DocketNumber: 80
Judges: Exum
Filed Date: 10/7/1975
Status: Precedential
Modified Date: 10/19/2024
Supreme Court of North Carolina.
*384 Mast, Tew & Nall, P. A. by Allen R. Tew, Clayton, for plaintiff.
No counsel contra.
EXUM, Justice.
The questions for decision are: (1) Whether plaintiff's claim of lien is fatally defective because of the erroneous statement of the date of first furnishing? (2) If not, whether the defect in any event precludes enforcement of the lien against defendants Korte? Both questions, we hold, are properly answered negatively.
Part 1, Article 2, Chapter 44A of our General Statutes provides for statutory liens on real property for mechanics, laborers and materialmen who deal with the owner of the property. Properly perfected liens "take effect from the time of the first furnishing of labor or materials .." N.C.Gen.Stat. 44A-10. Such liens are perfected by filing a claim of lien in the Clerk's office in the County where the real property is located "at any time after the maturity of the obligation secured thereby but not later than 120 days after the last furnishing of labor or materials ...." N.C.Gen. Stat. 44A-12(a)(b). The form for a claim of lien is prescribed by N.C.Gen.Stat. 44-12(c). This section provides that a claim of lien must "substantially" comport with the form set out. Item 5 of the form provides a place for furnishing the "[d]ate upon which labor or materials were first furnished upon said property by the claimant." Immediately following the prescribed form there is this provision: "A general description of the labor performed or materials furnished is sufficient. It is not necessary to file an itemized list or a detailed statement ...." N.C.Gen.Stat. 44A-12(c).
Because of an error in plaintiff's claim of lien whereby the date of first furnishing was given as being beyond the date of filing of the claim itself, both the trial court and the Court of Appeals were of the opinion that the claim of lien was fatally defective. The Court of Appeals reasoned:
"If laborers can file notices of lien stating an incorrect date of first furnishing and then enforce their liens with priority as of the actual date of first furnishing, it would be impossible for anyone to determine the priority of laborer's liens by a search of the records." 23 N.C.App. at 675-76, 209 S.E.2d at 513.
The Court of Appeals suggested also that it would be impossible to uphold the date actually given in the claim of lien.
*385 We disagree. First, we are not dealing here with priorities of competing liens nor with any party who relied on the claim of lien as filed. Second, the Court of Appeals seems to have assumed that if the lien were effective at all it would have to be effective either from the date of actual first furnishing or from the date of first furnishing as given in the claim of lien. There are other possibilities.
We agree with Judge Baley that the date of first furnishing "is an obvious clerical error which could not mislead any interested party." 23 N.C.App. at 676, 209 S.E.2d at 513. This is so because one whose interest in the property arose after the date this claim of lien was filed would be on notice not only that the stated date of first furnishing was obviously error but also that the first furnishing of labor and materials must have antedated the filing of the claim itself. The lien could then without prejudice be given effect at least as of the date of filing.
None of our cases deal with the precise point here involved. They were decided before the enactment of Chapter 44A under a statute which required that all claims of lien "shall be filed in detail, specifying the materials furnished or labor performed, and the time thereof." N.C.Gen.Stat. 44-38 and its predecessors. They also involve claims of lien defective in respects other than, and in some cases in addition to, an incorrect statement of the date of furnishing materials and labor. Lumber Co. v. Builders, 270 N.C. 337, 154 S.E.2d 665 (1967); Lowery v. Haithcock, 239 N.C. 67, 79 S.E.2d 204 (1953); Jefferson v. Bryant, 161 N.C. 404, 77 S.E. 341 (1913); Cook v. Cobb, 101 N.C. 68, 7 S.E. 700 (1888); Wray v. Harris, 77 N.C. 77 (1877). Our Court has, however, sustained the claim of lien when it was "a reasonable and substantial compliance with the statute." Cameron v. Lumber Co., 118 N.C. 266, 268, 24 S.E. 7, 7 (1896) ("No one need misunderstand it who should become interested in the property.")
Cases from other jurisdictions are more on point and instructive. Schwartz v. Lewis, 138 A.D. 566, 123 N.Y.S. 319 (Sup.Ct. App.Div.1910), was an action to foreclose a mechanic's lien. Claim of lien, filed April 18, 1908, stated that the first furnishing occurred October 24, 1907, and the last furnishing January 29, 1907. The New York lien statute required the dates of both first and last furnishings to be given. In fact, the last furnishing occurred January 29, 1908. The Court said:
"If by any fair construction the statement can be read so as to show the date intended, and that date is substantially correct, effect will be given to the notice." Id. at 568, 123 N.Y.S. at 320.
"The first item was furnished October 24, 1907. The lien was filed April 18, 1908. The last item must necessarily have been subsequent in point of time to the first, and prior in point of time to the filing.....We may therefore reject the year after January as surplusage which does not mislead anyone." (Emphasis supplied.) Id. at 568, 123 N.Y.S. at 321.
In Pearce v. Knapp, 71 Misc. 324, 127 N.Y.S. 1100 (Otsego County, 1911) claim of lien stated that the first work was performed April 20, 1910, and the last work about May 2, 1910; that the first item of material was furnished about May 20, 1910, and the last item about May 2, 1910. The court sustained the lien holding that the dates of furnishing materials were obviously transposed as could be ascertained by looking at the claim in its entirety. Robison v. Thatcher, 252 Or. 603, 451 P.2d 863 (1969) affirmed a decree foreclosing a mechanic's lien. The claim of lien stated in one place that the owner did not request some extra work involved and in another place stated that he did. The court held that such an internal inconsistency in the claim of lien caused by scrivener's error would not defeat an otherwise valid lien.
Having determined that the claim of lien is not fatally defective because of an obvious scrivener's error in stating the date *386 of first furnishing it is now necessary to decide whether the lien might in any event be enforced against defendants Korte who purchased before the claim was filed. If we assume the claim was filed within "120 days after the last furnishing of labor or materials", N.C.Gen.Stat. 44A-12(b), and the Kortes, consequently, purchased before the claim of lien was required to be filed, they were in effect charged with notice of the facts giving rise to the lien. "[I]t is entirely possible for a buyer of improved real estate to complete a purchase in the belief that the title is clean and then, a month or two later, to find himself faced with a lien filed by an unpaid workman hired by the former owner." Dale A. Whitman, "Transferring North Carolina Real Estate, Part I: How the Present System Functions." 49 N.C.L.Rev. 413, 441 (1971). Having constructive notice of the facts upon which the claim of lien is based, the Kortes may not take advantage of a scrivener's error in the claim relative to these facts and upon which they did not rely to defeat a lien which, because of these facts, relates back to a time that predates their purchase. N.C.Gen.Stat. 44A-10. Lumber Co. v. Trading Company, 163 N.C. 314, 79 S.E. 627 (1913); Miller v. Condit, 52 Minn. 455, 55 N.W. 47 (1893); Chapman v. Brewer, 43 Neb. 890, 62 N.W. 320 (1895); see also Georgia State Savings Assn. v. Marrs, 178 Ark. 18, 9 S.W.2d 785 (1928); Union Trust Co. v. Casserly, 127 Mich. 183, 86 N.W. 545 (1901).
In Lumber Co. v. Trading Company, supra, the Court had under consideration an early predecessor of the present lien statute which required that the claim of lien be filed within twelve months after completion of the work "provided, that as to the rights of a purchaser for value and without notice, the notice of lien must be filed within six months." Pell's Revisal of 1908, § 2028 (Supp.1911). The facts were that the claim of lien was filed less than twelve months but more than six months after completion of the work on the property in question. Purchaser bought the property before the claim of lien was filed but had actual notice that the lienor had a claim generally but not the amount nor the details thereof. This Court upheld the lien as against such a purchaser holding that the purchaser was not "without notice" of the lien within the meaning of the statute. The Court said, "[A]s to purchasers, that, `where one has notice of an opposing claim, he is put "upon inquiry," and is presumed to have notice of every fact which a proper inquiry would have enabled him to find out.'" 163 N.C. at 317, 79 S.E. at 629. In Miller receiver of a mechanic's lienor sought to foreclose the lien free from the mortgage of one Drexel. The actual first furnishing of labor was May 17, 1889, but the claim of lien stated it to be July 10, 1889. Drexel took his mortgage on June 1, 1889, having actual notice of the work being done which gave rise to the lien. The Minnesota court held that the lien was not invalid and since Drexel had actual notice of the work being done giving rise to the lien, the lien was effective as of May 17.
In Chapman mortgagees attempted to foreclose free from an asserted materialman's lien. Work giving rise to the lien had actually begun on November 5 or 7, 1889. On November 15 mortgages were executed and were recorded on November 21 and 27. On March 17, 1890, a claim of lien was filed stating that the first furnishing of materials occurred on December 30, 1889, and the last furnishing on January 25, 1890. The Nebraska court gave the materialman's lien priority over the mortgages. It said:
"The fact that the date of the commencement of labor or furnishing of material was stated to be December 30, 1889, when it should have been November 5th or 7th, could not and did not have any significance for or to mortgage lien holders, or in any manner affect their rights under the mortgages executed during the month of November at a time when the work and furnishing which were the foundation of the lien were in progress, and had been from a date prior to such *387 execution, as they were bound to take notice of these things, and their mortgages were taken subject to any rights of lien which had accrued or attached in favor of mechanics or material men. Their rights were acquired long prior to the time the statement was filed in which appeared the erroneous date, and such statement was not notice to them, nor could or were their liens or rights in any way affected by it; and the evidence of the true date was competent, and its reception in no manner or extent harmful or prejudicial to the parties holding the mortgages." 43 Neb. at 896-897, 62 N.W. at 322.
Although the Nebraska statute did not require the dates of performance to be stated in the claim of lien it did provide that the lien was effective as of the date of first furnishing. Consequently the court's reasoning with regard to the effect of an erroneously stated date of first furnishing on a mortgagee taking before the filing of the claim of lien applies to this aspect of the instant case.
It was, consequently, error for the Wake County District Court to dismiss with prejudice plaintiff's claim for relief against the Kortes and to discharge the claim of lien. The decision of the Court of Appeals affirming this order is, therefore, reversed and this case is remanded to that Court with instructions to remand it to the District Court of Wake County for further proceedings in accordance with this opinion.
Reversed and remanded.