DocketNumber: Docket 17978
Citation Numbers: 223 N.W.2d 361, 56 Mich. App. 54, 1974 Mich. App. LEXIS 701
Judges: Bronson, P.J., and J.H. Gillis and Van Valkenburg
Filed Date: 10/8/1974
Status: Precedential
Modified Date: 10/19/2024
Plaintiff-appellee, Ben T. Young Company, is a waterproofing subcontractor. Defendant-appellant, Lafayette East Company, is a general contractor. On August 4, 1967, Lafayette subcontracted to Young installation of membrane waterproofing on the roof of a building Lafayette was constructing in Lansing, Michigan.
Part of the agreement entered into on that date provided as follows:
"Guarantee: The subcontractor guarantees that all work to be performed hereunder will be first class in every respect. He further agrees to execute and deliver prior to the final payment a written guarantee in form approved by the Owner, guaranteeing all materials and workmanship, to be free from defects, for a period of three (3) years extending from the date of completion and acceptance of the entire project by the Owner, Architect and Contractor. He further agrees to make all necessary corrections of any found defects, all at the expense of the Subcontractor.”
Young installed the waterproofing to specifications. Its work was regularly inspected by Lafay
The following spring the roof began to leak. Lafayette requested Young to honor its guarantee and repair the leaks. An inspection of the site convinced Young that the leaks were not düe to faults in its material or workmanship and it accordingly declined to take responsibility for the damage.
Lafayette then refused to forward the final portion of the installment payments due Young on the subcontract. Young filed suit on November 28, 1968 to collect this balance ($1,553.80); Lafayette counterclaimed for $50,000 damages for breach of the work-quality guarantee. The case was removed to Wayne County Circuit Court on May 29, 1969. After a non-jury trial, judgment was entered for Young on July 31, 1973 in the full amount of $1,553.80. Lafayette’s counterclaim had been dismissed on June 11,1973. This appeal followed.
The trial court held that Young had established its right to the final installment payment. Lafayette does not dispute the fact of performance but asserts that the performance rendered was not of the quality warranted.
Since Lafayette claimed breach of the guarantee, it had the burden of demonstrating that Young did not perform in accordance with the contract.
The trial judge’s conclusion that Lafayette did not adequately show breach on the part of Young depended on his interpretation of the guarantee. Lafayette argued that Young guaranteed a leak-proof roof when he promised that "all work” would be "first class in every réspect”. The trial judge disagreed, holding that Young guaranteed only that its work would be of the highest quality.
The language used is concededly ambiguous. Ambiguities must be resolved against the party drawing the contract. Michigan Chandelier Co v Morse, 297 Mich 41, 46; 297 NW 64 (1941); Gary Boat Club, Inc v Oselka, 31 Mich App 465, 471; 188 NW2d 127 (1971). Since Lafayette drew this contract, the ambiguity must be resolved in Young’s favor.*
The trial judge concluded that "it was not shown that the leaks in the area of the construction joint were attributable to the improper installation or defective material applied by plaintiff”. That finding is amply supported by the record. Lafayette did not demonstrate that Young breached its own guarantee, as correctly construed by the trial
Affirmed. Costs to appellee.
Oakland Metal Stamping Co v Forest Industries, Inc, 352 Mich 119, 125; 89 NW2d 503 (1958). The burden remains Lafayette’s even
The fact that Young suggested changes in the plans which were eventually adopted is of no consequence since Lafayette’s architect reviewed and approved the changes before they were implemented. In so doing, Lafayette made them its own. Cf. McFarland v Gillioz, 327 Mo 690, 700; 37 SW2d 911, 916 (1931).