DocketNumber: WD 80749
Citation Numbers: 562 S.W.3d 323
Judges: Mitchell
Filed Date: 9/4/2018
Status: Precedential
Modified Date: 10/19/2024
BNSF Railway Company (BNSF) appeals the denial of its motion for judgment notwithstanding the verdict following a jury trial and judgment awarding Thomas and Dana Tubbs (the Tubbses)
Background
The Tubbses own and operate a farm in a floodplain near the Missouri River in Holt County, Missouri. The farm is located just southeast of Big Lake and about three-and-a-half miles east of the Missouri River. BNSF, an interstate freight railroad, owns and operates a track that runs east to west across the floodplain and bisects the Tubbses' farm. The track sits atop an earthen embankment, which was originally built in 1887.
The embankment blocked the free flow of occasional floodwaters from the Missouri River. In response to recurrent flooding over the years, BNSF incrementally raised the height of the track and added more ballast (crushed rock) between the embankment and the track to prevent water from spilling over the track and interrupting rail service. But, as the height of the track increased, BNSF did not provide additional drainage capacity (e.g. , bridges or culverts) to address the increased volume of dammed water. Record-setting floodwaters from the Missouri River breached the embankment in July 2011 and damaged the Tubbses' farm.
In 2012, the Tubbses filed a lawsuit in Holt County Circuit Court against BNSF and its contractor, Massman Construction Company, seeking actual and punitive damages for state-law torts, including trespass, nuisance, negligence, inverse condemnation, and statutory trespass in connection with the embankment breach.
In 2014, the STB concluded that the Tubbses' state-law claims were related to the design, construction, and maintenance of BNSF's rail line and, therefore, were preempted by the Interstate Commerce Commission Termination Act,
Following the STB and Eighth Circuit decisions, the Tubbses filed a Second Amended Petition relying on the same factual assertions but consolidating their allegations into a single claim of negligence based on two FRSA regulations-the drainage regulation in
Your verdict must be for plaintiffs, if you believe:
First, defendants failed to maintain and keep free of obstruction each drainage or other water carrying facility under or immediately adjacent to the roadbed to accommodate expected water flow for the area concerned, and
Second, defendant was thereby negligent, and
Third, as a direct result of such negligence plaintiffs sustained damage.
Over BNSF's objection, the court also instructed the jury to decide whether punitive damages should be awarded against BNSF.
The following evidence favorable to the jury's verdict was adduced at trial. Historically, the valley where the Tubbses' farm is located had experienced several large floods, including floods in 1952, 1967, 1973, 1984, 1993, 2007, 2008, and 2010. In response to, or anticipation of, these events, BNSF occasionally raised the height of its track to prevent water from spilling over it and interrupting rail service, but BNSF never added any new openings in the embankment to allow for cross-drainage. Each time BNSF raised the track to protect it from expected water flow, the increase in height, together with the lack of additional drainage, increased the damming capability of the embankment because, as the track grew in height, the more water it would block, thereby raising the pressure on the embankment.
Upstream from the Tubbses' farm, the U.S. Army Corps of Engineers (the Corps) operates a series of five large reservoirs. In 2007, the Corps publicly announced that it would be releasing a larger volume of water from its reservoirs in the future, which would increase the flow of the Missouri River, creating a greater likelihood of downstream flooding.
In the spring of 2011, BNSF knew there "was a possibility that there would be flooding" in the Missouri River Basin that year. The previous winter had been the snowiest in recent years in the northern region, and the eventual snowmelt significantly raised water levels in the Corps' reservoirs. Then, both April and May of 2011 had record-setting rainfall in the upper Missouri River Basin. The rain in May nearly filled the Corps' reservoirs to capacity. By the end of May, the Corps announced that it planned to release 150,000 cubic feet of water per second from its Gavins Point reservoir in South Dakota.
In May and June of 2011, BNSF hired engineering consultants to advise it regarding the anticipated flooding that summer. At the time, BNSF's embankment had one drainage opening in its five-mile span, which was a bridge 134 feet in length. One consultant advised BNSF that four additional drainage openings in the embankment and a substantial increase in the existing opening were needed to address the anticipated water flow. Specifically, the consultant indicated that the height and length of the track necessitated ten times the amount of existing drainage through the embankment to accommodate expected water flow.
Around the same time, BNSF raised its mainline track and fortified the entire track structure by placing rock, riprap, and other material trackside. BNSF focused its efforts on raising its track east of Big Lake-a stretch of about a mile-where the track sat at a slightly lower elevation.
On June 19 or 20, 2011, a levee about eight miles north of Big Lake collapsed. The breach was several hundred feet wide and allowed a tremendous volume of water to move south, requiring the evacuation of local community members, including the Tubbses. Floodwaters quickly reached the north side of BNSF's embankment, and BNSF stopped operating freight trains on that segment of the line on June 20 because the track was submerged.
*331In an effort to restart service, BNSF had internal discussions about the possibility of intentionally cutting holes in the embankment where the track ran along another farm to allow water to pass to the south side of the embankment equalizing the water pressure so the company could start rebuilding the embankment under the roadbed. At trial, the Tubbses introduced an internal BNSF email indicating that the railroad had intentionally breached the embankment to relieve pressure created by the floodwaters. But witnesses testified that BNSF never actually intentionally breached the embankment, and the Tubbses did not submit the claim of intentional breach to the jury.
The difference in surface water elevations on the north and south sides of the embankment produced a water pressure differential that was too great for the embankment to withstand, and, on July 21, 2011, the embankment failed at the site of the Tubbses' farm. The breach in the embankment adjacent to the Tubbses' farm eventually grew to a width of 900 feet. As the embankment gave way, the water rushed from north to south with such velocity that it scoured holes on the Tubbses' farm down to bedrock. The scour holes covered almost forty acres and were sixty feet deep in places. When the floodwaters finally receded, they left large sand deposits on approximately 385 acres of the farm; in some places, the sand was eight feet deep. A farm appraiser estimated that the difference in the value of the Tubbses' farm before and after the embankment breach was $2,598,000.
During the instruction conference, BNSF's counsel proposed the following withdrawal instructions relevant to this appeal:
Instruction No. C-The evidence of the height of Defendant's track or increases in height of Defendant's track is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
Instruction No. E-The design of Defendant's track structure is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
Instruction No. A-Any evidence concerning intentional breach of the roadbed is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
The trial court rejected these withdrawal instructions, but instructed the Tubbses' counsel "to not argue intentional breach" in his closing statement.
When the Tubbses' counsel raised arguments about the height of the track during his closing argument, BNSF renewed its objection on preemption grounds. This time, the trial court sustained BNSF's objection and told the Tubbses' counsel in a sidebar discussion: "And to correct this ..., I'm going to instruct you to explain [to the jury] that the pertinent issue is the drainage of the water." Counsel then turned to the jury and said: "So I want to make sure that the complaint is not that they raised the track by [two] foot; that's not the issue. It's raising the track with no drainage; [they] didn't add one more foot of opening."
The jury returned a verdict in favor of the Tubbses, awarding them $2,598,000 in compensatory damages and $1,231,000 in punitive damages, and the trial court entered its judgment accordingly. BNSF filed a timely Motion for Judgment Notwithstanding the Verdict and Alternatively for a New Trial or to Amend the Judgment, in which BNSF raised the four issues, among others, on appeal here. The trial court denied BNSF's motion in its entirety. This appeal follows.
*332Analysis
BNSF raises four points on appeal. In Points I and II, BNSF argues that the trial court erred in denying BNSF's motion for judgment notwithstanding the verdict because the Tubbses failed to make a submissible case as to (1) the applicable standard of care (Point I) and (2) punitive damages (Point II). In Points III and IV, BNSF argues that the trial court erred in refusing BNSF's withdrawal instructions pertaining to evidence of (1) the height and design of the track (Point III) and (2) an intentional breach of BNSF's embankment (Point IV). We discuss each point in turn.
1. The Tubbses presented a submissible case on the standard of care.
A. Standard of Review
"When reviewing a circuit court's overruling of a motion for judgment notwithstanding the verdict, [the reviewing court] 'must determine whether the plaintiff presented a submissible case by offering evidence to support every element necessary for liability.' " Newsome v. Kansas City, Mo. Sch. Dist. ,
B. Standard of Care
To present a submissible case of negligence, "a plaintiff is required to prove: (1) the existence of a duty on the part of the defendant; (2) the failure of defendant to perform that duty; and (3) an injury to plaintiff directly and proximately resulting from the defendant's failure to perform the duty." Poloski v. Wal-Mart Stores, Inc. ,
Before examining BNSF's assertion on this point, however, we must first address the Tubbses' claim that the STB and the Eighth Circuit decisions are the law of the case on the nature of BNSF's duty of care. The Tubbses sought a stay of their state court action so that the STB could determine whether the Tubbses' state-law claims were preempted under the ICCTA. Although the Tubbses' petition for damages pending at that time in state court did not raise claims based on an alleged violation of
Here, the FRSA regulations that Petitioners cite [49 C.F.R. §§ 213.33 and *333213.103(c) ] are applicable to the entire national rail system and do not directly conflict with the uniform federal regulation of railroads under the Interstate Commerce Act. Accordingly, § 10501(b) does not preempt the FRSA regulations on drainage under railroad tracks. Petitioners' claims based on alleged violations by BNSF of these regulations are therefore also not preempted by § 10501(b).
Thomas Tubbs ,
Moreover, the Tubbses cannot prevail under their own test [for preemption of their state-law claims] because they have not established that they have no federal remedies remaining. Indeed, they embrace the surviving tort claims that are "based on alleged violations of BNSF of [the FRSA] regulations."
....
Additionally, the Tubbses have not explained why their remaining federal remedies-including their claim that BNSF is liable under the FRSA-are insufficient to protect their constitutional rights.
Tubbs ,
In their brief, the Tubbses argue that the STB and Eighth Circuit made these statements "in full recognition of the fact that the Tubbses' claim was premised on BNSF's failure to have sufficient drainage openings under its track." The Tubbses interpret these statements by the STB and Eighth Circuit as validating their interpretation of § 213.33, i.e. , that the rule imposed a duty on BNSF to add additional drainage if the existing drainage was insufficient to accommodate the expected water flow. The Tubbses contend that the STB and Eighth Circuit resolved the issue of whether BNSF had a duty to add drainage, that their resolution of that issue is the law of the case, and that the only issues left for the jury under the facts of this case were whether the railroad breached its duty, whether the breach caused damage to the Tubbses, and what the amount of any damage was.
Under the law-of-the-case doctrine, "a previous holding in a case constitutes the law of the case and precludes relitigation of the issue on remand and subsequent appeal." Walton v. City of Berkeley ,
We disagree with the Tubbses that the law-of-the-case doctrine precludes us from reviewing the trial court's interpretation and application of § 213.33 in this case. The Tubbses read the portions of the STB and Eighth Circuit decisions addressing their FRSA claim too broadly. Neither tribunal interpreted the drainage regulation *334or applied it to the facts of this case.
The Tubbses argue that, even if the proper interpretation of § 213.33 was not resolved by the STB, the railroad could have raised the issue and thus the law-of-the-case doctrine still applies. We disagree. The FRA, not the STB, is the federal agency charged with promulgating, interpreting, and enforcing the FRSA regulations, which include the drainage regulation. Moreover, even if the STB could have interpreted § 213.33, it was the Tubbses who sought a stay of the state case in order to seek guidance from the STB, yet they never raised the issue of the proper interpretation of § 213.33 with the STB.
Therefore, we reject the Tubbses' claim that the STB and Eighth Circuit decisions are the law of the case on the nature and scope of the duty § 213.33 imposed on BNSF.
Having determined that the STB and Eighth Circuit decisions did not address the nature of the duty owed under § 213.33, we now turn to that issue. And, consistent with our applicable standard of review, we analyze the issue anew, applying the same principles applicable at the trial court level.
When addressing a standard of care issue, it is the court's responsibility to define the standard of care and the jury's responsibility to determine whether the defendant fell short in meeting that duty. See Thompson v. Brown & Williamson Tobacco Corp. ,
Here, the parties agree that § 213.33 provides the relevant standard of care.
Thus, we begin by examining the language of § 213.33, which, in pertinent part, provides that "[e]ach drainage or other water carrying facility under or immediately adjacent to the roadbed
Under the plain language of § 213.33, the phrase "maintained and kept free of obstruction" pertains to only "drainage or other water carrying facilit[ies]." In other words, it is "[e]ach drainage or other water carrying facility," and not other parts of the track like the roadbed or the embankment, that must be "maintained and kept free of obstruction." But, as the Tubbses assert, use of the conjunctive "and" indicates that "maintained" and "kept free of obstruction" are two different concepts and, thus, should not be conflated. See City of Olivette v. St. Louis Cty. ,
The term "maintained" is not defined in the FRSA or its implementing regulations. In the absence of a statutory or regulatory definition, we look to the dictionary to determine the plain and ordinary meaning of a term. Mantia v. Mo. Dep't of Transp. ,
But we cannot read that phrase in isolation. We also must give meaning to the concluding phrase of § 213.33 -"to accommodate expected water flow for the area concerned." See Buttress v. Taylor ,
BNSF offers two arguments to support its narrow reading of § 213.33. First, BNSF argues that the "area concerned" is the track and the area adjacent thereto and does not include the Tubbses' property.
"It is a basic rule of [regulatory] construction that words should be given their plain and ordinary meaning whenever possible and [courts] will look elsewhere for interpretation only when the meaning is ambiguous or would lead to an illogical result defeating the purpose of the [regulation]." State ex rel. Moore v. Brewster ,
Here, it is difficult to reconcile the meaning of two critical phrases in § 213.33, and therefore, we look to the purpose of § 213.33 to interpret its meaning. This regulation is promulgated pursuant to the Federal Railroad Safety Act, the purpose of which "is to promote safety in every area of railroad operations and reduce railroad-related accidents and incidents."
In MD Mall Associates, LLC v. CSX Transportation, Inc. ,
Although MD Mall involved storm water runoff and not widespread flooding conditions, § 213.33 must also be interpreted to prevent the threat to track integrity posed by water pouring over the track or washing away the roadbed's support structure during flooding. In flood conditions, the interpretation of § 213.33 suggested by BNSF-that BNSF is required to maintain existing drainage facilities and keep them free of obstruction, but is not required to provide an adequate amount of drainage-conflicts with the purpose of the drainage regulation. Floodwaters accumulating on one side of a track embankment with inadequate cross-drainage will rise more rapidly and, thus, be more likely to overtop the track, creating a hazard the regulation is intended to prevent. Moreover, uneven water levels between the upstream and downstream sides of such an embankment expose the upstream side to significantly more pressure, thus compromising the embankment's integrity, which is what happened here. Therefore, in the context of a flood, the narrow reading of § 213.33 advanced by BNSF is inconsistent with the regulation's purpose.
*339Therefore, to give both phrases-"each drainage ... facility ... shall be maintained or kept free of obstruction" and "to accommodate the expected water flow for the area concerned"-meaning consistent with the purpose of § 213.33, we must read the regulation to require not only that existing drainage facilities be kept structurally sound and free of obstruction but also that an adequate amount of drainage be provided.
BNSF also argues that even if § 213.33 imposes upon it a duty to expand or add drainage facilities, that duty applies to accommodate only expected water flow, which does not include flooding of historic proportions such as that experienced near Big Lake in 2011.
As noted above, "[i]t is a basic rule of [regulatory] construction that words should be given their plain and ordinary meaning whenever possible and [courts] will look elsewhere for interpretation only when the meaning is ambiguous or would lead to an illogical result defeating the purpose of the [regulation]." Moore ,
BNSF argues that "expected water flow" means that which is anticipated based on long-term experience with water flow in the area concerned. While BNSF acknowledges that its embankment and track are located in an area prone to flooding, and thus flooding was expected in the area concerned, it argues that the 2011 flood was different in magnitude or duration from previous floods in the Big Lake area. BNSF contends that § 213.33 did not impose a duty to provide drainage to accommodate the flood of 2011, which was outside of historic norms and, therefore, could not have been expected.
There was evidence of repeated flooding in the Big Lake area starting in the early 1950s. Although there was evidence that a flood in 1952 had a higher peak discharge and higher peak flow than the 2011 flood, there was also evidence that the 2011 flood involved more water and was longer in duration than previous *340floods. But whether the 2011 flood was so unique vis-à-vis other floods as to make its water flow unexpected was a question for the jury. And, even if the jury concluded that the 2011 flood was greater in magnitude than previous floods, there was still a question of fact as to whether such a flood was probable in light of other evidence, including that, in 2007, the Corps publicly announced that, in the future, it would be releasing a larger volume of water from its reservoirs upstream from Big Lake, which would increase the flow of the Missouri River, creating a greater likelihood of downstream flooding. Thus, there was sufficient evidence to submit to the jury the question of whether BNSF violated its duty to accommodate expected water flow.
The first element of a submissible case of negligence is the existence of a duty on the part of the defendant. Poloski ,
2. The Tubbses presented a submissible case on punitive damages.
A. Standard of Review
"Whether sufficient evidence exists to support an award of punitive damages is a question of law, which [courts] review de novo. " Blanks v. Fluor Corp. ,
B. Punitive Damages Standard
"Ordinarily punitive damages are not recoverable in actions for negligence, because negligence, a mere omission of the duty to exercise care, is the antithesis of willful or intentional conduct."
there may be conscious negligence tantamount to intentional wrongdoing ... where the person ... act[ing] or failing to act must be conscious of his conduct, and, though having no specific intent to injure, must be conscious, from his knowledge of surrounding circumstances *341and existing conditions, that his conduct will naturally or probably result in injury.
Blanks ,
To begin, the standard for determining whether the plaintiffs made a submissible case for punitive damages applies somewhat differently in the context of the present case where the standard of care is provided by a regulation, the purpose of which is not to prevent the type of injury the plaintiffs claim to have suffered. As we discussed in connection with Point I above, the purpose of § 213.33 is to prevent water from pooling on or under the tracks, overtopping the tracks, or otherwise compromising track integrity, because that may endanger safe railroad operations or cause railroad-related accidents or incidents. But, the Clarification Amendment imposes liability when a railroad's violation of § 213.33 results in property damage even though the regulation itself is not intended to protect neighboring property owners. Typically, punitive damage claims based on an alleged violation of a duty of care established by statute or regulation involve a duty designed to protect the injured party. In such cases, whether punitive damages can be awarded in a negligence action depends on whether the "defendant knew or had reason to know a high degree of probability existed that the action would result in injury." Oyler ,
Viewed in the light most favorable to the Tubbses, the evidence in this case was sufficient to permit the jury to conclude that BNSF acted with "conscious negligence tantamount to intentional wrongdoing" where BNSF knew that its track was located in an area that frequently flooded, that the embankment under its track acted as a dam, that the existing drainage facility in the embankment was inadequate to allow water to pass from one side of the embankment to the other, and that the differential in water levels caused by the damming effect of the embankment caused pressure on the embankment. Moreover, although the embankment had survived prior floods, by raising the embankment, BNSF increased the pressure that flooding would cause on the embankment, and BNSF had been put on notice as early as 2007 that, in the future, the Corps would be releasing a larger volume of water from its reservoirs upstream from Big Lake, which would increase the flow of the Missouri River. Thus, there was evidence that BNSF knew that the lack of drainage facilities risked overtopping or compromised structural integrity. Yet BNSF failed to add drainage facilities to accommodate the expected water flow and, as a result, the embankment collapsed.
According to the trial testimony, the area where BNSF's track was located was prone to flooding and BNSF had been put on notice that water flow in the area was likely to increase in the future. BNSF knew its embankment acted like a dam, obstructing the free flow of floodwaters across the valley. Several times over the years, BNSF raised the height of its track to prevent water from spilling over the track and interrupting rail service. But, as the height of the track increased, BNSF did not add drainage to address the increased volume of dammed water. The embankment's damming effect created a situation where the pressure differentials between the upstream (northern) side and *342the downstream (southern) side could threaten the stability of the embankment. There was testimony that, when the water pressure builds up against the embankment, it causes sediment to be washed away to the point that the embankment collapses, which is exactly what happened at the Tubbses' farm.
In May, BNSF began hiring engineering consultants to advise the railroad about the anticipated flooding that summer. One consultant advised BNSF that drainage through the embankment was so inadequate that four additional drainage openings and a substantial increase in the existing opening were needed to address the anticipated floodwaters. Yet, BNSF added no drainage. Despite having knowledge of the effect of increasing the track height without adding drainage and the likelihood of significant flooding, BNSF focused its actions on raising the track again and fortifying the embankment by adding riprap. In the initial stages of the flood, before the embankment breach at the Tubbses' farm, BNSF contractors were "out there mobilizing to start building bridges." BNSF "knew [they] were going to do something. [They] just didn't know exactly what."
The evidence was sufficient for a reasonable jury to conclude that BNSF was indifferent to the risks associated with the lack of adequate drainage through the embankment.
BNSF argues that there was insufficient evidence to support the jury's award of punitive damages because the Tubbses had to show that the railroad's conduct was "tantamount to intentional wrongdoing," and they failed to do so. Lopez v. Three Rivers Elec. Co-op Inc. ,
prior similar occurrences known to the defendant have been infrequent; the injurious event was unlikely to have occurred absent negligence on the part of someone other than the defendant; and the defendant did not knowingly violate a statute, regulation, or clear industry standard designed to prevent the type of injury that occurred.
The Eastern District of this court recently elaborated on the meaning of "tantamount to intentional wrongdoing," and we find the analysis in that case persuasive. Koon , 539 S.W.3d at 773-74. In Koon , the court held that there was sufficient evidence for the jury to award punitive damages against a doctor who failed to monitor a patient to whom he had prescribed increasingly high amounts of opioids. Id. The court explained that, "though [the doctor] may have had 'no specific intent to injure,' his awareness-from his knowledge of surrounding circumstances-that his conduct would probably result in injury demonstrates that his actions were 'tantamount to intentional wrongdoing.' " Id. at 773. Likewise, in the present case, the evidence, viewed most favorably to the Tubbses, supports a finding that BNSF was aware-from its knowledge of surrounding circumstances-that its conduct, coupled with the expectation of increased water flow, would probably result in collapse of the track embankment. Under Koon , that is enough to make BNSF's conduct "tantamount to intentional wrongdoing." And, under the Clarification Amendment, the fact that a collapse occurred and the Tubbses' farm was destroyed as a result exposes BNSF to punitive damages.
Accordingly, we conclude that the evidence was sufficient to permit the jury to conclude that BNSF acted with reckless indifference to, or conscious disregard for, its obligations under § 213.33 in circumstances that presented a high probability of harm. Thus, the trial court did not err in submitting the issue of punitive damages to the jury. Point II is denied.
3. The trial court did not err in rejecting BNSF's withdrawal instructions.
A. Standard of Review
"A trial court's refusal of a withdrawal instruction will not be reversed absent an abuse of discretion."
*344Wilson v. P.B. Patel, M.D., P.C. ,
B. Withdrawal Instruction Standard
"Trial courts have the discretion to give withdrawal instructions 'when evidence on an issue has been received, but there is inadequate proof given for final submission of the issue to the jury.' " Wilson ,
C. Withdrawal Instructions on Height and Design of Track
At trial, BNSF raised an objection to the Tubbses' arguments about the height of the track, arguing that the issue was preempted. The trial court overruled the objection but gave BNSF a standing objection to any inquiry about the track's height. Then, during the instruction conference, BNSF proposed the following withdrawal instructions about the height and design of the track structure:
Instruction No. C-The evidence of the height of Defendant's track or increases in height of Defendant's track is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
Instruction No. E-The design of Defendant's track structure is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
The court rejected these instructions. When the Tubbses' counsel raised arguments about the height of the track during his closing argument, BNSF renewed its objection on preemption grounds. This time, the trial court sustained BNSF's objection and told the Tubbses' counsel in a sidebar discussion: "And to correct this ..., I'm going to instruct you to explain [to the jury] that the pertinent issue is the drainage of the water." Counsel then turned to the jury and stated: "So I want to make sure that the complaint is not that they raised the track by 2 foot; that's not the issue. It's raising the track with no drainage; [they] didn't add one more foot of opening."
The verdict-directing instruction provided to the jury stated,
Your verdict must be for plaintiffs, if you believe:
*345First, defendants failed to maintain and keep free of obstruction each drainage or other water carrying facility under or immediately adjacent to the roadbed to accommodate expected water flow for the area concerned, and
Second, defendant was thereby negligent, and
Third, as a direct result of such negligence plaintiffs sustained damage.
None of the instructions given to the jury mentioned the height or design of the track.
We find that the trial court did not abuse its discretion in denying BNSF's Instruction No. C (height of BNSF's track) or Instruction No. E (design of BNSF's track structure). The Tubbses' claim of inadequate drainage is inextricably linked to increases in the height of the track. Proposed instructions C and E would have withdrawn evidence of the height and design of the track, but the height and design of the track were relevant to the Tubbses' claim that more drainage was needed to comply with § 213.33. The taller the track, the greater the damming effect of the embankment and, therefore, the greater the need for drainage. It would have been unreasonable to ask the jury to consider the Tubbses' claim without regard to any evidence of the increasing height of the track. And our review of the trial testimony revealed that, for the most part, when evidence about track height was presented, it was in conjunction with the lack of additional drainage.
Even if we were to determine from our review of the testimony that the jury could have been misled into thinking that the proper height and design of the track were issues for deliberation, counsel's statement about the pertinent issue being drainage, when coupled with the verdict-directing instruction, were sufficient to ensure that the jury would not be misled. Both counsel's statement and the verdict-directing instruction, which tracked the language of § 213.33, made clear to the jury that the issue for deliberation was drainage and not track height or design. Thus, the trial court properly exercised its discretion in rejecting BNSF's withdrawal instructions on track height and design. Point III is denied.
D. Withdrawal Instruction on Intentional Breach Theory
At trial, the Tubbses introduced an internal BNSF email indicating that the railroad had intentionally breached the embankment where the track ran along another farm to relieve pressure created by the floodwaters. However, all of the witnesses who testified on this issue, including the author of the email, stated that the intentional breach never occurred, and the Tubbses offered no other evidence to the contrary.
During the instruction conference, BNSF proposed the following withdrawal instruction:
Instruction No. A-Any evidence concerning intentional breach of the roadbed is withdrawn from the case and you are not to consider such evidence in arriving at your verdict.
The trial court rejected this instruction, but directed plaintiffs' counsel "to not argue intentional breach" in his closing statement. None of the instructions provided to the jury addressed the issue of intentional breach.
Although it would have been prudent for the trial court to give BNSF's withdrawal instruction on intentional breach, the court's decision to reject the instruction is not an abuse of discretion. "There is no abuse of discretion if reasonable persons could differ about the propriety *346of the trial court's decision." Stevens ,
Although the BNSF email about an intentional breach was admitted into evidence, every witness, including the Tubbses' expert, testified that no intentional breach occurred. The instructions given to the jury were consistent with the evidence. None of the instructions, including the verdict director, mentioned an intentional breach. And the Tubbses' counsel did not mention the intentional breach email in his closing argument. See Burton v. Phillips ,
Conclusion
Finding that the Tubbses made a submissible case on the standard of care under
Lisa White Hardwick and Edward R. Ardini, Jr., Judges, concur.
Thomas Tubbs sued individually and as Trustee of the Thomas Tubbs Revocable Trust, and Dana Tubbs sued individually and as Trustee of the Dana Lynn Tubbs Revocable Trust. For ease of reference, we refer to the Respondents collectively as "the Tubbses."
When reviewing the denial of a motion for judgment notwithstanding the verdict, we view the evidence and all reasonable inferences therefrom in the light most favorable to the jury's verdict. Fleshner v. Pepose Vision Inst., P.C. ,
The Tubbses voluntarily dismissed Massman Construction from the lawsuit shortly before trial.
All statutory references are to the United States Code (2012).
All regulatory references are to the Code of Federal Regulations (2018).
The Tubbses incorporated by reference their prior state-law claims in their Second Amended Petition to avoid any argument of waiver but they did so with the understanding that those claims had been dismissed.
BNSF raised an objection to the Tubbses' arguments about "the height" of the track, arguing that the "height of the track is a preempted issue." In response, the Tubbses argued that their claim was not that the height of the track constituted a design defect but rather that, pursuant to § 213.33, BNSF provided inadequate drainage under the roadbed and that the height of the track was relevant to the issue of adequate drainage. The trial court overruled the objection but gave BNSF a standing objection to all inquiries related to the height of the track.
On June 2, 2011, the Village of Big Lake filed for injunctive relief under state law alleging that BNSF had raised the track over the last fifteen years without suitable openings and without the Village's preapproval, which was required by ordinance. The trial court dismissed the Village's claims on federal preemption grounds, and this court affirmed. See Vill. of Big Lake v. BNSF Ry. Co. ,
The Tubbses amended their Petition to include a claim based on
As noted above, the STB determined that the Tubbses' state-law claims were preempted under the Interstate Commerce Commission Termination Act (ICCTA), and the Eighth Circuit denied their petition for review of the STB's decision. There are actually two federal preemption statutes that are potentially relevant here-the ICCTA and the Federal Railroad Safety Act (FRSA). Generally, the ICCTA provides the appropriate basis for analyzing whether a state law affecting rail transportation, including construction of tracks, is preempted by federal law. The FRSA provides the appropriate basis for analyzing whether a state law affecting rail safety is preempted. The ICCTA has a broader preemptive effect than the FRSA. Because the STB and the Eighth Circuit applied ICCTA preemption to the Tubbses' state-law claims and we are bound by their decisions, we do not address FRSA preemption here.
As the Tubbses point out, their negligence claim is authorized by
" 'Roadbed' is not defined in the regulations but the term commonly refers to the area under and adjacent to the tracks." Anderson v. Wis. Cent. Transp. Co. ,
Section 213.33 is part of Subpart B (Roadbed) of the FRSA regulations. Subpart B "prescribes minimum requirements for [the] roadbed and areas immediately adjacent to [the] roadbed."
In its opening brief, BNSF rejects the Tubbses' argument that a requirement to provide additional drainage is implied in § 213.33 by noting that the Federal Railroad Administration (FRA) cannot regulate through implication. In support of its argument, BNSF cites FCC v. Fox Television Stations, Inc. ,
While "area concerned" is not defined in the regulations, "it is clear that the 'area concerned,' specifically for safety purposes, is the railroad track and the track's roadbed." Miller v. Southeastern Pa. Transp. Auth. ,
For example, 49 C.F.R. Part 213, Subpart C (Track Geometry) prescribes requirements for the gage, alignment, and surface of track, and the elevation of outer rails, among other things.
In interpreting the meaning of § 213.33, BNSF asks us to consider an FRA opinion letter. On November 28, 2017, the FRA issued an opinion letter to BNSF concluding that
BNSF argues that it would be unreasonable to expect it to make changes to the structure of its embankment in the spring of 2011 based on information it learned that spring. As set out, supra , in concluding that there was sufficient evidence from which the jury could have found that BNSF violated its obligations under § 213.33, we do not rely on evidence of conditions unique to the spring of 2011. And, to the extent that we rely on actions BNSF considered taking at that time, we do so because they reflect the magnitude of the problem that existed related to BNSF's embankment and the fact that the railroad chose to make other structural changes to the track rather than adding drainage.
BNSF also cites Alcorn v. Union Pacific Railroad Company ,