DocketNumber: CI-85-821, C4-85-957
Citation Numbers: 393 N.W.2d 490, 1986 Minn. LEXIS 870
Judges: Coyne, Yetka, Kelley
Filed Date: 8/29/1986
Status: Precedential
Modified Date: 10/19/2024
Respondent J.L. Manta, Inc. obtained a permanent injunction barring the State of Minnesota from awarding a bridge painting contract to Rainbow, Inc. and precluding the State from rejecting all bids and read-vertising for bids. We reverse.
Early in 1986 the Department of Transportation (DOT) advertised for bids for painting a bridge over the Mississippi River on Trunk Highway 3. The bid form indicated that the project comprised three
The bids ranged from Manta’s low bid of $301,749 to a high bid of $696,530 — with the majority of the seven bids exceeding $450,000. Manta’s bid, however, contained an alteration. The unit price and extension for the traffic control item had been changed from $4088 to $4082 by writing a “2” over the final “8”. The sum of $4082 and the extended bid prices for mobilization and painting amounted to Manta's total bid price of $301,749.
Relying on the mandatory language of Minn.Stat. § 16B.09, subd. 2 (1984):
Alterations and erasures. A bid containing an alteration or erasure of any price contained in the bid which is used in determining the lowest responsible bid must be rejected unless the alteration or erasure is corrected pursuant to this subdivision. An alteration or erasure may be crossed out and the correction printed in ink or typewritten adjacent to it and initialed in ink by the person signing the bid.
and Specifications 1206 and 1301 of the State’s Standard Specifications for Highway Construction (1978), the DOT rejected Manta’s bid because of the improper alteration. '
When the DOT awarded the contract to Rainbow, Inc., the next lowest bidder, Manta sued to enjoin the State from awarding the contract to any bidder except Manta and also sought a writ of mandamus compelling award of the contract to Manta. After Rainbow intervened, the district court granted Manta its requested injunc-tive relief but did not require the DOT to contract with Manta. The court of appeals affirmed the trial court’s determination that rejection of the Manta bid was arbitrary and capricious, but held that the State could not be enjoined from awarding the bridge painting contract to any business or person but Manta. The court of appeals concluded that the State had no authority to contract with Rainbow, Inc., or to reject all bids “for the sole purpose of resoliciting bids,” observing that rejection of all bids would be proper if the State abandoned the project or if there were some substantial reason for rejecting the Manta bid. J.L. Manta, Inc. v. Braun, 376 N.W.2d 466, 471 (Minn.App.1985).
I.
Although the lower courts regarded the rejection of Manta’s bid as arbitrary and capricious, it seems to us that there was indeed a substantial reason for its rejection: the DOT was simply following the statutory mandate. Certainly, the paramount purpose of the statutory bidding process is to protect the public interest by requiring contracts to be let to the lowest responsible bidder. Foley Bros., Inc. v. Marshall, 266 Minn. 259, 264, 123 N.W.2d 387, 391 (1963). Acknowledging that purpose of the competitive bidding requirement, the lower courts accepted Manta’s contention that it had substantially complied with the statutory requirements and that a $6 alteration in a bid of more than $300,000 is de minimus and should not be a ground for rejection of the bid of a responsible bidder.
We have recognized that the public should not be denied the benefit of the lowest bid for every minor technical defect that does not affect the substance of the bid. Thus, we have held that insubstantial departures from the commissioner’s requirements — defects which do not reflect bad faith, undermine the procedures, or prejudice the rights of those intended to be protected by the procedures — such as filing a certificate of non-collusion rather than an affidavit, Foley Bros., 266 Minn. at 264, 123 N.W.2d at 391, or submitting a bid a short time after the time set by the specifications, Nielsen v. City of St. Paul, 252 Minn. 12, 88 N.W.2d 853 (1958), do not justify rejection of the bid. We have also
With respect to the treatment of a bid containing an alteration or erasure of a bid price — an aspect of competitive bidding peculiarly susceptible to fraud and collusion — the legislature has deprived the officials who will let the contract of any discretion. Had it been within the DOT’s discretion to accept a bid containing a non-complying alteration, then, of course, its refusal to accept Manta’s bid would have been an arbitrary exercise of that discretion. A six dollar alteration in a bid of $301,749 is unquestionably de minimus. But section 16B.09, subd. 2, does not allow for the exercise of any discretion by the DOT. The statute specifically describes the only acceptable method of altering any price contained in the bid which is used in determining the lowest responsible bid. Unless the alteration or erasure is “crossed out and the correction printed in ink or typewritten adjacent to it and initialed in ink by the person signing the bid,” the bid “must be rejected.” Minn.Stat. § 16B.09, subd. 2. The statute, both clear and explicit, offers no basis for construction. Had the legislature intended either to make rejection or retention of a bid containing an altered price dependent upon the amount of the change or its relationship to the amount of the total bid price, or to accord public officials discretion to decide whether to accept or reject altered bids on a case by case basis, we have no doubt that section 16B.09, subd. 2, would have been couched in significantly different language.
Moreover, the absolute character of the legislative mandate that the bid must be rejected is responsive to the nature of the defect — a non-complying alteration has the potential for undermining or subverting the entire bidding procedure. Presumably, the legislature deemed it wise to protect the integrity of the bidding process with an absolute rule which would eliminate not only the opportunity for fraud and corruption, but also the confusion and suspicion bred by unauthorized bid changes or alterations by unidentified authors and the inevitable disputes over how much is de mini-mus. Ordinarily, such an absolute rule works reasonably well, but, as with any arbitrary bright line rale, there are instances — such as the one before us — where the rale produces a harsh result. The state’s bid proposal form explicitly warns bidders, “[Y]ou must initial changes made in the Schedule of Prices_” Two of the specifications for highway construction direct the bidder’s attention to the statutory requirement for rejection of bids containing non-complying alterations and detail the proper method of making corrections. Manta ignored or overlooked these warnings and the statute’s absolute mandate. We cannot.
II.
Having determined that rejection of the Manta bid was statutorily mandated, we must examine the court of appeals’ conclusion that the DOT’s acceptance of the Rainbow bid was equally arbitrary. After the bids were opened, DOT employees inserted unit prices for the mobilization and traffic control items, and corrected mathematical errors in the total bid amount or extension for the painting item and in Rainbow’s total bid price. Manta contends that the insertion of unit prices for mobilization and traffic control converted an incomplete nonre-sponsive bid into a responsive bid. Al
In addition, the DOT altered the total bid amount for the painting item and made a corresponding change in Rainbow’s total bid price. Rainbow’s bid for the painting item was for a quantity of 281,100 square feet at a unit price of $1.15. The extended amount, $323,150, was mathematically incorrect. The DOT corrected the bid price for the painting item by crossing out Rainbow’s figure and entering the correct product of 281,100 and $1.15, $323,265. The total bid price was then altered to reflect the correct sum of the bid price for the three items included in the bid.
These mathematical corrections are expressly contemplated by Minnesota Department of Transportation, Standard Specifications for Highway Construction (1978), which set out requirements, covenants, and specifications applicable to and controlling highway construction contracts. Minn.Stat. § 161.32 (1984). Specifications 1206 and 1301 provide that the unit bid price governs if there is a discrepancy and that bids are to be compared on the basis of the correct summation of the products of the scheduled quantities and unit bid prices.
III.
Nevertheless, although the DOT has the option of accepting the Rainbow bid as the lowest remaining responsible bid, it is not precluded from rejecting all bids and readvertising the contract in the event it should elect to do so. Electronics Unlimited, Inc. v. Village of Burnsville, 289 Minn. 118, 182 N.W.2d 679 (1971). Specification 1301 expressly reserves the right “to reject any or all proposals.” Even in the absence of a constitutional or legislative reservation, courts have generally recognized the right to reject all bids where, as here, the invitation to bid expressly reserved the right of rejection. Annot., 31 A.L.R.2d 469, 475-80.
At the time the bridge painting project was bid, Minn.Stat. § 16B.09, subd. 2 (1984) provided, “Any bid may be rejected.” Because Minn.Stat. § 16.08 (1982), the predecessor of section 16B.09, subd. 2, had permitted the rejection of “any or all bids,” the court of appeals regarded the deletion of the words “or all” as evidence of a
Moreover, we have previously recognized that an express reservation in the specifications, buttressed in this case by the statutory reservation, is sufficient authorization for the State’s rejection of all bids even after the commencement of litigation and issuance of an injunction against the initial award of the contract. Electronics Unlimited, Inc. v. Village of Burnsville, 289 Minn. 118, 182 N.W.2d 679, 684 (1971). Of course, the right to reject all bids is not unlimited. By its own rules the State recognizes the necessity for cause. Minn. Rules § 1230.0700, subp. 3. While there has not yet been a rejection of all bids for the bridge painting contract, the DOT has the right to reject all bids if the state’s present financial status requires postponing or redesigning the project or there is other sufficient cause for rejection of all bids.
Reversed.
. "When the words of a law in their application to an existing situation are clear and free from all ambiguity, the letter of the law shall not be disregarded under the pretext of pursuing the spirit.” Minn.Stat. § 645.16 (1984).
. While none of the parties to this litigation question the validity of the specifications, we note that the commissioner of transportation has authority over all aspects of the trunk highway system in Minnesota, including repair and improvements and the contracting therefor by bid, see Minn.Stat. §§ 161.20 and .32 (1984), and that such authority is expressly taken out of the general authority of the commissioner of administration over state contracts. Minn.Stat. § 16B.13 (1984). We also note that section 16B.09, which imposes the duty to award a contract to the lowest responsible bidder states:
All state contracts and purchases made by or under the supervision of the commissioner or an agency for which competitive bids are required must be awarded to the lowest responsible bidder, taking into consideration conformity with the specifications, terms of delivery, and other conditions imposed in the call for bids.
(Emphasis added).