DocketNumber: No. 12889
Citation Numbers: 166 Mont. 519, 536 P.2d 757, 1974 Mont. LEXIS 385
Filed Date: 12/24/1974
Status: Precedential
Modified Date: 10/19/2024
On October 23, 1974 plaintiffs, pursuant to Rule 40, Montana Rules of Appellate Civil Procedure, applied to this Court seeking reinstatement of an injunction which had been dissolved by the district court of Lewis and Clark County, pending appeal and final decision by this Court. The controversy here arose as follows:
•On June 14, 1974 plaintiffs instituted this action,' Civil Cause No. 37972 in the district court, by filing a complaint for declaratory judgment and injunction against defendant. Plaintiffs sought a ruling declaring defendant’s proposed 230 kilo-volt transmission line from Billings to Great Falls, Montana (the line), subject to the Montana Utility Siting Act of 1973, sections 70-801 to 70-823, R.C.M.1947, and an order temporarily restraining defendant from constructing the line. District. Judge Peter G. Meloy issued the temporary restraining order and set a show cause hearing on the matter.
On July 3, 1974 defendant answered the complaint stating the line was under construction prior to January 1, 1973 and therefore was specifically exempt from the Montana Utility Siting Act under section 70-811 of that Act. An evidentiary hearing was held the same day. The parties were given additional time to file further briefs.
On September 4, 1974 Judge Meloy found that the line was within the exception provided by section 70-811, R.C.M.1947, and concluded that the temporary restraining order should be dissolved. Accordingly, judgment in favor of defendant and against plaintiffs was entered on September 26, 1974.
On October 4, 1974 plaintiffs filed a notice of appeal and moved the district court under Rule 7(a), Montana Rules of Appellate Civil Procedure, to stay execution of the judgment. This motion was denied on October 7, 1974, whereupon plaintiffs made application to this Court.
The relief sought is therefore denied.