DocketNumber: Docket No. 8,033
Citation Numbers: 27 Mich. App. 352, 183 N.W.2d 411, 1970 Mich. App. LEXIS 1339
Judges: Brennan, Quinn, Zlem
Filed Date: 10/26/1970
Status: Precedential
Modified Date: 11/10/2024
Aleo Construction Corporation appeals from the decision of the trial court sitting without a jury that it is liable to O’Brien for Bradley’s judgment against him. The case arose out of the construction of the Carriage Green Apartments in Kalamazoo. Aleo had contracted with O’Brien for the painting work on the complex for $27,700 or $210 per unit. O’Brien subsequently subcontracted the work to Bradley at the same price. Bradley immediately began work by the spraying process which the trial court found the original contracting parties had contemplated, and he was paid by Aleo for work done during May and June of 1966. He continued painting until August 8, 1966, when an Aleo representative indicated the work must be done by
Bradley filed suit in 1967 against O’Brien for $14,809.77 in compensation for work completed under the contract and authorized extras. O’Brien in turn sued Aleo, alleging that if Bradley obtained a judgment against him, Aleo was liable to him for the amount of such judgment. After a two-day trial, the trial court found Aleo was estopped from denying liability by the fact it had allowed plaintiff to continue his work despite Alco’s alleged dissatisfaction with it. The trial court found estoppel applicable where Alco’s superintendent was present daily while work was being done, did nothing to defeat Bradley’s expectation of being paid for the work he was doing, and asked Bradley to continue the painting despite defects in the drywall construction pointed out by Bradley and O’Brien. The trial court granted judgments as requested by Bradley and O’Brien, crediting Aleo with $6,669 paid in May and June.
After reviewing the transcript, we find that the trial court’s findings of fact were not clearly erroneous. GCR 1963, 517.1; McCarron v. Upper Peninsula Hauling Association (1968), 13 Mich App 168; Weeks v. Conservation Department (1968), 9 Mich App 429. In addition, we can find no error in the trial court’s having applied the law of equitable estoppel to the facts it found. Schliess v. City of Grand Rapids (1902), 131 Mich 52; Morgan v. Plotkin (1922) 219 Mich 265; City of St. Clair Shores v. L & L Construction Company, Inc. (1961), 363 Mich 518.
Secondly, Bradley and O’Brien testified that although there was no charge included in the contract for painting common areas, it was contemplated that $10 of the $210 per unit price would he allocated for these items. Included in the damages was $860 for painting common areas, although Bradley and O’Brien had already charged the allocable $10 in 44 completed units, to-wit: $440, and a portion of the $10 in fixing the charges for work done in uncompleted areas, to-wit: $111.85. Thus to the extent of $551.85, which constitutes a double charge for the common areas, the judgment must be corrected. The correct award under the evidence presented below is $7,588.92 for Bradley against O’Brien and $7,297.45 for O’Brien against Aleo.
Judgment of the trial court is affirmed with the foregoing corrections. Costs to appellees.