DocketNumber: Docket 281728
Citation Numbers: 761 N.W.2d 399, 281 Mich. App. 599
Judges: Borrello, Davis, Gleicher
Filed Date: 12/9/2008
Status: Precedential
Modified Date: 10/19/2024
Court of Appeals of Michigan.
*400 Kallas & Henk PC (by John F. Fleming), Bloomfield Hills, for Assemblers, Inc.
Steven A. Wright, P.C. (by Sandra L. Wright and Steven A. Wright), Shelby Township, for American Manufacturers Mutual Insurance Company.
Alber Crafton, PSC (by Phillip G. Alber and Omar J. Harb), Troy, for United States Fidelity & Guaranty Company.
*401 Before: BORRELLO, P.J., and DAVIS and GLEICHER, JJ.
DAVIS, J.
Plaintiff appeals as of right orders of summary disposition entered in favor of defendants American Manufacturers Mutual Insurance Company (American Manufacturers) and United States Fidelity & Guaranty Company (USF&G). We affirm in part, reverse in part, and remand for further proceedings consistent with this opinion.
This case arises out of the Howe Elementary School demolition and reconstruction project begun by the Detroit Public Schools in 2001. The Detroit Public Schools contracted with American International, Inc., to be the general contractor for the project. American International obtained a payment bond from USF&G, and it subcontracted part of the construction project to defendant Metro Steel Fabricators, Inc. (Metro Steel). Metro Steel obtained its own payment bond from American Manufacturers. Metro Steel then subcontracted part of the construction work to plaintiff.
On May 8, 2003, plaintiff "stopped working on the Howe Elementary School project" without completing it. Plaintiff contends that its work on the project was nearly complete at that time, but that it was not receiving its expected payments and it perceived that it would continue not receiving its payments. Plaintiff therefore ceased work "to avoid further losses." It is undisputed that plaintiff was not, in fact, paid all that it was owed on the Howe Elementary School project. On March 25, 2004, the Detroit Public Schools formally terminated the construction contract with American International for failure "to properly make payments to Subcontractors or for labor, materials and equipment" pursuant to that contract.[1] On May 6, 2004, Metro Steel explicitly acknowledged in a letter to plaintiff that $124,666 remained owing on the Howe Elementary School project. Plaintiff seeks the same amount in the instant action. Nevertheless, the Detroit Public Schools thereafter persuaded plaintiff to complete its work on the project, giving plaintiff "assurances of payment." On August 19, 2004, plaintiff returned to the work site and completed its work on the Howe Elementary School project.
On August 27, 2004, plaintiff sent notices to both sureties that it was making a claim on each of the payment bonds. Plaintiff then commenced the instant action against them. All parties filed motions for summary disposition. USF&G argued that the last day plaintiff worked as a subcontractor to a subcontractor on the original contract was May 8, 2003, and that it failed to provide notice of its claim within 90 days thereof, as required by the contractor's bond for public buildings or works act, MCL 129.201 et seq.[2] USF&G also argued that it could not be held liable on the bond because it was a secondary surety to American Manufacturers's bond and because plaintiff was responsible for delays in the project. American Manufacturers argued that its bond contained a contractual limitations period that required claimants to file suit within one year of giving notice under the bond or of the last day on which work was performed and that plaintiff exceeded this date by more than three months under any possible interpretation of the facts. Plaintiff argued *402 that the work it performed on August 19, 2004, was merely a completion of its work on its subcontract with a subcontractor and that American Manufacturers's bond was a statutory bond and it was required to afford the longer limitations period available under the public works bond statute. The trial court granted summary disposition in favor of the sureties; the parties later agreed to a consent judgment and final order resolving the remaining claims.[3]
A grant or denial of summary disposition is reviewed de novo on the basis of the entire record to determine if the moving party is entitled to judgment as a matter of law. Maiden v. Rozwood, 461 Mich. 109, 118, 597 N.W.2d 817 (1999). When reviewing a motion under MCR 2.116(C)(10), which tests the factual sufficiency of the complaint, this Court considers all evidence submitted by the parties in the light most favorable to the nonmoving party. Where the evidence fails to establish a genuine issue regarding any material fact, the moving party is entitled to judgment as a matter of law. Maiden, supra at 120, 597 N.W.2d 817. A motion brought under MCR 2.116(C)(8) should be granted only where the complaint is so legally deficient that recovery would be impossible even if all well-pleaded facts were true and construed in the light most favorable to the nonmoving party. Maiden, supra at 119, 597 N.W.2d 817. This Court also reviews de novo as a question of law the proper interpretation of both contracts and statutes. Detroit Fire Fighters Ass'n, IAFF Local 344 v. Detroit, 482 Mich. 18, 28, 753 N.W.2d 579 (2008).
MCL 129.201 et seq. was created by the Legislature in order to protect "principal contractors" from the void left by the "long-standing mechanics' lien law" that prohibited mechanics' liens on public buildings. Adamo Equip. Rental Co. v. Mack Dev. Co., Inc., 122 Mich.App. 233, 236, 333 N.W.2d 40 (1982). Although intended "to safeguard and protect contractors and materialmen in the public sector," it significantly distinguishes between "rights and duties of the primary contractor and the rights and duties of the secondary contractors...." Id. at 236-237, 333 N.W.2d 40. This Court has explained that "the principal contractor" means "the contractor who has the primary responsibility for performing the terms of the contract" and might or might not be the first contractor. Id. at 237, 333 N.W.2d 40. The plain language of MCL 129.201 imposes the requirement of providing a bond under the statute only on the principal contractor.
It is undisputed that Metro Steel was not the principal contractor, so Metro Steel was not required by statute to provide a bond pursuant to MCL 129.201 et seq. Plaintiff contends, however, that the bond issued by American Manufacturers is a statutory bond because it incorporates by reference Metro Steel's subcontract with American International, which in turn allegedly required Metro Steel to obtain a statutory bond because the subcontract between Metro Steel and American International incorporated by reference the prime contract between American International and the Detroit Public Schools that required American International to provide a statutory bond.[4] The prime contract appears *403 to require the general contractor to obtain a payment bond using a form explicitly specifying that the bond is statutory and in conformance with the public works bond act. However, Metro Steel is not the general contractor, the reference to "bidders" appears to be in the context of dealings directly with the project owner, and the American Manufacturers bond did not include that particular language.
Indeed, there is no language in the American Manufacturers bond or in the subcontract between American International and Metro Steel making any reference to a statutory bond. Rather, the subcontract states that any other documents referenced are "as amended or supplemented by other provisions of the Subcontract Documents," and it explicitly states that the subcontract takes precedence over the prime contract in the event any provisions are inconsistent. Given that MCL 129.201 et seq. are only intended to govern the principal contractor, and given that none of the documents executed by any party to the instant appeal imposed any requirement of a statutory bond, we conclude that no statutory bond was required of American Manufacturers.[5] We agree with the trial court that the payment bond issued by American Manufacturers was contractual, rather than statutory, so the limitations period specified therein applied.
Conversely, it is undisputed that the USF&G payment bond was a statutory bond because it was issued to American International, the principal contractor on the Howe Elementary School project. As a consequence, for plaintiff to make a claim under the bond, it must have "given written notice to the principal contractor and the governmental unit involved within 90 days from the date on which the claimant performed the last of the labor or furnished or supplied the last of the material for which the claim is made...." MCL 129.207. Additionally, a "claimant" is defined as "a person having furnished labor, material, or both, used or reasonably required for use in the performance of the contract." MCL 129.206. The parties agree that the applicable limitations period is 90 days after the last day of work on the contract. The bond act itself is to be liberally construed, but the notice requirement must be strictly construed and enforced. Grand Blanc Cement Products, Inc. v. Ins. Co. of North America, 225 Mich.App. 138, 144, 571 N.W.2d 221 (1997). Plaintiff provided "notice" on August 27, 2004. Therefore, the most significant issue is whether the work plaintiff performed on August 19, 2004, was "in the performance of the contract."
We find that issue impossible to resolve on the basis of the existing factual development in this matter. It is not seriously contended that the work plaintiff performed on that date was so de minimis that it cannot be counted, nor is it seriously contended that the work on that date was not work that had originally been called for under the contract. USF&G argues that the total amount plaintiff claims it is owed on the contract had already been agreed on by all relevant parties *404 before it performed the additional day of work. This could be construed as an acknowledgement that the original contract was terminated at that point, but it could also simply be an acknowledgement of why plaintiff was no longer performing work on the contract; in any event, the letter only purports to confirm that plaintiff was owed further payment. Although plaintiff apparently performed the additional day of work on the basis of "assurances" by the Detroit Public Schools, there is in fact no evidence in the record shedding any light on what actually happened in that transaction. USF&G points out that plaintiff documented that additional day of work on a form entitled "additional work authorization." However, USF&G's argument that the mere title of a form proves anything about the underlying transaction elevates form over substance, and in any event, the form also specifies that Metro Steel (the subcontractor) is the entity to be invoiced.
We find that the evidencewhen properly viewed in the light most favorable to the nonmoving partysimply cannot foreclose or prove either possibility. Without further factual development, neither party could be entitled to summary disposition on this basis.
We do, however, conclude that if the work plaintiff performed on August 19, 2004, was "on the contract," the fact that American International had been terminated as the general contractor is irrelevant. USF&G's bond provides that it will not be liable for obligations of the contractor (American International) that are unrelated to the construction project. However, the unpaid work for which plaintiff is attempting to bring a claim all predates American International's termination, and in any event, American International's termination as the general contractor did not terminate plaintiff's status as a subcontractor to a subcontractor. The issue remains whether the work was "on the contract" or pursuant to a separate agreement between plaintiff and the Detroit Public Schools.
USF&G also urges us to adopt § 53 of the Restatement of Suretyship and Guaranty, 3d. In particular, USF&G argues that suretyship law obligates a claimant to exhaust recovery from the surety "closest" to the claimant, which in this case would be American Manufacturers. USF&G further argues that if plaintiff cannot do so because it exceeded the applicable limitations period in American Manufacturers's bond, plaintiff can only blame itself for not having a remedy. However, it is undisputed that there is no Michigan law on this point. We conclude that applying USF&G's proposed rule here would be contrary to the stated purpose of MCL 129.201 et seq.
The public works bond act is to be liberally construed to "protect contractors and materialmen in the public sector to ensure that they do not suffer injury when other contractors default on their obligations." W T Andrew Co., Inc. v. Mid-State Surety Corp., 450 Mich. 655, 659, 545 N.W.2d 351 (1996). It was enacted by the Legislature because materialmen and contractors cannot place liens on public buildings; by its own express terms, it is intended to protect parties who "furnished labor, material, or both, used or reasonably required for use in the performance of the contract." MCL 129.206; see MCL 129.203; Kammer Asphalt Paving Co., Inc. v. East China Twp. Schools, 443 Mich. 176, 181-182, 504 N.W.2d 635 (1993). The payment bond issued by USF&G likewise defines a "claimant" to include any "individual or entity having a direct contract with the Contractor or with a subcontractor of the Contractor to furnish labor, materials or equipment for use in the performance of the Contract."
*405 Neither the bond nor the statute contains an exemption or exception for any other payment bonds, nor do any of the conditional prerequisites to recovery include exhaustion of recovery from any other sureties. Indeed, they show the opposite. The Legislature passed the public works bond act to require bonds like the one issued by USF&G for the purpose of protecting parties like plaintiff. The plain language of the statute and the bond itself show that USF&G is liable on its bond irrespective of the American Manufacturers bond, at least presuming plaintiff is found on remand to have fulfilled the other requirements for being a claimant.
The sureties finally assert that plaintiff cannot recover on either bond because plaintiff was responsible for delays in the construction project. However, the trial court did not address this matter, and facts necessary to make that determination do not appear to have been entered into the record. We decline to consider this issue in light of the existing lack of factual development.
We affirm the trial court's grant of summary disposition in favor of American Manufacturers. We reverse the trial court's grant of summary disposition in favor of USF&G, and we remand to the trial court for further proceedings. We do not retain jurisdiction.
[1] American International has apparently filed for bankruptcy and ceased to exist.
[2] This is also known as "the public works bond statute." See, e.g., W.T. Andrew Co., Inc. v. Mid-State Surety Corp., 450 Mich. 655, 657, 545 N.W.2d 351 (1996).
[3] Metro Steel is not a party to this appeal.
[4] Plaintiff also argues that the plain language of American Manufacturers's bond shows that it is a statutory bond, but the paragraph on which plaintiff relies is inapplicable: by its own terms, that paragraph only applies where the "[b]ond has been furnished to comply with a statutory or other legal requirement." Because Metro Steel was not the principal contractor, it did not obtain the bond from American Manufacturers to comply with "a statutory or other legal requirement."
[5] Plaintiff also relies on caselaw involving similarly worded payment bonds. But those cases involved principal contractors who had contracted directly with a public entity, and there was therefore no dispute that statutory bonds were required, Gloucester City Bd. of Ed. v. American Arbitration Ass'n, 333 N.J.Super. 511, 755 A.2d 1256 (2000), or were cases where a statutory bond was otherwise indisputably required. Kirkpatrick v. Phillips, 162 Mich. 251, 127 N.W. 340 (1910). These cases are therefore irrelevant to the issue at hand.
Kammer Asphalt Paving Co. v. East China Township Schools , 443 Mich. 176 ( 1993 )
WT ANDREW COMPANY v. Mid-State Surety Corp. , 450 Mich. 655 ( 1996 )
Gloucester City v. AM. ARBITRATION ASS'N. , 333 N.J. Super. 511 ( 2000 )
Adamo Equipment Rental Co. v. MacK Development Co. , 122 Mich. App. 233 ( 1982 )
Grand Blanc Cement v. INA , 225 Mich. App. 132 ( 1997 )
DETROIT FIRE FIGHTERS ASS'N IAFF LOCAL 344 v. City of ... , 753 N.W.2d 579 ( 2008 )