Plaintiffs selected a contractor for the construction of a residence on their land in Oakland County and introduced the contractor to defendant supplier with whom they had had earlier discussions as to estimated material needs and costs. The contractor did deal with defendant in purchasing materials for construction of the house but did not fully pay defendant therefor.
Notice of intent to claim mechanic’s lien was timely served on plaintiffs
MCLA 570.6; MSA 26.286 provides:
"Every person recording such statement or account as provided in the preceding section, except those persons contracting or dealing directly with the owner, part owner or lessee of such premises, shall within 10 days after the recording thereof, serve on the owner, part owner or lessee of such premises, if he can be found within the county or in case of his absence from the county, on his agent having charge of such premises, within the county wherein the property is situated, a copy of such statement or claim; * * * .”
Plaintiff-owners sued to have the claimed lien held invalid because of the lack of the allegedly necessary personal service of the statement of lien. Defendant contended that it had been "dealing directly” with plaintiffs, as within the exception to MCLA 570.6 and that personal service of the statement of lien was thus not required. Both parties moved for summary judgment, with supporting affidavits as to the facts of their relationship.
The defendant by affidavit alleged that plaintiff husband, on introducing his contractor to defendant’s vice-president promised personal responsibility for material charges, and further promised to see that defendant received payment for materials directly from his mortgage company; that plaintiff wife contacted defendant advising of the shaky financial condition of their contractor, seeking assurance that they would not be billed for any material sold to their contractor except such as went into their home and affirming their responsibility for such materials; that plaintiff husband acknowledged his wife’s call and affirmed their
The purpose of the notice requirement of MCLA 570.6 is to allow the owner an opportunity to withhold payment from his prime contractor for the protection of the lien claimant from the consequences of inadvertent payment to the impecunious contractor Mohawk Lumber & Supply Co v Petix, 349 Mich 323, 333-334 (1957). The exception to the requirement stems from knowledge in fact of the existence of such claims derived either from contractual liability between owner and lien claimant, or from direct dealings between them sufficient to give the owner the same knowledge of the existence of the claim or notice of facts that would put a prudent man on inquiry.
The existence of facts showing direct dealing and their sufficiency to fall within the statutory exception will depend upon the circumstances of a particular case. In Beck v Delta Recreation Corp, 2 Mich App 518 (1966), summary judgment was affirmed by a finding that the contacts there alleged did not, as a matter of law, amount to "direct dealing” within the meaning of the statutory exception. We hold as a matter of law that the affidavit-proffered facts asserted by defendant in this case would constitute direct dealing, if true. These facts and contrary facts asserted in affidavit by plaintiffs presented a factual issue to be re
Reversed.
MCLA 570.1; MSA 26.281.
MCLA 570.5; MSA 26.285.
1891 PA 179, as amended.