Citation Numbers: 33 Mo. App. 154, 1888 Mo. App. LEXIS 454
Judges: Rombauer
Filed Date: 12/11/1888
Status: Precedential
Modified Date: 10/19/2024
delivered the opinion of the court.
The defendant Harriet Beers, owner of certain hotel property in the city of St. Louis, being desirous of making extensive additions to her hotel, contracted in writing for their erection with the defendants Joab Strimple & Son. The contract bore date April 29, 1886, and provided among other things that the superintendent should be at liberty to make deviations from or alterations in the plan, form, construction and detail of execution, without invalidating the contract.
The plaintiff is a dealer in lumber. May 3, 1886, one of the Strimples called at plaintiff’s yard, presented
The plaintiff thereupon began to furnish the lumber required by Joab Strimple & Son, delivering it at the building from time to time as ordered, until August 31, 1886. In the early part of August, Joab Strimple, the senior member of the firm, absconded, leaving the work unfinished, and it was thereafter completed by the superintendent of the defendant Beers. Several orders for lumber were thereafter made upon plaintiff, which were partly signed by Page, foreman for the contractors, and partly by H. Strimple, the partner of Joab Strimple, who had absconded. The lumber upon these orders was delivered, like that upon former orders, on running account, and there was nothing to advise the plaintiff until after the last delivery on August 31 that the contract of Joab Strimple & Son for the erection of the structure had been cancelled, rescinded or abrogated in any manner.
The entire amount of lumber delivered by plaintiff to the contractors up to August 31,1886, amounted to $2,673.63. The contractors paid on account prior to that date $1,550.00, and had returned part of the lumber of the value of $20.18, leaving a balance of $1,103.45 due to the plaintiff, for which amount the plaintiff filed its lien claim against the building December 29; 1886, and the present action is prosecuted to enforce such lien claim.
The cause was tried by the court, without the intervention of a jury, and the plaintiff had judgment for $1,059.90, being the amount of its claim with interest,
Prom this judgment, Beers the owner appeals, assigning for error: (1) That the court admitted improper evidence; (2) that the court refused a proper declaration of law ; and (3) that the judgment is against the evidence.
The appellant complains that the court erroneously admitted in evidence a dray-ticket bearing date August 31, 1886, for five hundred feet clear poplar lumber and ninety-three feet assorted pine; that this item was the only item, as shown by the evidence, delivered within four months next preceding the filing of the lien claim, and if rejected, would necessarily have debarred the plaintiff from any recovery against the property.
We fail to find in the record that proof of this item was objected to specifically in any way. We even fail to see that the dray-ticket ever was offered in evidence. Proof of the item was clearly admissible against the contractor regardless of the fact whether the lumber entered into the construction of the building, because the plaintiff was bound to establish the extent of the contractors’ liability by evidence, notwithstanding the fact that they failed to answer, but made default.
The objection to the admission of the lien account in evidence is based on the grounds, that it was not shown by prior evidence that certain items therein contained were lienable items as against this property, and that the whole account was constructed on an erroneous theory, and was therefore not a just and true account.
As to the first ground of objection it will suffice to say that such an objection cannot be made effective by objecting to the account as a whole, and certainly not in a case like the present where the evidence is not clear and conclusive. Objection should be made to the specific items in the account, which are claimed to be
As to the second ground of objection it will suffice to say that the account is constructed on the only theory on which, in justice to all parties, it could be constructed, but that the real question in these cases is, not whether the account is artistically correct, but whether it is just and true.
The plaintiff, as above seen, had agreed to deliver a certain quantity of lumber for a certain price which was less than the aggregate market value of such lumber. Additions and deductions were to be at the same rate. In point of fact the contractors did not take all the lumber bid for, but took a good deal of additional lumber, which was charged to them at the rate of the original bid, and is so charged in the lien account filed. That the account thus filed contains a number of items which were in the original bid, b.ut for which no charge is made because they were never delivered, may be matter of surplusage, but does not deprive the account of its character of a just and true account. The objection on that ground is wholly without merit.
The defendants offered no evidence. At the close of the plaintiff’s case they requested the court to declare that under the pleadings and evidence the plaintiff was not entitled to recover a mechanic’s lien against the property sought to be charged, and this was the only declaration of law asked.
It is evident that if the plaintiff offered any evidence tending to show that it was entitled to a lien, then the instruction was properly refused. The defendants claim that the evidence fails to establish that the entire amount of the five hundred and ninety-three feet of lumber furnished August 31, entered into the construction of the building, and as the plaintiff adduced no evidence tending to show what part of such lumber did so enter and what part did not, the evidence presents
This claim is based upon a misconception of the law. It is the inseparable blending of items, for which the law gives no Pen. because they are not Penable in their nature, with Penable items which defeats the entire Pen claim and not the blending of Penable items, some of which remain unproved or unproved to their full extent. That distinction is clearly drawn in Johnson v. The Building Company, 23 Mo. App. 549, 550, and reiterated in Pullis v. Hoffman, 28 Mo. App. 671.
Conceding for the sake of argument that the plaintiff had failed to establish that all the lumber contained in the item of August 31, entered into the construction of the building, and had further failed to establish the exact amount of this particular item which entered into the construction of .the building, that of itself would not defeat its entire Pen claim, even though that item is the only one which draws the account within the statutory limitation. The fact that part of the item was so used still remains uncontroverted, and though plaintiff in the absence of definite proof may be entitled only to nominal damages, as against the owner, on account- of that particular item, the fact that' the entire indebtedness accrued within four months still remains established.
It will be thus seen that on any view of the evidence, the court was warranted in refusing the -declaration of law asked by the defendant owner. As no claim is made, either in the motion for new trial or in the assignment of error filed in this court, that the damages are excessive, we are not even called upon to examine the evidence to determine whether it is sufficient to warrant a finding for this whole item, amounting to $22.10, in favor of
Seeing no error in the record, we affirm the' ment.