Judges: Broiun, Ragland, Small
Filed Date: 4/8/1922
Status: Precedential
Modified Date: 10/19/2024
This is an appeal from a judgment of the Circuit Court of Jackson County, setting aside and annulling an order of the Public Service Commission requiring the Union Pacific Railroad Company to operate the whole of a certain switch track in Kansas City, for the use of all the owners of lots over which it passes without discrimination between them.
The switch track in question begins at the point of its connection with a side track of the Union Pacific Railroad Company on or near the west line of lot 25 in block 45 of Turner's Addition to Kansas City, extends thence northeasterly across the alley in said block, and thence eastwardily paralleling the alley and crossing Hickory Street and the south ends of lots 1, 2, 3, 4, 5, 6, 7 and 8 *Page 630 in block 44 of said addition, terminating at the east side of said lot 8.
In the year 1878 and since that time the buildings upon the lots in Turner's Addition, including those on the lots last referred to, were, and have been, used and occupied as warehouses, or in connection with wholesale mercantile businesses. During all that time J.F. Richards has been the owner of said lots 1, 2, 3 and 4. In response to his petition asking the right of way for a railroad track the Common Council of Kansas City, on December 13, 1878, duly enacted the following ordinance:
"Section 1. That J.F. Richards Company, their successors and assigns, be and they are hereby authorized and empowered to lay down, operate and maintain or cause to be laid down, operated and maintained a switch railroad track from a point, and connecting with, the sidetrack of the Kansas Pacific Railway Company, south of the alley in Block Forty-five in Turner and Company's Addition to the City of Kansas, Missouri, thence over and across said alley in rear of lots 22 and 23 in said Block Forty-five; thence over and across Hickory Street, the south rail being three feet north of the north line of said alley to the south ends of Lots 1, 2, 3, 4, Block 44, in said Turner Company's Addition, for the purpose of receiving and discharging from and loading and shipping on railroad cars, goods, wares and other merchandise.
"Section 2. That the authority granted in Section one of this ordinance is, however, on condition that the said J.E. Richards Company, their successors and assigns, shall construct or cause to be constructed and kept in repair the said switch railroad track where the same crosses said alley or Hickory Street on a level with the established grade of said alley and Hickory Street, and construct and keep the space between the rails and the space of two feet on the outside of the rails planked with white or burr oak planks two and one-half inches thick, and such planks should be thoroughly spiked to the cross ties and so placed as to make a connected and *Page 631 safe crossing from two feet outside of the rails on one side of said railroad track to two feet on the other side of said track, and shall extend clear across said alley and street and including the sidewalks of said street.
"Section 3. That no cars shall remain on said switch railroad track where the same crosses said street and alley any longer than ten minutes at any time, and the use of said street and alley by the public where said switch railroad track crosses the same shall be impeded or interfered with as little as possible by the operation of said switch railroad track."
Immediately upon the passage and approval of the ordinance, the predecessor of the Union Pacific Railroad Company, pursuant to some arrangement with J.F. Richards Company, constructed the switch track in question from the point of its connection with the company's side track to the east line of lot 4. Whether Richards bore all the expense of the construction, or whether he paid only for extending the track across his lots, is left in doubt by the evidence. But in any event he now claims only that part of the track that is on his premises, while the railroad company claims all that is west thereof. Soon after the original construction of the track it was extended by the railroad company across lots 5, 6, 7 and 8, presumably at the expense of the owners of those lots, who had previously agreed with Richards to pay him a rental for the use of the part of the track that was on his lots.
Ever since its construction the whole switch track has been operated and maintained by the railroad company in connection with its switch yards and as one of its industrial tracks. It has, so far as it is concerned, served the owners or occupants of lots 1, 2, 3, 4, 5, 6, 7 and 8 alike, in setting cars on their respective premises for loading and unloading. In rendering this service, the company, with reference to the charges made therefor under its schedule of tariffs, has at all times treated the switch track in question as a part of its terminal system at Kansas City. *Page 632
From the time of the extension of the track across the ends of lots 5, 6, 7 and 8 down to about 1904, the owners of those lots paid Richards a stipulated sum per month, or per car, according to their several agreements with him, for the privilege of having cars moved over that part of the track that was on his premises. On or about the date last named the Ferguson Implement Company, one of such owners, refused to make further payments, and Richards instituted suit against it for rents alleged to be due him. A judgment in Richards' favor was affirmed by the Kansas City Court of Appeals. [Richards v. Implement Co.,
On April 14, 1919, Sarah G. Neff, the representatives of the J.C. Gates Estate and George E. Bowling, the then owners respectively of lots 5, 6, 7 and 8, petitioned the Public Service Commission for an order requiring the railroad company to continue the switching service as theretofore rendered by it. The railroad company and Richards were made parties to the proceeding and a hearing was had before the Commission at Kansas City, November 4, 1919. After hearing the evidence offered by the respective parties, the Commission ordered:
"That the Union Pacific Railroad Company is hereby directed and required to operate the whole of the switch railroad track described in the application, and to switch and handle cars thereover for the use of all the owners or occupants of the lots over which said switch track passes, without discrimination between *Page 633 them or any of them for like service, and at its regular tariff rates."
Richards sued out a writ of certiorari, and on a review of the proceedings had before the Commission thereunder, the Circuit Court of Jackson County, on March 5, 1921, gave judgment setting aside and annulling the order heretofore set out. From that judgment the Commission prosecutes this appeal.
I. This controversy is between the State as represented by the Public Service Commission and the respondent Richards. The former asserts that the whole of the switch track in question is a railroad, or the integral part of a railroad,Switch Track: operated for public use, and as such is withinPublic Highway: its supervision. The latter contends that theDedication. part of the track that is on his lots is his private property and, consequently, not subject to the regulatory powers of the State. The Union Pacific Railroad Company stands indifferent; it is ready and willing to comply with the order of the Commission, if it may do so lawfully, that is, without violating the rights of Richards. The controversy, therefore, turns upon the question, whether the portion of Richards' lots occupied by the switch track has been appropriated by any constitutional method to public use as a railroad right of way. The Public Service Commission could not by its order, of course, subject Richards' land to a public use; he himself has never formally dedicated or conveyed it to any such use; nor has it been taken therefor under the power of eminent domain. If, then the railroad company as a common carrier has a right of way over his property, it is because of an implied dedication on his part. Was there such a dedication? That in the final analysis is the only question involved in the case.
It is said: the intention of the owner to set apart his lands for the use of the public is the foundation and life of every dedication, and only when this intention is unequivocably manifested can a dedication be found to exist. The acts or declarations of the owner relied on to *Page 634
establish it must be convincing and unequivocal, indicating, expressly or by plain implication, a purpose to create a right in the public to use the land adversely to himself. [Morrison v. Marquardt,
Richards in his petition to the Common Council of Kansas City represented that it was his purpose to lay down, operate and maintain, or cause to be laid down, operated and maintained, a switch railroad track from the railroad siding of the Kansas Pacific Railway Company to the east side of his lot 4, "for the purpose of receiving and discharging from and loading and shipping on railroad cars, goods, wares and other merchandise," and asked for a grant of the right of way for such track across two of the city's public thoroughfares. By clear implication he further represented that the switch-track so to be built, operated and maintained, was for the use of the public, because both he and the Common Council knew that the latter had no power to grant the right to lay the track across the highways of the city, unless it was to be used for the benefit of the public. [State ex *Page 635
inf. v. Light Dev. Co.,
It follows that the judgment of the circuit court, annulling the order of the Public Service Commission, should be reversed. It is so ordered. Small, C., concurs; Brown, C., absent.