Citation Numbers: 126 Mo. App. 366, 103 S.W. 585, 1907 Mo. App. LEXIS 413
Judges: Bland
Filed Date: 6/11/1907
Status: Precedential
Modified Date: 10/19/2024
(after stating the facts). — 1. Instruction numbered 1, given for plaintiff, is so indefinite and so involved as not to furnish the jury any guide to a correct verdict.. It correctly told the jury the price for the work in clearing the right -of way was fixed by the contract of June 3. It left, to the jury to determine how much of the- work on the right of way was completed by defendant and if not fully completed, why it was not fully completed. Defendant was doubtless inadvertently named where plaintiff was intended. But as the evidence shows defendant did complete part of the work, and that a part never was completed by any one, it is not probable the jury discovered the error and made the correct application. If the jury had found why the work was not completed by plaintiff, they would have had to go further and find what the legal consequences were, as the instruction did not tell them what they would be, and if they did not find the legal consequences, the fact that the work was not completed could
2. On the theory that defendant stopped the work, the second instruction is correct; but it seems to us the case urns tried on an erroneous theory. The petition alleges the work was done under the contract with defendant and alleges performance. The answer specifically denies performance and pleads a counterclaim for money paid plaintiff and for money paid out for completing the clearing of a part of the right of way. The reply alleges as an excuse for non-performance, the stoppage of the work by defendant. The case was tried on the theory that plaintiff had, as far as he had gone with the work, complied with the contract and was prevented from completing the work by defendant. It seems to us there is but one correct theory upon which the case can be properly tried, and that the pleadings admit of an application of this theory, to-wit, for work and labor done at the instance and request of defendant, the contracts, original and supplemental, furnishing the measure for the valuation of the work done.
For the errors herein noted, the judgment is reversed and the cause remanded.