Judges: Stevens
Filed Date: 3/15/1917
Status: Precedential
Modified Date: 11/10/2024
delivered the opinion of the court.
(After stating the facts as above).' Much is said in the briefs of counsel upon the contention made by appellee that a trial by jury in a court of equity is discretionary; that the chancellor has a right to direct a verdict, to adopt or reject the verdict of the jury and enter such decree as comports with his own conscience and his own conclusions upon the facts. It is the contention of appellee that any errors made in instructions cannot be relied upon by appellants, for the reason that the chancellor has adopted the verdict of the jury and thereby made it his own verdict on the facts; that, after all, the verdict of the jury amounts simply to the finding by the chancellor that complainant was entitled to recover the sum of nineteen thousand seven hundred and twenty-six dollars and seventy-two cents.
Under our view of this record, it is immaterial whether appellants may predicate error on the granting or refusing of instructions. The proof indisputably shows that Burkett breached his contract. The statements in his written resignation are against him on this point. In his written resignation submitted to the board he stated, and on demurrer to the bill in this case he successfully contended, that his contract with the county was illegal and void. It required an opinion of this court on the first appeal to determine this question. Furthermore, Mr. Burkett practically admits in his resignation that the price at which he agreed to work and maintain the roads would result in his financial ruin. In other words, -he frankly admitted that he' had made a poor contract and could not live up to it. He entered into a thirty-five thousand dollar bond, and under the proof this bond is liable for the actual damages sustained by the county the result of. an admitted breach of the contract. There was no error, then, on part of the chancellor in granting the peremptory instruction No. 1, and we see no substantial error
Appellants complain of the refusal of certain instructions which in effect told the jury that if they believed that Burkett worked and maintained the roads in accordance with the plans and specifications, and that notwithstanding this fact the members of the board acted arbitrarily and wrongfully in refusing to report the roads worked up to plans and specifications, and for that reason failed and refused, to pay Burkett for the work already done, that then Burkett had a right to discontinue his work, and in such event the jury should find for the defendant. The contract itself expressly stipulates that the members of the board are to be the sole judges as to whether or not the roads at any time are in fact worked according to the plans adopted. The board by the terms of the contract are invested with a discretion in determining whether the roads are maintained according to plans and specifications. They are public officers, and the contract expressly invests them with discretion and judgment in the premises. There is no evidence that any member of the board acted fraudulently. There was no error, therefore, in refusing instructions that the jury might find for the defendant.
The contract for the breach of which damages are here sought is materially different from a building or purely construction contract. We have said in the opinion heretofore rendered:
“This is a contract, not only for constructive work, but for the continuous repair and maintenance of roads, from day to day and from month to month, during the period provided for.”
It was a contract that required Mr. Burkett at all times to oversee the public roads and to expend from , day to day and week to week needed labor and material. In the very nature of things the public roads are for the use of the traveling public day and night,
Counsel for appellants with much persuasion contend that any measure of damages requires that we should take into account what Burkett would have received in the year 1912, had he completed his contract for that year. The new contractors, however, were not concerned with the year 1912, and necessarily confined their bids to the balance of the time, subsequent to the year 1912. It may be true that the new contractors bid more for the year 1913 than they would have bid if Burkett had maintained the roads in 1912 strictly according to his contract. But this is speculative, and a matter about which it is impossible for the court to have actual knowledge. If this were a building contract, manifestly the amount Burkett would have received in 1912 should be taken into account. But in the reletting of a building contract the owner ultimately gets what he originally contracted for — a completed building, one structure. In the instant case it was impossible for
In their contention that the contract was one and indivisible, counsel for appellants rely upon the case of United States Fidelity & Guaranty Co. v. Tate County, 74 So. 769 (No. 18,868), decided by Division A of this court at a former day of this term. The issue in the last-named case, however, was a different issue from the one here presented. In the Tate County case there was, as here, only one contract, and one breach of that contract. The sole point presented to the court was whether there was one, or more than one, cause of
We do not think Mr. Burkett has a right to complain at the action of the board in working the roads by convicts for a short period of time. If the roads in district No. 1 had been contracted to new contractors at an earlier date, it would have simply added to the damages for which Burkett is liable. It appears from all the evidence that Burkett must have contracted at a low figure, and that upon any reletting of the contracts for any beat there would have been an advance in the bid. It is evident that Burkett is
Affirmed.