DocketNumber: Docket No. 71027
Judges: Burns, Cynar, Tahvonen
Filed Date: 5/14/1984
Status: Precedential
Modified Date: 11/10/2024
On March 16, 1972, plaintiff, Midwest Bridge Company, entered into a contract with defendant, Michigan Department of Transportation (MDOT), to perform grading, install drainage structures, alter utilities and surface ser
The contracts between Midwest and MDOT and between Midwest and Sivier were unit price contracts. Under unit price contracts, the contractor • and subcontractor are paid for each unit of work performed, in contrast to a lump-sum contract where the contractor is paid for the total amount of work performed. The determination of how much work was performed in both contracts was made solely by MDOT. During the course of construction, MDOT would prepare biweekly estimates of work performed based upon measurements from the job site and complex calculations performed under the supervision of MDOT’s project engineer. The biweekly estimates also designated what portion of the work was performed by Sivier. On the basis of the biweekly estimates, biweekly progress payments were made by MDOT to Midwest, less a certain percentage held by MDOT as a retention fund. In reliance on the biweekly estimate, Midwest then paid Sivier out of the progress payment for its work performed.
The project was officially completed in December, 1974. On April 15, 1976, MDOT indicated to Midwest that it had overestimated the amount of work performed by Sivier, and thus was going to withhold $105,939.74 from the retention fund otherwise due Midwest. By this time, however, Sivier was dissolved as a corporation and there remained no assets available to allow Midwest to recoup the overpayments made in reliance on MDOT’s biweekly estimates. The final estimate of the contract amount was entered on March 22, 1978.
Midwest then filed suit against MDOT alleging breach of contract and seeking recovery of the $105,939.74. A bench trial was held in the Court of Claims. The trial court found in favor of Midwest and awarded it $105,939.74. MDOT now appeals and we affirm.
Midwest contended at trial that the method by which it paid Sivier was dictated by the state, and that this method necessitated reliance on the progress estimates made solely by MDOT. Midwest claimed, therefore, that MDOT breached its warranty to make accurate measurements and estimates on which it knew plaintiff must rely.
Although this issue is one of first impression in Michigan, it is closely analogous to the issue presented in Hersey Gravel Co v State Highway Dep’t, 305 Mich 333; 9 NW2d 567 (1943). In Hersey, bidding opened on a contract calling for excavation of approximately 373,000 cubic yards of earth and 17,000 cubic yards of rock. Plaintiff won the bid, and during performance completed excavation of an additional 32,000 cubic yards of earth and 11,000 cubic yards of rock. Plaintiff sought compensation for the additional excavations completed. The trial court found for plaintiff, holding that a warranty was made in connection with the excavations, and that this warranty had been breached because of the misstatement of the conditions actually existing. On appeal, defendant argued that the contract required plaintiff to satisfy itself regarding actual soil conditions, and therefore defendant did not warrant the contract specifications. The Supreme Court, however, rejected defendant’s argument, stating (305 Mich 340-341):
" 'Undoubtedly the commission’s knowledge of subsoil conditions was superior to that of the plaintiffs, and they tried to acquire this knowledge from it. It is equally true that these facts were not within the fair reasonable reach of the plaintiffs, and there was lack of time for them to obtain this information by an independent investigation before the letting. * * *
" 'The duty rested on the sewer commission to furnish to the plaintiffs in this case all the material information it had in its possession, obtained either by borings or from past experience, as to subsoil conditions in the sewer line, and if it failed to do so, and as a result thereof the plaintiffs were put to large additional expense in completing the contract, they are entitled to recover the reasonable damages sustained by them.’ Davis v Comm’rs of Sewerage, 13 F Supp 672, 681 (WD Ky, 1936).”
Hersey is in accordance with decisions from other jurisdictions. It is well settled that the bidder on a proposal for public work may, when acting in good faith, rely on advertised specifications and estimates when there is nothing in those estimates to indicate that they are made merely by way of suggestion. If reliance is made on the estimates,
Although the inaccuracies relied on by Midwest in the instant case were not in the plans and specifications, Hersey should apply, as defendant warranted the accuracy of its estimates.
Midwest had no method independent of MDOT’s estimates to calculate the amount of work accomplished by Sivier. Even had Midwest waited until the end of the job to pay Sivier, it was required by statute to pay within 60 days after completion of the job. MCL 570.1101 et seq.; MSA 26.316(101) et seq. Midwest was not notified of the overpayment until two years after completion. Accordingly Midwest would still have been required to rely on the original MDOT estimates had Midwest waited until the end of the job to pay Sivier.
The trial court found that it was necessary for plaintiff to rely on defendant’s erroneous estimates. The court held, therefore, that defendant breached its warranty to make accurate estimates and payments, and awarded damages to plaintiff in the amount withheld by defendant. As the court’s holding was not clearly erroneous, GCR 1963, 517.1, we affirm.