangered species. We describe that law in greater detail in the next section. *Page 92 Responsibilities under Siting Act
The Siting Act establishes a licensing process for certain new generation facilities that integrates a comprehensive evaluation of a proposed construction site and the impact of the project on the surrounding community and the State. See generally Annotated Code of Maryland, Public Utility Companies Article ("PUC"), § 7-207 et seq.; NR §§
Under the Siting Act, the PSC is the principal licensing authority for new generation in Maryland, but is subject to a requirement to evaluate and balance a number of factors as part of the decision making process. PUC § 7-207(e). Beyond this consideration of specified factors, the PSC is required to ensure that its approval of the project and any conditions imposed on the developer meet State and federal statutory and regulatory requirements as determined by MDE and, more importantly for this issue, by a determination by DNR that a particular site is suitable for the proposed construction. See PUC § 7-208.
As a threshold issue, the Siting Act requires the Secretary of Natural Resources to make a preliminary determination that a proposed site is suitable for the proposed construction. NR §
For example, in a CPCN proceeding several years ago involving an application for a 40 megawatt wind facility in Garrett County, the Secretary of Natural Resources deemed a portion of a proposed site for an array of wind turbines unsuitable because of the likelihood the construction would result in a "take" of several protected species.5 In this instance, agency review of the proposed site uncovered a number of State-listed species, particularly in the mid-portion of the site. The Secretary of Natural Resources deemed that portion of the site unsuitable and advised the Commission of his finding together with the supporting evaluation.6 The PSC Hearing Examiner adopted the Secretary's recommendation and issued a proposed order that granted a CPCN for the suitable portions of the site, but prohibited construction in the unsuitable portion of the site.
Subsequent legislation created an exception to the CPCN requirement for wind generation facilities of 70 megawatts or less. Chapter 163, Laws of Maryland 2007, now codified as PUC § 7-207.1. That provision also establishes an abbreviated approval process for these facilities that does not include the same comprehensive environmental review provided by the CPCN process. However, the PSC would still have to take the State ESA into account in implementing that provision. *Page 94
The State ESA charges DNR with carrying out particular functions. It also requires all State agencies, in consultation with DNR, to ensure that their actions do not jeopardize endangered or threatened species. Finally, the PSC is to obtain the views of DNR as to the suitability of energy projects, including wind projects that satisfy certain criteria, when it decides whether to issue a CPCN for such a project.
Douglas F. Gansler Attorney General
Robert N. McDonald Chief Counsel
Opinions and Advice*