DocketNumber: No. 49402
Citation Numbers: 712 S.W.2d 453
Judges: Gaertner, Smith, Snyder
Filed Date: 6/30/1986
Status: Precedential
Modified Date: 10/19/2024
Plaintiff sued defendant for breach of a commercial sales contract claiming defendant had refused to pay for paint plaintiff had delivered to defendant on open account. Defendant counterclaimed for damages, alleging some of the paint plaintiff had delivered was defective. A jury returned verdicts for plaintiff on the petition and on the counterclaim. The trial court, however, ordered a new trial on the counterclaim on the ground that the verdict for plaintiff was against the weight of the evidence. Plaintiff appeals from the order granting the new trial.
Under its contract with defendant plaintiff agreed to supply the type and quantity of paint defendant needed to perform a contract with the state to repaint a bridge that spans the Missouri River near Jefferson City. Painting the bridge entailed sandblasting the bridge’s steel superstructure, applying a primer coat of zinc paint to the bare steel, and sealing that coat with a coat of vinyl paint.
On August 22, 1974, a state inspector informed defendant that the zinc paint defendant’s laborers had been applying to the bridge for nearly two weeks did not meet contract specifications. What happened next is the subject of some dispute, but viewing the record in the light most favorable to defendant we find substantial evidence of the following: Because defendant could not proceed without zinc paint to prime the unprotected steel, it ceased operations until mid-September. During the latter half of September, defendant applied vinyl paint to the sections of the bridge it had primed with paint that had passed inspection. Defendant then spent October sandblasting sections of the bridge that had been primed with defective paint. In November defendant changed paint systems and had no further need for plaintiff’s products.
Plaintiff does not dispute, and the record before us supports, defendant’s claim that some of the paint plaintiff supplied defendant was defective. Nevertheless, plaintiff asserts the order granting defendant a new trial was error because defendant failed to produce substantial evidence that it suffered damages as a consequence of plaintiff’s breach.
Though the persuasive force of the testimony of defendant’s witnesses on the issue of damages is somewhat diminished by the witnesses’ digressions, we believe that a reasonable jury could conclude from their testimony that defendant suffered a loss.
What defendant’s witnesses essentially presented was a cash flow analysis of the bridge project from August 20 to November 1, 1974. That is, they detailed the expenses defendant incurred on the project during that ten-week period, deducted from those expenses defendant’s gross receipts from the state, and claimed the difference as damages. Plaintiff points out, correctly, that some of the expenses defendant detailed were neither incident to, nor a consequence of, plaintiff’s breach. Other of these expenses, however, clearly were, and defendant may recover for them.
A buyer's damages for breach in regard to accepted goods include consequential as well as incidental damages. Secs. 400.2-714—400.2-715, RSMo.1978. Consequential damages, particularly lost profit, are often difficult to ascertain. But where, as here, a certain amount of profit is figured into a bid on a project, damages are somewhat easier to ascertain.
Defendant bid $449,000.00 to paint the bridge. When the state accepted the bid, $449,000.00 became the contract price. The profit component of the contract price is the difference between the contract price and the cost to defendant of performance in accordance with contract specifications. The record shows that in order to perform in accordance with contract specifications in this case, defendant had to re-sandblast, re-prime, and re-seal sections of the bridge
The order granting defendant a new trial is affirmed and the cause remanded.
. Plaintiff lost a favorable judgment on defendant’s counterclaim when a new trial was ordered. Plaintiff is therefore an "aggrieved” party within the meaning of sec. 512.020, RSMo.