DocketNumber: No. 44
Citation Numbers: 49 Md. App. 676
Judges: Lowe
Filed Date: 10/7/1981
Status: Precedential
Modified Date: 10/18/2024
delivered the opinion of the Court.
This is an appeal from the Circuit Court for Anne Arundel County by Bruce C. Hill, Trustee (Hill) of the Estate of C. George Mills and Sons, Inc. (Mills) who was awarded $315.06 of a claim against Parkway Industrial Center (Parkway) for $8,229.25. The latter amount was said to be due on a contract with Mills to build a bank and office building on Parkway’s property. Mills subcontracted with Barber-Coleman Company to furnish and install temperature controls on the project. By October 25, 1978, Barber-Coleman substantially completed its work for Mills.
On December 22, 1978, Mills executed a Deed of Trust for the benefit of creditors and appellant Bruce C. Hill was named Trustee. Five days later, on December 27, 1978, Barber-Coleman notified Parkway of its intent to claim a mechanics’ lien against the project property belonging to Parkway. On January 17, 1979, the Circuit Court for Baltimore County assumed jurisdiction of the Trust Estate of Mills. Meanwhile, on April 10,1979, the Circuit Court for Anne Arundel County ordered a mechanics’ lien established in favor of Barber-Coleman against Parkway for $7,914.19 and ordered the property sold unless paid on or before April 30,1979. Parkway paid Barber-Coleman to effect the release of the lien in compliance with the court order.
On May 29, 1980, Hill as Trustee for Mills, sued Parkway to obtain the payments which Parkway had withheld because Mills had allegedly failed to complete its work and finish the job, or to fulfill its guaranties, pay its subcontractors and provide Parkway with lien releases.
The trial court found that Mills had substantially performed its work under its contract with Parkway and was therefore due $8,229.25 from Parkway as of November 9, 1978. The court also found that Barber-Coleman had substantially completed its work under the agreement with
Pursuant to the Mechanics’ Lien Law, Md. Real Property Code Ann. § 9-104 (f) (1980), the owner of the land upon which improvements are made may withhold sums due a contractor in the amount the owner ascertains to be due a subcontractor who has notified the owner of an intent to claim a lien. To avoid this statute appellant contends that Parkway is in this case both owner and contractor because of the contractual terminology so specifying.' Because appellee "is not an owner exclusively. . .”, appellant claims that appellee may not avail itself of the right to withhold under § 9-104 (f). Appellant contends semantically that appellee as owner may withhold payments only from itself as contractor. The chancellor charitably addressed this contention as a "fine distinction” but nonetheless held that Parkway was an owner entitled to invoke the rights under § 9-104 (f).
The Mechanics’ Lien law was designed, in part, to provide the property owners as a second source of payment since they receive the ultimate benefit of services and materials and, as a practical consideration, control the cash. Palmer Park Ltd. v. Marvelite, Inc., 255 Md. 121, 126 (1969). That appellee was such an owner was a finding of fact which we do not find to have been clearly erroneous in light of the § 9-101 (e) definition.
"Before issuance of the final payment the Subcontractor [Mills], if required, shall submit evidence satisfactory to the Contractor [Parkway] that all payrolls, bills for materials and equipment, and all known indebtedness connected with the Subcontractor’s Work have been satisfied.”
But the issues relating to the chancellor’s factual findings are merely a prelude to the heart of the appellant’s contention. Hill’s legal arguments are summarized by him in two sentences:
"I. In order for a claim of a debtor of an assignor for the benefit of creditors to acquire a claim against the assignor, that may be used as a setoff to the debtor’s own liability, that claim must arise before the date of the assignment for benefit of creditors.”
"II. A claim against the assignor for the benefit of creditors must arise before the date of the commencement of proceedings for the assignment for the benefit of creditors in order to have a setoff*680 against the trust estate which would not be a preference.”
Both of appellant’s arguments concerning what claims may be used as setoffs deal almost exclusively with when the claim arises. He relies primarily upon Richardson v. Anderson, 109 Md. 641 (1909) which he refers to as the "seminal case in Maryland dealing with the law of assignment for the benefit of creditors”. In Richardson, the Maryland Grain Agency executed a deed of trust for the benefit of creditors on February 27, 1908. Anderson was the trustee. Richardson had been the agency manager and owed the agency $1,541.71 for which Anderson, as trustee, sued him. Among Richardson’s defenses was a claimed equitable setoff for the amount of a note then due to George Merryman from whom Richardson obtained it by endorsement after the assignment by Maryland Grain for the benefit of its creditors.
The Court of Appeals pointed out that it would be unjust, inequitable and intolerable in law or equity to permit a debtor to purchase, for a small consideration, claims against the assignor and acquire preferences in the distribution of the trust estate. Id. at 645.
Richardson had also been an accommodation endorser, prior to the assignment, for an agency indebtedness which came due after execution of that deed of trust. The Court decided that in order for there to be a setoff in favor of the creditor of the assignor, the debt must exist at the time of the assignment by virtue of a claim then due. Id. at 646.
From these two issues in Richardson, appellant in the case before us has concluded several rules of law governing assignment for the benefit of creditors. First he concedes the primary Richardson predicate:
That an assignee for the benefit of creditors takes property subject to all existing equities...,
and further that
The equities need not exist at the inception of the debt.
*681 It is sufficient if they exist prior to the assignment.
But these concessions are made in passing to reach the rule upon which his arguments rest:
A claim acquired after the assignment cannot be set off against the assignee; nor a liability, existing but not due at the time of the assignment, even if it becomes due before the suit was commenced.
In order to determine when a claim is acquired one first must determine what the term means. "Claim” is defined by Black’s Law Dictionary (333 3rd ed., 1944) as
"A legal capability to require a positive or negative act of another person.” (emphasis added).
Appellant, however, equates the establishment of a lien for priority purposes with when a "claim” is due. While it is certainly true that a mechanics’ lien does not attach until it is established by the court after procedural conformity, Mervin L. Blades and Son, Inc. v. Lighthouse Sound Marina and Country Club et al., 37 Md. App. 265, 27 (1977), the lien is only a means of receiving payment, it is not the claim upon which the lien is founded. The debt or claim upon which a lien is predicated becomes due when the work is done or the materials supplied. For ninety days after completion a subcontractor is given a statutory alternative against which he may proceed on the debt that has come due. The claim to which he is, upon completion, entitled is consummated and collected simply by notifying the property owner, § 9-104 (a), and proceeding as outlined in the statute within 180 days after the work is finished or the materials furnished, § 9-105 (a). The statute clearly presupposes a debt due when the work was completed, which it was here by Barber-Coleman no later than October 25,1978, as factually found by the chancellor.
The term "claim” is more analogously interpreted here in light of its use in the second issue raised by Richardson. The second issue was whether Richardson could set off against
To have construed Richardson as appellant would have us do, would create the harsh and unfair result of having equity courts compel Parkway to pay twice a single debt. Richardson simply holds that a defendant has all of the rights after an assignment that he would have had before it, but not one whit more — and that seems fair indeed. He may not take advantage of an insolvent’s misfortune by buying claims or paying off debts to which he had not yet been exposed simply to gain an advantage over fellow creditors;
Judgment affirmed.
Costs to be paid by appellant.
. Md. Real Prop. Code Ann. § 9-101 (e) (1980):
"Owner. — 'Owner’ means the owner of the land except that, when the contractor executes the contract with a tenant for life or for years, 'owner’ means the tenant.”
. Constituting such a payment as a statutorily proscribed "preference” through a rather convoluted reasoning process also avails appellant naught. To do so he again fails to distinguish between the attachment of a