DocketNumber: No. 33,185.
Citation Numbers: 7 N.W.2d 7, 213 Minn. 376, 1942 Minn. LEXIS 533
Judges: Hilton
Filed Date: 12/11/1942
Status: Precedential
Modified Date: 11/10/2024
The defendant company was engaged in general construction work and had a general contract to remodel an apartment building. Plaster work being required, the plaintiff offered to lath and plaster the apartment building according to the plans and specifications and to furnish the labor and material for the sum of $275. This offer was accepted, and plaintiff entered upon the performance of the work. Plaintiff claims that much extra work, *Page 378 not covered by the plans and specifications, was done by him. He presented a bill to the defendant's manager for $686.20. The bill contains the statement: "Labor and material as actually furnished because of additional requirements and constituting drastic modification and nullification of original estimate as required by and [on] behalf of owner." Plaintiff testified that this amount was compromised, the defendant to pay only $560. Defendant made various payments totaling $250. Also, defendant paid $210 to a builder's supply company for materials that went into the premises to secure a lien waiver in order that it could collect under its general contract with the owners of the apartment. There is some testimony to the effect that, in order to get a lien waiver from the plaintiff, defendant was required to pay the plaintiff $100 of the $250 mentioned above. Upon removal from the conciliation court of Duluth to the municipal court, judgment was entered for the defendant sustaining its counterclaim of $185.
In a prior hearing on this case, Warner v. A. G. Anderson, Inc.
The various assignments of error raise the question whether the findings of the trial court were contrary to the evidence. Our rule is that the findings of the trial court will not be set aside unless clearly or manifestly against the weight of the evidence or have no reasonable support in the evidence. Sommers v. City of St. Paul,
The remaining question raised by the plaintiff is whether the answer of the defendant properly pleads a counterclaim. The action was commenced in the conciliation court of the city of Duluth. It was there that defendant interposed its counterclaim. It states, in effect, that defendant was compelled to pay the sum of $210 to satisfy certain liens against the property for material purchased by the plaintiff in connection with the work done and that by reason thereof the plaintiff is indebted to the defendant in the sum of $185. Pleading in these small claims courts need not follow the technical rules. L. 1927, c. 17, setting up the Duluth conciliation court, in § 16(b), provides that no formal pleadings shall be necessary and § 19(b) states that upon appeal to the municipal court "the claim of the plaintiff and the answer of the defendant appearing in the files shall stand as the complaint and answer respectively in such action." Under this procedure, the original statements of the various claims and answer will stand unless further particulars are requested by the other party.
Judgment affirmed. *Page 380