Citation Numbers: 70 S.E. 625, 154 N.C. 300, 1911 N.C. LEXIS 263
Judges: Hoke
Filed Date: 3/15/1911
Status: Precedential
Modified Date: 11/11/2024
Action, heard on exceptions to report of referee. There was evidence tending to show that on 16 September, 1907, plaintiff and defendant company had entered into a contract that plaintiff was to construct for defendant a trestle and fender over Contentnea Creek near Hookerton, N.C. the same to be built in a substantial and workmanlike manner and completed by 1 December, 1907; and defendant, on its part, agreed that it would furnish and supply "On board cars, or on ground within 300 feet of said trestle, all of the material to be used in the construction of said work, and same is to be furnished in such a manner and time as not to impede the said Brown in the performance of his part of the said contract." The work having been completed, the action was instituted to recover a balance alleged to be due plaintiff on the contract and also damages for failure to supply material in the time stipulated for in the contract. Defendant denied any and (302) all liability to plaintiff, and set up, further, a counterclaim for damages by reason of failure to do the work properly and according to the terms and stipulations of the contract. The case was referred, by consent, to Messrs. L. R. Varser and Thomas D. Warren and on the hearing before the referees there was evidence offered by the parties in support of their respective positions. Referees made their report to February Term, 1910, making very full findings of fact and holding for conclusions of law:
1. That there had been a failure on part of defendant to deliver material on time, causing damage.
2. That defendant was indebted to plaintiff in the sum of $1,334.90, balance due for the work and damages caused by wrongful delay on part of defendant.
3. There was nothing due defendants on counterclaim.
The court, on the hearing, overruled the defendant's exceptions, in all respects confirmed the report and gave judgment for the amount ascertained to be due, and defendant excepted and appealed.
The issue of indebtedness between these parties is dependent largely upon disputed questions of fact, and *Page 238
these having been resolved against defendant by the referees and on relevant testimony, and their findings having been affirmed by the trial court, there is very little left for our consideration. It has been uniformly held, with us, that in actions of this character "The findings of fact by a referee, supported by evidence and sustained by the trial court, are not reversible." Malloy v. Lincoln Mills,
Objection was made, first, to the conclusion on the part of the referees, that there had been a wrongful delay on the part of defendant (303) in the delivery of material, causing damage. This position predicated chiefly on the finding of fact No. 9, as follows: "That the plaintiff was at all times ready, able, and willing to perform the work in accordance with the terms of the contract, but was prevented from performing the same as required by the contract on account of the defendant's failure to furnish the material as agreed and on account of the defendant's delivering part of the material on the opposite side of a slough from the trestle or in a slough at such point, rendering it necessary for plaintiff to haul said material about one-half a mile to get it to the place of construction. And, taken in connection with the requirement of the contract, "That defendant agreed to deliver all material for the trestle on cars or on the ground and within 300 feet of the trestle, and same is to be furnished in such a manner and time as not to impede said Brown in the performance of his part of the contract," the ruling is clearly correct. In support of the finding, there was evidence on the part of plaintiff tending to show that a lot of heavy material was dumped on the ground about 300 feet from the trestle, in a direct line, but across a slough, which necessitated an additional haul of half a mile on part of plaintiff, causing delay and extra expense. There was no sufficient or satisfactory explanation offered as to the unloading of the material at such an inconvenient place. It is a principle well understood that in the interpretation of a deed or contract the intent of the parties, as embodied in the entire instrument, must prevail, "and each and every part must be given effect if it can be done by any fair and reasonable intendment. . . ." Davis v. Frazier,
It was further objected that in the damages assessed against defendant for wrongful delay, there was included an item of $75 charged as a rental at $2.50 per day for a floating pile driver belonging to plaintiff and kept idle for a period of 30 days, the exception being that, according to our decisions, the correct measure of damages was the interest on the value of the machine, which would have amounted, at most, to about $13, defendant referring more especially to the case of RockyMount Mills v. R. R.,
There was evidence on the part of plaintiff tending to show that the floating pile driver, in question, was an implement belonging to plaintiff, which could be and was not infrequently rented for a definite sum; that opportunity was presented to rent the machine in other (306) work, and that the time lost in its use was about 60 days, and a reasonable rental value for same was $10 per day. There was a finding of fact in accordance with the testimony, except that the time lost was fixed by the referees at 30 days and the net rental at $2.50 per day. On this finding we think the court below, approving the conclusions of the referees, correctly held that the rental value of the machine for the time the rent of same was lost afforded the correct basis for estimate, and that there is no error which gives defendant any just ground of complaint. The judgment will therefore be
Affirmed.
Cited: Jeffords v. Waterworks Co.,
Rocky Mount Mills v. Wilmington & Weldon Railroad , 119 N.C. 693 ( 1896 )
Patterson v. Greensboro Loan & Trust Co. , 157 N.C. 13 ( 1911 )
Sharpe v. Southern Railway Co. , 130 N.C. 613 ( 1902 )
Lumber Co. v. . Iron Works , 130 N.C. 584 ( 1902 )
Malloy v. Lincoln Cotton Mills , 132 N.C. 432 ( 1903 )
Lambertson v. Vann. , 134 N.C. 108 ( 1903 )
Dodds v. . Hakes , 23 N.Y. St. Rep. 192 ( 1889 )
Jeffords v. Albemarle Waterworks , 157 N.C. 10 ( 1911 )
Gulf States Creosoting Co. v. Loving , 120 F.2d 195 ( 1941 )
Troitino v. . Goodman , 225 N.C. 406 ( 1945 )
Thomas v. Carolina Wood Products Co. , 194 N.C. 729 ( 1927 )
Grand Trunk Western R. Co. v. HW Nelson Co. , 116 F.2d 823 ( 1941 )