DocketNumber: Docket Nos. 54615-54616, (Calendar No. 4)
Citation Numbers: 228 N.W.2d 380, 394 Mich. 59, 1975 Mich. LEXIS 203
Judges: Swainson, Williams, Levin, Coleman, Fitzgerald, Kavanagh
Filed Date: 4/29/1975
Status: Precedential
Modified Date: 11/10/2024
Supreme Court of Michigan.
Wells, Wilmoth, Keating & Nitz, P.C. (by Daniel J. Henry, Jr., and Donald P. Schuur), for plaintiff.
Dakmak, Gropman & Sinai, P.C., and Liberson, Fink, Feiler, Crystal & Burdick P.C. (by Jeffery L. Schmier), for defendant Central Park North Co. and American Casualty Company.
T.G. KAVANAGH, C.J.
This is an action to foreclose a materialman's liens.
Central Park North Co. owns an apartment complex consisting of six interconnected apartment buildings which during construction were numbered from 1 through 6. Hollenbeck Drywall, Inc., now bankrupt, was the drywall subcontractor for the complex. Georgia-Pacific Corporation, plaintiff-appellant, sold drywall materials to Bob Ryan, Inc., a wholesaler. Bob Ryan sold and delivered drywall materials to Hollenbeck Drywall which were used in constructing the complex.
Bob Ryan began delivering materials to buildings #4 and #5 on May 26, 1965, and continued through June, 1965. Payments for those materials were made to Bob Ryan by means of promissory *62 notes which were then assigned by Bob Ryan to Georgia-Pacific.
On June 16, 1965, Bob Ryan was notified by Georgia-Pacific that it would no longer accept Hollenbeck's promissory notes in lieu of cash. On July 12 Bob Ryan began delivering materials to building #1.
On September 9, 1965, Bob Ryan began delivering materials to building #2.
On October 3, 1965, Bob Ryan served a notice of intent to file a mechanics' lien against building #1 for the value of materials furnished to it and followed the same procedure for building #2.
On October 14, 1965, shortly after the notices of intent to claim liens were served on Central Park North, the general contractor, Hamilton Construction Company, issued a check for the sum of $4,104 made payable jointly to Hollenbeck Drywall and Bob Ryan. The purpose of the check was not designated.
Hollenbeck Drywall negotiated the check solely upon its endorsement without notice to Bob Ryan.
On February 10, 1966, mechanics' liens against buildings #1 and #2 were filed by Bob Ryan in accordance with MCLA 570.5; MSA 26.285. These liens were subsequently assigned to Georgia-Pacific.
On March 24, 1966 Central Park North posted two bonds to vacate the liens resulting in the surety, American Casualty Company, becoming a codefendant.
Georgia-Pacific on January 13, 1967, instituted suit to foreclose its liens.
In February, 1967, the bank that had erroneously cashed the check made payable jointly to Hollenbeck Drywall and Bob Ryan paid Bob Ryan the $4,104. Bob Ryan sent this money to Georgia-Pacific *63 to apply to the oldest indebtedness of Hollenbeck Drywall, that is the money owed on the promissory notes held by Georgia-Pacific. Bob Ryan did not apply that money as a credit on the liens.
Judgment was entered in favor of Georgia-Pacific in the amount of $10,423.91. That amount included the lien of $3,575.22 against building #1 and the lien of $11,391.15 against building #2 minus $438.46[1] for an invoice that was disallowed, and also minus the payment of $4,104.
Central Park North argues that the liens are void for two reasons: a) Bob Ryan was acting in bad faith by not reducing the amount claimed in the liens by the $4,104 paid by Hamilton Construction and by the $438.96 which the trial court disallowed; and b) the notices of intent to claim the liens were not timely served.
The Bad Faith Issue
The trial court held that the $4,104 was paid in response to a request for payment by Hollenbeck and was for materials used in buildings #1 and #2 and, therefore, should have been subtracted from the amount claimed by the liens. Accordingly, the trial court credited Central Park North with that amount and reduced the claim of $14,527.91 to a judgment of $10,423.91 plus interest.
Central Park North argues that Bob Ryan knowingly inflated the statements of accounts and liens filed on February 10, 1966, pursuant to MCLA 570.5; MSA 26.285, and was therefore, acting in *64 bad faith. For support Central Park North cites Gibbs v Hanchette, 90 Mich. 657; 51 N.W. 691 (1892); J E Greilick Co v Taylor, 143 Mich. 704; 107 N.W. 712 (1906); Silverstein v Berman, 254 Mich. 478; 236 N.W. 840 (1931); Equitable Trust Co v Detroit Golf & Recreation Co, 260 Mich. 606; 245 N.W. 531 (1932); Currier Lumber Co v Ruoff, 298 Mich. 505; 299 N.W. 163 (1941); Sacchetti v Recreation Co, 304 Mich. 185; 7 NW2d 265 (1943).
Each of the cases cited involved the voiding of a lien because the statement of account was held to have been made in bad faith. In the instant case when Bob Ryan filed its statements, it had not yet received the $4,104. Thus, including it in the amount due was not inaccurate as to the $4,104 at that time.
Although Bob Ryan was in error in not subsequently reducing the amount of its claim prior to trial, the trial court considered that error and the erroneous inclusion of one invoice in reaching judgment, and thus apparently did not find Bob Ryan's errors to have been made in bad faith.
In mechanics' liens cases the question of bad faith depends to a great degree on the facts and circumstances shown. Sacchetti v Recreation Co, 304 Mich. 185, 192; 7 NW2d 265 (1943). From our reading of the record, we do not find sufficient evidence to support a conclusion that Bob Ryan's errors were made in bad faith so as to void the liens.
The Timely Notice Issue
Section 1 of the mechanics' liens act, MCLA 570.1 et seq.; MSA 26.281 et seq., requires, inter alia, that a materialman must serve on the owner a written notice of intent to claim a lien against a *65 building for any amounts unpaid for the materials furnished to that building. Such notice must be served "within 90 days after furnishing the first of such material". MCLA 570.1; MSA 26.281.
The trial court found from the evidence before it that Bob Ryan contracted with Hollenbeck Drywall to furnish materials on an individual per building basis, that the buildings on the project were separate and divisible, and that the notices of intent to file liens against buildings #1 and #2 were timely served within 90 days of the first deliveries to those buildings. We agree with those findings of facts and affirm the judgment of the trial court.
The Court of Appeals after a de novo review of the record found that there was only a single contract between Bob Ryan and Hollenbeck Drywall for the furnishing of materials to a single project consisting of six separate buildings. It held that the liens were void because they were not served within 90 days of the first delivery to the project, i.e., within 90 days of the delivery of materials to buildings #4 and #5 on May 26, 1965.
As authority for the proposition that when several buildings are constructed under a single contract the project must be treated as a single improvement under the mechanics' liens act, the Court cited Union Trust v Casserly, 127 Mich. 183; 86 N.W. 545 (1901); Sandusky Grain Co v Borden's Condensed Milk Co, 214 Mich. 306; 183 N.W. 218 (1921); David Lupton's Sons Co v Berghoff Printing Co, 249 Mich. 455; 229 N.W. 810 (1930); and International Mill & Timber Co v Kensington Heights Home Co, 215 Mich. 178; 183 N.W. 793 (1921).
We are persuaded the Court of Appeals erred, both in its conclusion that there was a single *66 contract and in its application of the cases cited above. In every case cited the lien was held to be valid. The Court permitted lien claimants to file single liens against a project over objections that separate liens were required if there were separate contracts or separate buildings.
Although not applicable to those cases, but consonant with the rationale is a clause added to the basic act of 1891 by 1897 PA 143 which remains in its essential form within MCLA 570.1; MSA 26.281. In pertinent part that clause now reads:
"and in case of construction of a number of buildings * * * under 1 contract upon, around or in front of the same lot or contiguous lots for the same owner, part owner or lessee, of any interest in the real estate upon which said buildings are situated * * * such lien for such material or labor or leased equipment so furnished, shall attach to all of said buildings * * * together with the land upon, around or in front of which the same are being constructed, the same as hereinbefore provided in case of a single building * * *."
But permitting the filing of a single lien does not forbid the filing of separate liens. The question of whether a claimant who furnishes labor or materials for separate buildings under a single contract may have separate liens upon each of the buildings has not been decided in Michigan.
Section 27 of the mechanics' liens act declares that the act is a remedial statute intended to benefit and protect subcontractors, materialmen, and laborers and should be construed liberally in order to carry out the intent of the Legislature. MCLA 570.27; MSA 26.307. See also Smalley v Gearing, 121 Mich. 190; 79 N.W. 1114 (1899).
The intent of the Legislature when it amended *67 the statute in 1897 and the effect of the cases cited by the Court of Appeals was to extend rather than restrict the rights of mechanics and materialmen in filing liens with the object being to permit the filing of one lien rather than several.
Decisions in other jurisdictions under various circumstances and statutes have held it to be proper for a lien claimant to proceed by way of separate lien claims with respect to separate buildings that are part of a single project. See 15 ALR3d 73, § 11[d], pp 143-145, and the cases cited therein. The question of separate notices when there is a single contract is not discussed in those cases.
We are not convinced that the Michigan statute precludes the filing of separate liens upon single buildings when a claimant has furnished labor or materials pursuant to a single contract. However, since this lawsuit has been tried on the question of separate contracts and the record supports the finding of separate contracts, we do not decide the case on the basis of a single contract.
In the instant case Bob Ryan contracted to supply materials on a per building basis. It claimed separate liens against buildings #1 and #2 and served notices of intent to claim the liens within 90 days of first delivering materials to those buildings. We conclude that the notices were timely served and fulfilled their purpose of alerting the owners of Central Park North of the possibility of liens, so that they could protect themselves by following the procedures set forth in MCLA 570.4; MSA 26.284. Hartwick Lumber Co v Chonoski, 216 Mich. 424; 185 N.W. 774 (1921).
The decision of the Court of Appeals is reversed. The judgment of the trial court is affirmed.
Costs to plaintiff.
*68 SWAINSON, WILLIAMS, LEVIN, M.S. COLEMAN, and J.W. FITZGERALD, JJ., concurred with T.G. KAVANAGH, C.J.
The late Justice T.M. KAVANAGH took no part in the decision of this case.
[1] The record indicates that the invoice was actually in the amount of $438.96; however, for the purpose of this lawsuit that 50 cents shall be disregarded under the familiar rule of de minimis non curat lex.
Silverstein v. Berman , 254 Mich. 478 ( 1931 )
Sacchetti v. Recreation Co. , 304 Mich. 185 ( 1943 )
Currier Lumber Co. v. Ruoff , 298 Mich. 505 ( 1941 )
Equitable Trust Co. v. Detroit Golf & Recreation Co. , 260 Mich. 606 ( 1932 )
David Lupton's Sons Co. v. Berghoff Printing Co. , 249 Mich. 455 ( 1930 )
Bell v. CSX Transp., Inc. , 172 F. Supp. 2d 933 ( 2001 )
Burton Drywall, Inc. v. Kaufman , 69 Mich. App. 85 ( 1976 )
William Moors, Inc. v. Pine Lake Shopping Center, Inc. , 74 Mich. App. 81 ( 1977 )
Security Insurance Company of Hartford v. Houser , 191 Colo. 189 ( 1976 )
Michigan Milk Producers Ass'n v. Commercial Union Insurance , 564 F. Supp. 1545 ( 1983 )
Michigan Milk Producers Ass'n v. Commercial Union Insurance , 493 F. Supp. 66 ( 1980 )
R & T Sheet Metal, Inc v. Hospitality Motor Inns, Inc , 139 Mich. App. 249 ( 1984 )
Tempo, Inc v. Rapid Electric Sales & Service, Inc , 132 Mich. App. 93 ( 1984 )
Williams & Works, Inc. v. Springfield Corp. , 76 Mich. App. 541 ( 1977 )